Question

In: Computer Science

Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule...

Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule using either Microsoft Project or ProjectLibre.

Discipline

Activity

Effort

Planning

Set up work environment

2 days

Develop WBS and plan work

1 day

Analysis Activities

Meet with Community Board users

2 days

Meet with several agents

2 days

Define data

1 day

Model use cases

2 days

Design Activities

Design screen layouts

3 days

Design Database

1 day

Design use case processing

3 days

Build Activities

Build database

1 days

Write program code

8 days

Build test data

2 days

Set up for user test

1 days

Conduct acceptance test

2 days

Release first use cases

1/2 day

Do retrospective

1/2 day

Total Days

32 days = 6.5 weeks

Solutions

Expert Solution

1.) Create a New Project of any Name using MPP.

2.) Create New Task in that Project E.g. Here Discipline will go as Task.

3.) Create Sub-Task in the Parent Task. E.g. Here Activity will go as Sub-Task to Discipline.

4.) Put the Duration against each Task or Sub-Task defined here in Efforts.

5.) Save the file using .mpp extension.

6.) Now we can look over the Gantt Chart to know more about scheduling.


Related Solutions

Follow the UML diagram and directions on the attached file to create a RectangularPrism class and...
Follow the UML diagram and directions on the attached file to create a RectangularPrism class and a RectangularPrismDemo class. --------------------------------------------------------------------------------------------------------------------------------------- RectangularPrism            - length: double       - width: double       - height: double + RectangularPrism() + RectangularPrism(l:double,w:double, h:double) + setLength(l:double):void + setWidth(w:double):void + setHeight(h:double):void +getLength():double +getWidth():double +getHeight():double +getVolume():double +getSurfaceArea():double +toString():String --------------------------------------------------------------------------------------------------------------------- Create a RectangularPrism class in its own file based on the UML Create a separate RectangularPrismDemo Class file to demonstrate your class by doing the following: Create two prisms,...
Code and document the following functions using NON-RECURSIVE ITERATION only. Test the functions by calling them...
Code and document the following functions using NON-RECURSIVE ITERATION only. Test the functions by calling them from a simple interactive main() function using a menu, with different values used to select the choice of function. Overall, you should have one C program (call it Lab1.c) containing one main() function and 5 other functions, where the functions are called based on an interactive user menu. The program should contain a loop that permits users to enter a new choice of function...
Create a python code that calculates fixed point iteration method using a for loop.
Create a python code that calculates fixed point iteration method using a for loop.
Develop a table using the information provided in Attachment 1 (do not forget columns for rent...
Develop a table using the information provided in Attachment 1 (do not forget columns for rent and insurance). Provide totals for each expense category (e.g., salary) and for each month. Calculate the following: Average of the actual expenses incurred for each expenses category. Estimate to Complete (ETC). This is the amount you are forecasting will be spent for each of the expense categories for the remainder of the year. (Use the monthly average times the number of remaining months except...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity A to K is descried as follows: A with a duration of 2 month; B has immediate predecessor of A with total duration of 4 month; C has immediate predecessor of (A) with total duration of 2 month; (D) has immediate predecessor of B with total duration of 2month; (E) has immediate predecessor of B and C with total duration of 4 month; (F)...
In this project you will be provided a set of specifications to create an entity-relationship diagram...
In this project you will be provided a set of specifications to create an entity-relationship diagram and design accompanying table layout using sound relational modeling concepts and practices. The relationships between the entities and the attributes for the entities will be identified and described. This database will provide the foundation for the follow-on project. The following paragraphs provide the background and summary of the business requirements. You are a database consultant with Premier Software, LLC and have been assigned to...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries for September 2019 for your company. 2. Set up T-accounts and post your journal entries and adjusting entries to T-accounts. 3. Prepare your company’s pre-closing trial balance, as of September 30, 2019. 4. Prepare an income statement, in a good format, for the month of September 2019 for your company. 5. Prepare a statement of retained earnings, in a good format, for the same...
Consider the information provided in the following table. Using the additional information provided at the bottom,...
Consider the information provided in the following table. Using the additional information provided at the bottom, calculate the value of the firm using FCFF method.                                                           [15] Year 2019 2020 2021 2022 2023 2024 2025 Total Assets 10000 Fixed Assets 8000 Current assets 2000 Debt 4000 Equity 5000 Current liabilities 1000 Sales 15000 Operating expenses 12000 EBIT 3000 Int 400 PBT 2600 Tax(25%) 650 PAT 1950 For first five years, growth rate is sales in 5% and from sixth year...
Chapter 10 Assignment Complete inventory problems attached in the document. Complete questions using inventory formulas to...
Chapter 10 Assignment Complete inventory problems attached in the document. Complete questions using inventory formulas to find the solutions. Afterwards, use an excel spreadsheet to find the same answers. 1. An office supply store open 5 days a week must determine the best inventory policy for boxes of copier paper. Weekly demand is nearly constant at 250 boxes and when orders are placed, then entire shipment arrives at once. The cost per box is $22 and the inventory holding cost...
Using the scenario provided in the Milestone One Guidelines and Rubric document, prepare a brief summary...
Using the scenario provided in the Milestone One Guidelines and Rubric document, prepare a brief summary of the HCI (human–computer interface) and the IMD (information management database) of the distribution company, using appropriate IT terminology. Submit this as a Word document with supporting screenshots embedded in the document.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT