Question

In: Operations Management

question 1 The following table provides a description for the project Z. Activity Duration Predecessor Cost...

question 1

The following table provides a description for the project Z.

Activity Duration Predecessor Cost to crash by 1 day Max Days to Crash
A 5 - $       300 1
B 3 - $       100 1
C 4 A $       100 1
D 3 A $       200 2
E 4 B $       400 3
F 2 D, E $       500 2
G 4 E $       300 3
H 3 C $       100 2

1. What is the critical path of this project?

2. What is the duration of this project? (before crashing)

3. If your task is to crash this project by 2 days, what is the most efficient cost of doing it? (Just input the number with no decimals or dollar signs

question 2

The expected duration of the project (average) is 30 days and variance is 16.

1. What is the probability that the project will be completed on day 32 or earlier?

2. Suppose the official deadline for the project is 34 days. What is the probability that the project will be delayed?

question 3

A restaurant has tracked the number of meals served at lunch over the last four weeks. The data show little in terms of trends, but do display substantial variation by day of the week. Use the following information to determine the seasonal (daily) indices for this restaurant.

Week

Day

1

2

3

4

Sunday

40

35

39

43

Monday

54

55

51

59

Tuesday

61

60

65

64

Wednesday

72

77

78

69

Thursday

89

80

81

79

Friday

91

90

99

95

Saturday

80

82

81

83

Solutions

Expert Solution

1. ALL POSSIBLE CHAINS

ACH = 12

ADF = 10

BEG = 11

BEF = 9

CRITICAL PATH = LONGEST PATH = ACH = 12

CRASHING

WE WILL CRASH FROM THE LOWEST CRASH PER PERIOD ACTIVITY THAT IS ON THE CRITICA PATH


ACTIVITY

NORMAL TIME

COST / PERIOD

TIMES CRASHED

# CRASH

CRASH COST

A

5

300

0

B

3

100

1

2ND

100

C

4

100

0

D

3

200

0

E

4

400

0

F

2

500

0

G

4

300

0

H

3

100

2

1ST AND 2ND

200


MOST EFFICIENT COST = 200 + 100 = 300

2. A. VARIANCE = 16

STANDARD DEVIATION = SQRT(VARIANCE) = SQRT(16) = 4

EXPECTED TIME = 30

DUE TIME = 32

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (32 - 30) / 4 = 0.5

PROBABILITY FOR A Z VALUE OF 0.5 = NORMSDIST(0.5) = 0.6915 OR 69.15%

B. VARIANCE = 16

STANDARD DEVIATION = SQRT(VARIANCE) = SQRT(16) = 4

EXPECTED TIME = 30

DUE TIME = 34

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (34 - 30) / 4 = 1

PROBABILITY FOR A Z VALUE OF 1 = NORMSDIST(1) = 0.8413

MORE THAN 34 = 1 - 0.8413 = 0.1587 OR 15.87%

3. AVERAGE OVERALL DEMAND = AVERAGE OF ALL DEMAND VALUES IN ALL SEASONS = 69.7143

AVERAGE PERIODIC DEMAND = SUM OF DEMAND IN A PARTICULAR PERIOD / N, WHERE N = NUMBER PERIODS TAKEN INTO CONSIDERATION

SEASONAL INDEX = AVERAGE PERIODIC DEMAND / AVERAGE DEMAND


PERIOD

AVG PERIOD DEMAND

AVG DEMAND

SEASONAL INDEX

1

40 + 35 + 39 + 43 / 4 = 38

69.7143

38 / 69.7143 = 0.545

2

54 + 55 + 51 + 59 / 4 = 53.3333

69.7143

53.3333 / 69.7143 = 0.765

3

61 + 60 + 65 + 64 / 4 = 62

69.7143

62 / 69.7143 = 0.889

4

72 + 77 + 78 + 69 / 4 = 75.6667

69.7143

75.6667 / 69.7143 = 1.085

5

89 + 80 + 81 + 79 / 4 = 83.3333

69.7143

83.3333 / 69.7143 = 1.195

6

91 + 90 + 99 + 95 / 4 = 93.3333

69.7143

93.3333 / 69.7143 = 1.339

7

80 + 82 + 81 + 83 / 4 = 81

69.7143

81 / 69.7143 = 1.162

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 1 1 B --- 1 1 C A,B 0.5 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". How much slack time (in days) does acitivity C have after leveling recources?
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 1 B --- 1 1 C A,B 1 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT