In: Operations Management
For the set of tasks given below, do the following:
Task | Task Time(seconds) |
Immediate Predecessor |
||
A | 45 | - | ||
B | 11 | A | ||
C | 9 | B | ||
D | 50 | - | ||
E | 26 | D | ||
F | 11 | E | ||
G | 12 | C | ||
H | 10 | C | ||
I | 9 | F, G, H | ||
J | 10 | I | ||
193 | ||||
b. Determine the minimum and maximum cycle times
in seconds for a desired output of 500 units in a seven-hour day.
(Round your answers to 1 decimal place.)
The minimum cycle time | seconds |
The maximum cycle time | seconds |
c. Determine the minimum number of workstations
for output of 500 units per day. (Round up your answer to
the next whole number.)
Minimum number of workstations
d. Balance the line using the greatest
positional weight heuristic. Break ties with the most
following tasks heuristic. Use a cycle time of 50
seconds.
Work stations | Following Tasks |
I | (Click to select) E B C A D |
II | (Click to select) D F C B A |
III | (Click to select) A C B, E, C B A, E, C |
IV | (Click to select) G F, A, G G, H G, F, H, I C |
V | (Click to select) J A B D C |
e. Calculate the percentage idle time for the line
using the 50 second cycle time. (Round your answer to 1
decimal place. Omit the "%" sign in your response.)
Percentage of idle time
%
B) Determine the maximum and minimum cycle times.
Maximum Cycle time = total time of completing al the task by single worker = total task time = 193 seconds
Minimum Cycle time = highest task time = 50 seconds of activity D
c) What is the minimum number of stations needed?
First determine desired cycle time for producing 500 unit per day in 7 hours per day
Demand = 500 units per day
Available time = 7 hours/day = 7*60*60 = 25200 seconds per day
Cycle time = Available time/Demand = 25200/500= 50.4 seconds per unit
Cycle time = 50.4 seconds per unit
Total work content =193 seconds
Theoretical number of workstation required = Total work content/Cycle time = 193/50.4 = 3.83
Minimum theoretical number of WS = 4 workstation
d)
a precedence diagram.
Determine Positional weights:
Start with extreme right task of the line. Positional weight for task is sum of the task’s time and the time of all following tasks.
TASK |
Calculation |
Positional Weights |
A |
=45+11+9+12+9+10+10 |
106 |
B |
=11+9+12+9+10+10 |
61 |
C |
=9+12+9+10+10 |
50 |
D |
=50+26+11+9+10 |
106 |
E |
=26+11+9+10 |
56 |
F |
=11+9+10 |
30 |
G |
=12+9+10 |
31 |
H |
=10+9+10 |
29 |
I |
=9+10 |
19 |
J |
10 |
10 |
Assignment of Tasks:
For the first workstation, select the task with highest positional weight, prerequisite that preceding task of the selected task is completed and the duration is less than the desired cycle time (C).
Obtain remaining time on the workstation by subtracting the cumulative assigned time from cycle time.
If remaining time becomes less than cycle time, move for next workstation. Repeat the procedure till all the tasks are assigned.
Station |
Cycle time Available |
Task |
Time (Seconds) |
Time left (Seconds) |
Ready tasks (positional wt) |
A(106),D(106) |
|||||
1 |
50 |
A (45) |
45 |
5 |
D(106),B(61) |
2 |
50 |
D (50) |
50 |
0 |
B(61),E(56) |
3 |
50 |
B (11) |
11 |
39 |
E(56),C(50) |
39 |
E (26) |
26 |
13 |
C(50),F(30) |
|
13 |
C (9) |
9 |
4 |
F(30),G(31),H(29) |
|
4 |
50 |
G (12) |
12 |
38 |
F(30),H(29) |
38 |
F (11) |
11 |
27 |
H(29) |
|
27 |
H (10) |
10 |
17 |
I(19) |
|
17 |
I (9) |
9 |
8 |
J(10) |
|
5 |
50 |
J (10) |
10 |
40 |
Assignments are as follows:
WS |
Task |
Total time |
Idle time |
1 |
A |
45 |
5 |
2 |
D |
50 |
0 |
3 |
B, E, C |
46 |
4 |
4 |
G, F, H, I |
42 |
8 |
5 |
J |
10 |
40 |
Total |
57 |
e.
Total idle time = 57
% of idle time = total Idle time/(cycle time x # of Workstations) x 100 = 57/(50 x 5) x 100
% of idle time = 22.8%