Question

In: Operations Management

For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

For the set of tasks given below, do the following:

Task Task
Time(seconds)
Immediate
Predecessor
A 45 -
B 11 A
C 9 B
D 50 -
E 26 D
F 11 E
G 12 C
H 10 C
I 9 F, G, H
J 10 I
193


b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)
  

The minimum cycle time seconds
The maximum cycle time seconds


c. Determine the minimum number of workstations for output of 500 units per day. (Round up your answer to the next whole number.)
  
Minimum number of workstations            

d. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.

Work stations Following Tasks
I (Click to select)  E  B  C  A  D
II (Click to select)  D  F  C  B  A
III (Click to select)  A  C  B, E, C  B  A, E, C
IV (Click to select)  G  F, A, G  G, H  G, F, H, I  C
V (Click to select)  J  A  B  D  C


e. Calculate the percentage idle time for the line using the 50 second cycle time. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)
  
Percentage of idle time             %

Solutions

Expert Solution

B) Determine the maximum and minimum cycle times.

Maximum Cycle time = total time of completing al the task by single worker = total task time = 193 seconds

Minimum Cycle time = highest task time = 50 seconds of activity D

c) What is the minimum number of stations needed?

First determine desired cycle time for producing 500 unit per day in 7 hours per day

Demand = 500 units per day

Available time = 7 hours/day = 7*60*60 = 25200 seconds per day

Cycle time = Available time/Demand = 25200/500= 50.4 seconds per unit

Cycle time = 50.4 seconds per unit

Total work content =193 seconds

Theoretical number of workstation required = Total work content/Cycle time = 193/50.4 = 3.83

Minimum theoretical number of WS = 4 workstation

d)

a precedence diagram.

Determine Positional weights:

Start with extreme right task of the line. Positional weight for task is sum of the task’s time and the time of all following tasks.

TASK

Calculation

Positional Weights

A

=45+11+9+12+9+10+10

106

B

=11+9+12+9+10+10

61

C

=9+12+9+10+10

50

D

=50+26+11+9+10

106

E

=26+11+9+10

56

F

=11+9+10

30

G

=12+9+10

31

H

=10+9+10

29

I

=9+10

19

J

10

10

Assignment of Tasks:

For the first workstation, select the task with highest positional weight, prerequisite that preceding task of the selected task is completed and the duration is less than the desired cycle time (C).

Obtain remaining time on the workstation by subtracting the cumulative assigned time from cycle time.

If remaining time becomes less than cycle time, move for next workstation. Repeat the procedure till all the tasks are assigned.

Station

Cycle time Available

Task

Time (Seconds)

Time left (Seconds)

Ready tasks (positional wt)

A(106),D(106)

1

50

A (45)

45

5

D(106),B(61)

2

50

D (50)

50

0

B(61),E(56)

3

50

B (11)

11

39

E(56),C(50)

39

E (26)

26

13

C(50),F(30)

13

C (9)

9

4

F(30),G(31),H(29)

4

50

G (12)

12

38

F(30),H(29)

38

F (11)

11

27

H(29)

27

H (10)

10

17

I(19)

17

I (9)

9

8

J(10)

5

50

J (10)

10

40

Assignments are as follows:

WS

Task

Total time

Idle time

1

A

45

5

2

D

50

0

3

B, E, C

46

4

4

G, F, H, I

42

8

5

J

10

40

Total

57

e.

Total idle time = 57

% of idle time = total Idle time/(cycle time x # of Workstations) x 100 = 57/(50 x 5) x 100

% of idle time = 22.8%


Related Solutions

Task Task Time (seconds) Tasks that must Precede A 50 -- B 40 -- C 20...
Task Task Time (seconds) Tasks that must Precede A 50 -- B 40 -- C 20 A D 45 C E 20 C F 25 D G 10 E H 35 B,F,G The above tasks must be performed on an assembly line in the sequence and times specified. The workstation cycle time is 72 seconds. Using the longest task time to balance the assembly line, the first workstation include, the second workstation include , the third workstation include , and...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s)...
Time​ (days) Immediate Time​ (days) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 55 55 77 long dash— H 44 44 66 ​E, F B 11 22 55 long dash— I 22 77 1010 ​G, H C 55 55 55 A J 22 44 77 I D 44 88 1313 A K 66 1010 1313 I E 11 1010 1717 ​B, C L 22 66 66 J F 11 55 77 D M 22 22 33...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time...
Information on a project’s activities is shown in the following table: Activity Immediate Predecessor Activity Time (wks) Total Budgeted Cost A - 4 24,000 B - 3 27,000 C B 2 14,000 D A 8 32,000 E D 3 24,000 F C, E 4 60,000 G D 6 30,000 H F 6 30,000 I G 4 20,000 J G, H 3 18,000 K I 2 10,000 L J 4 16,000 Create a Gantt chart based on earliest start times. (20...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
Based upon the following tasks, durations and predecessor relationships which of the following tasks is not...
Based upon the following tasks, durations and predecessor relationships which of the following tasks is not critical? 1, 10, N/A; 2,8,1; 3,5, 1; 4, 9, 1; 5, 6, 3; 6, 6, 2; 7, 11, 5; 8, 10, 6; 9, 9, 4; 10, 7, 9; 11, 10,( 7,8,10); a. 4 b. 9 c. 6 d. 10
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk...
a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack A 5 - 4 $50 B 3 - 2 $10 C 6 A 3 $2,500 D 3 A 1 $10 E 8 C,B 7 $200 F 3 D,E 1 $1,000 G 4 F 4 - Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk ES EF LS LF Slack Critical (Y/N) Free Slack A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B, D 3 F D 4 G E F 6 a. Draw the network (20 points) b. What is the critical path? c. How many weeks will it take to complete the project ? d. Identify the early start, early finish, late start, and late finish for each activity...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT