Questions
A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with...

A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with a straight blade. The material (dry and noncohesive) weighs 98 pcf in the bank state. It is estimated the material will swell 6%, from bank to loose state. The center-of mass-to-center-of-mass pushing distance is 200 ft. Job efficiency can be assumed to be equivalent to a 45-min hour. Calculate the production in bey per hour and the direct cost of the proposed earthmoving operation in dollars per bey. The company's normal O&O cost for these machines is $95 per hour and the operator's wage is $15.00 per hour plus 40% for fringes, insurance, and worker's compensation.

In: Civil Engineering

Give design criteria or basis for designing a foundation project

Give design criteria or basis for designing a foundation project

In: Civil Engineering

write the importance of initial setting time of cement in various operation of making cement mortar...

write the importance of initial setting time of cement in various operation of making cement mortar and cement concrete

In: Civil Engineering

Compare Mild Steel & High tensile steel used in the construction industry

Compare Mild Steel & High tensile steel used in the construction industry

In: Civil Engineering

A highway contractor has opened a cut in fine silty sand (SM). Because of the cut...

A highway contractor has opened a cut in fine silty sand (SM). Because of the cut location and lack of drainage, surface water has drained into the cut, leaving the material very wet. Rubber-tired scrapers are hauling material from the cut to an adjacent fill. The material is being placed in the fill in 20 to 25cm lifts and compacted by heavy sheep foot roller towed by a crawler tractor. It is apparent that the specified compaction (95% of standard AASHTO density) is not being attained. The sheep foot roller not “walking out and scraper tires are causing the compaction problem? What would you suggest to the constructor to improve the compaction process? Ideally, concrete should be poured at temperatures between 16°C and 38°C.

In: Civil Engineering

Discuss the strategic considerations for MRT decisions with respect to planning, finance, management and pricing. Transportation...

Discuss the strategic considerations for MRT decisions with respect to planning, finance, management and pricing.

Transportation Engineering
urgent !
pls do answer correctly !!

No additional information.
The question is complete !

In: Civil Engineering

Determine the size of a square footing at the ground level to transmit a load of...

Determine the size of a square footing at the ground level to transmit a load of 900 kN in sand
weighing 18 kN/m3
and having an angle of shearing resistance of 36° (Nγ = 46, Nq = 43). Factor of safety is 3.
What will be the modification in the result, if the footing may be placed at a depth of 1 m below ground
surface ? Assume, in this case, the water table may rise to the ground surface. γ′ = 9 kN/m3
.

In: Civil Engineering

describe the difference between yield stress and ultimate stress of a steel element

describe the difference between yield stress and ultimate stress of a steel element

In: Civil Engineering

A three-storey building is to be constructed on a sand beach. Ground water rises to a...

A three-storey building is to be constructed on a sand beach. Ground water rises to a maximum
of 3 m below ground level. The beach sand has the following properties: γd = 17.5 kN/m3
, φ = 32° (Nc = 40,
Nq = 25, Nγ = 30). The maximum column load will be 700 kN. Determine the sizes of footing for depths of 1
m and 2 m using a factor of safety of 3. Settlement are not to be considered. Evaluate the two alternatives
from practical consideration (difficulties of construction and cost).

In: Civil Engineering

Discuss the various types of foundations and their selection with respect to different situations.

Discuss the various types of foundations and their selection with respect to different situations.

In: Civil Engineering

Why is grit removal important as a procedure in wastewater plants?If conventional grit removal systems are...

Why is grit removal important as a procedure in wastewater plants?If conventional grit removal systems are designed to remove particles larger than 0.210 mm and specific gravity of 2.65, why are particles this size and larger often found downstream? Explain.

In chemical disinfection of drinking water,what is breakpoint chlorination? Explain.

In: Civil Engineering

A high water-table was encountered in low-fine content soil during the excavation. This may endanger slope...

A high water-table was encountered in low-fine content soil during the excavation. This may endanger slope stability and result in an accident. Suggest the most suitable groundwater control technique to prevent this accident and explain its details

In: Civil Engineering

Suggest the most suitable piling technique used for sandy soil encountered at the worksite. Explain the...

Suggest the most suitable piling technique used for sandy soil encountered at the worksite. Explain the pile erection procedure step by step.

In: Civil Engineering

Situation: The town of Waterville has the following past population data projected beyond 1990. Year                ...

Situation: The town of Waterville has the following past population data projected beyond 1990.

Year                 1900    1910    1920    1930    1940    1950    1960    1970    1980    1990   

Population       10,240 12,150 18,430 26210 22,480 32.410 45,050 57,200 64,030 77,320

The average water consumption (including every possible sector) is 160 gal/cap-day in 2005. The town has a wastewater treatment plant (WWTP) with a treatment capacity of 20 MGD. Due to the rapid growth of the population, the town is planning to build a new WWTP assuming that the old WWTP will not be used any more after the new WWTP is operating.

Requirements: You are hired by the town as an engineer to do the planning. You need to (1) estimate the future populations using any reasonable method; (2) estimate the future wastewater generation rate (e.g., in the units of gal/cap-day); (3) estimate the initial year and design year of the new WWTP; (4) the average, maximum, and minimum daily and hourly flow rates for the initial and design year under both dry and wet weather conditions; (5) assume that the wastewater generated by the town is of medium strength, estimate the BOD5, COD, SS, VSS, TKN, Total P, and alkalinity (as CaCO3) in the raw wastewater to be treated by the new treatment plan.

In: Civil Engineering

The complexity of construction projects stems from different types of projects, the many stake holders, the...

The complexity of construction projects stems from different types of projects, the many stake holders, the different delivery approaches, and different contracts to carry out the projects. please discuss this statement.

In: Civil Engineering