Question

In: Operations Management

a)Fill in the network diagram below Task Time (wk) Predecessor Min Time with Crashing Crashing cost/wk...

a)Fill in the network diagram below

Task

Time (wk)

Predecessor

Min Time with Crashing

Crashing cost/wk

ES

EF

LS

LF

Slack

Critical (Y/N)

Free Slack

A

5

-

4

$50

B

3

-

2

$10

C

6

A

3

$2,500

D

3

A

1

$10

E

8

C,B

7

$200

F

3

D,E

1

$1,000

G

4

F

4

-

Task

Time (wk)

Predecessor

Min Time with Crashing

Crashing cost/wk

ES

EF

LS

LF

Slack

Critical (Y/N)

Free Slack

A

5

-

4

$50

B

3

-

2

$10

C

6

A

3

$2,500

D

3

A

1

$10

E

8

C,B

7

$200

F

3

D,E

1

$1,000

G

4

F

4

-

b-Clearly List your critical path

c-What is the shortest time need to complete the project (without expediting)?

d-To expedite the project by two weeks, which activities will you crash? Crashing cost?

Solutions

Expert Solution

Answer:

a.

b. Critical Path: A-C-E-F-G

c. 26 weeks

Shortest time to complete project is 26 weeks. (Earliest Finish time of Activity G - Last activity on critical path)

d. A,E. Cost: $250

To reduce the project duration, we need to crash the activities on critical path.

Activity A has the lowest crashing cost among all activities on critical path. Max possible crashing is 1 week.

Activity E has the 2nd lowest crashing cost among all activities on critical path. Max possible crashing is 1 week.

Crash the Activities A and E by 1 week to reduce the project duration by 2 weeks.

Crashing Cost = Crashing Cost of A + Crashing Cost of E = 50 +200 = $250


Related Solutions

For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A ---...
1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to the above information. Using a table format, identify the critical path. What is the project completion time?
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Age   Browsing Time (min/wk) 34   372 48   198 24   469 33   387 43   262 58   85...
Age   Browsing Time (min/wk) 34   372 48   198 24   469 33   387 43   262 58   85 20   469 49   192 64   86 55   119 46   233 36   345 35   357 29   415 37   327 ​d) Check the residuals to see if the conditions for inference are met. The equal spread condition IS/IS NOT satisfied because the scatterplot of the residuals against the predicted values shows NO PATTERN/A THICKENING OF THE SPREAD/A THINNING OF THE SPREAD/A CURVATURE. .The nearly normal condition...
Create Gantt Chart and network Diagram Task Precedes Optimistic MostLikely Pessimistic Norm$ CrashTime Crash$ A D...
Create Gantt Chart and network Diagram Task Precedes Optimistic MostLikely Pessimistic Norm$ CrashTime Crash$ A D 4 4 4 1000 3 1301 B E 2 3 28 1391 4 2000 C F 2 4 12 2000 4 2713 D G 2 3 22 1198 5 1400 E G 1 4 7 899 3 1100 F H 7 10 19 2500 6 3765 G H 1 3 11 792 3 1450 H none 2 2 8 300 1 504
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For...
1. A precedence diagram is shown below. Solve the network for the basic scheduling information. For each activity, show the computed value of early start, early finish, late start, late finish, total float, and free float.   Activity Duration mobilize 1 remove siding 4 excavate/form slab 7 place slab 4 set support beam 1 stud wall up 6 install siding 4 install windows 5 set raffers 4 install roof 6 finish trim 4 paint siding 7 move out 1
Consider the cost of assigning a task to an individual as shown in the table below....
Consider the cost of assigning a task to an individual as shown in the table below. It is assumed that each individual can be assigned to at most one task, and each task can be assigned to at most one individual. The objective is to minimize the cost of assignments. individual Task 1 2 3 1 17 18 16 2 14 19 17 3 15 19 18 (a) Write down the linear programming formulation of this problem. (i.e., write down...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation;...
Draw a network diagram and answer the questions below: (Please show all your workings or explanation; simple answers alone will not account for full marks) • Activity 1 can start immediately and has an estimated duration of three weeks. • Activity 2 can start after activity 1 is completed and has an estimated duration of three weeks. • Activity 3 can start after activity 1 is completed and has an estimated duration of six weeks. • Activity 4 can start...
Listed below are time intervals​ (min) between eruptions of a geyser. Assume that the​ "recent" times...
Listed below are time intervals​ (min) between eruptions of a geyser. Assume that the​ "recent" times are within the past few​ years, the​ "past" times are from around 20 years​ ago, and that the two samples are independent simple random samples selected from normally distributed populations. Do not assume that the population standard deviations are equal. Does it appear that the mean time interval has​ changed? Is the conclusion affected by whether the significance level is 0.10 or 0.01​? Recent...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT