In: Operations Management
a)Fill in the network diagram below
Task |
Time (wk) |
Predecessor |
Min Time with Crashing |
Crashing cost/wk |
ES |
EF |
LS |
LF |
Slack |
Critical (Y/N) |
Free Slack |
A |
5 |
- |
4 |
$50 |
|||||||
B |
3 |
- |
2 |
$10 |
|||||||
C |
6 |
A |
3 |
$2,500 |
|||||||
D |
3 |
A |
1 |
$10 |
|||||||
E |
8 |
C,B |
7 |
$200 |
|||||||
F |
3 |
D,E |
1 |
$1,000 |
|||||||
G |
4 |
F |
4 |
- |
|||||||
Task |
Time (wk) |
Predecessor |
Min Time with Crashing |
Crashing cost/wk |
ES |
EF |
LS |
LF |
Slack |
Critical (Y/N) |
Free Slack |
A |
5 |
- |
4 |
$50 |
|||||||
B |
3 |
- |
2 |
$10 |
|||||||
C |
6 |
A |
3 |
$2,500 |
|||||||
D |
3 |
A |
1 |
$10 |
|||||||
E |
8 |
C,B |
7 |
$200 |
|||||||
F |
3 |
D,E |
1 |
$1,000 |
|||||||
G |
4 |
F |
4 |
- |
b-Clearly List your critical path
c-What is the shortest time need to complete the project (without expediting)?
d-To expedite the project by two weeks, which activities will you crash? Crashing cost?
Answer:
a.
b. Critical Path: A-C-E-F-G
c. 26 weeks
Shortest time to complete project is 26 weeks. (Earliest Finish time of Activity G - Last activity on critical path)
d. A,E. Cost: $250
To reduce the project duration, we need to crash the activities on critical path.
Activity A has the lowest crashing cost among all activities on critical path. Max possible crashing is 1 week.
Activity E has the 2nd lowest crashing cost among all activities on critical path. Max possible crashing is 1 week.
Crash the Activities A and E by 1 week to reduce the project duration by 2 weeks.
Crashing Cost = Crashing Cost of A + Crashing Cost of E = 50 +200 = $250