Based upon the following tasks, durations and predecessor relationships which of the following tasks is not critical? 1, 10, N/A; 2,8,1; 3,5, 1; 4, 9, 1; 5, 6, 3; 6, 6, 2; 7, 11, 5; 8, 10, 6; 9, 9, 4; 10, 7, 9; 11, 10,( 7,8,10);
a. 4
b. 9
c. 6
d. 10
Drawing a relationship diagram of the activities we see that activity 1 is the start and activity 11 is the end activity. And there are 3 paths between the start and end. The longest path among the three paths will be critical.
Path (i) - 2-6-8 = 8days + 6days + 10days = 24days
Path (ii) - 3-5-7 = 5days + 6days + 11days = 22days
Path (iii) - 4-9-10 = 9days + 9days + 7days = 25days (longest of the three paths and critical)
Therefore critical activities are 1-4-9-10-11.
Hence 6 is the only non-critical activity, among the options.
ANS: c. 6
Alternatively, network analysis can be done to find the required non-critical activity.
6 is a non- critical activity.
ANS: c. 6