Question

In: Computer Science

Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule...

Develop an iteration schedule diagram using the information provided in the attached document. Create this schedule using either Microsoft Project or ProjectLibre.

Discipline

Activity

Effort

Planning

Set up work environment

2 days

Develop WBS and plan work

1 day

Analysis Activities

Meet with Community Board users

2 days

Meet with several agents

2 days

Define data

1 day

Model use cases

2 days

Design Activities

Design screen layouts

3 days

Design Database

1 day

Design use case processing

3 days

Build Activities

Build database

1 days

Write program code

8 days

Build test data

2 days

Set up for user test

1 days

Conduct acceptance test

2 days

Release first use cases

1/2 day

Do retrospective

1/2 day

Total Days

32 days = 6.5 weeks

Solutions

Expert Solution

1.) Create a New Project of any Name using MPP.

2.) Create New Task in that Project E.g. Here Discipline will go as Task.

3.) Create Sub-Task in the Parent Task. E.g. Here Activity will go as Sub-Task to Discipline.

4.) Put the Duration against each Task or Sub-Task defined here in Efforts.

5.) Save the file using .mpp extension.

6.) Now we can look over the Gantt Chart to know more about scheduling.


Related Solutions

Create a python code that calculates fixed point iteration method using a for loop.
Create a python code that calculates fixed point iteration method using a for loop.
Develop a table using the information provided in Attachment 1 (do not forget columns for rent...
Develop a table using the information provided in Attachment 1 (do not forget columns for rent and insurance). Provide totals for each expense category (e.g., salary) and for each month. Calculate the following: Average of the actual expenses incurred for each expenses category. Estimate to Complete (ETC). This is the amount you are forecasting will be spent for each of the expense categories for the remainder of the year. (Use the monthly average times the number of remaining months except...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity...
Activity network diagram is used to develop a work schedule for the facilities design effort. Activity A to K is descried as follows: A with a duration of 2 month; B has immediate predecessor of A with total duration of 4 month; C has immediate predecessor of (A) with total duration of 2 month; (D) has immediate predecessor of B with total duration of 2month; (E) has immediate predecessor of B and C with total duration of 4 month; (F)...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries...
Based on information given in the attached Excel document, 1. Prepare journal entries and adjusting entries for September 2019 for your company. 2. Set up T-accounts and post your journal entries and adjusting entries to T-accounts. 3. Prepare your company’s pre-closing trial balance, as of September 30, 2019. 4. Prepare an income statement, in a good format, for the month of September 2019 for your company. 5. Prepare a statement of retained earnings, in a good format, for the same...
Consider the information provided in the following table. Using the additional information provided at the bottom,...
Consider the information provided in the following table. Using the additional information provided at the bottom, calculate the value of the firm using FCFF method.                                                           [15] Year 2019 2020 2021 2022 2023 2024 2025 Total Assets 10000 Fixed Assets 8000 Current assets 2000 Debt 4000 Equity 5000 Current liabilities 1000 Sales 15000 Operating expenses 12000 EBIT 3000 Int 400 PBT 2600 Tax(25%) 650 PAT 1950 For first five years, growth rate is sales in 5% and from sixth year...
Using the scenario provided in the Milestone One Guidelines and Rubric document, prepare a brief summary...
Using the scenario provided in the Milestone One Guidelines and Rubric document, prepare a brief summary of the HCI (human–computer interface) and the IMD (information management database) of the distribution company, using appropriate IT terminology. Submit this as a Word document with supporting screenshots embedded in the document.
By using the WBS for contruscting a house, students will create a Network Diagram and Critical...
By using the WBS for contruscting a house, students will create a Network Diagram and Critical Path Analysis for the project. A network diagram is essentially a flow chart that includes all of the project elements and how they relate to one another. It depicts the sequence of activities in the project and also shows parallel activities and the links between each activity (PMBOK Guide). When outlined on a network diagram, the critical path is the longest path through the...
Using the provided network diagram, write a program in c ++ that finds the shortest path...
Using the provided network diagram, write a program in c ++ that finds the shortest path routing using the Bellman-Ford algorithm. Your program should represent the fact that your node is U. Show how the iterative process generates the routing table for your node. One of the keys to your program will be in determining when the iterative process is done. Deliverables 1. Provide an output that shows the routing table for your node after each iteration. Add a second...
Using the table function in a Microsoft Word Document, create a table which compares and contrasts...
Using the table function in a Microsoft Word Document, create a table which compares and contrasts the following payments systems: 1. RBRVS 2. RUG’S 3. APC’s Include in your comparison include at least the following elements Classification system(s) used (ICD-10-CM, ICD-10-PCS, CPT, etc.) Health care setting (Inpatient, outpatient, physician office, etc.). Examples of who uses the payment system (Medicare, Medicaid, commercial payers, etc.) Examples of data that is required for the payment system (principle diagnosis, principle procedure, discharge disposition, etc.)
Using the patient profile provided, develop and post an education plan for the patient based on...
Using the patient profile provided, develop and post an education plan for the patient based on their current health status. Include 2 short-term and 1 long-term goals for the patient and provide detailed education to the patient on how to meet these goals and maintain optimum health. Include information on follow-up care as well. A.R. is a 26-year-old male with a history of IV drug use. He has been clean and sober for 2 years. He was diagnosed as HIV...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT