Question

In: Civil Engineering

Select four (4) large projects (local or international) and carry out the following: i. Suggest the...

Select four (4) large projects (local or international) and carry out the following:
i. Suggest the most suitable (unique for each one) forms of contract for them.
ii. Provide a brief description for why each of the form of contracts is suitable for
the projects.
iii. Describe one (1) advantage for using each of the form of contracts for the projects.
iv. Describe one (1) disadvantage for using each of the form of contracts for the
projects.

Solutions

Expert Solution

i) Let us consider the 4 different projects as Constructing a highway, constructing a dam, building a railway line and maintaining or repairing a pavement

1) Constructing a highway - Target Cost Construction Contract

2) Constructing a dam - Cost Plus profitContract

3) Building a railway line -  Unit Price Construction Contract

4) Maintaining or repairing a pavement - Lump sum contract

ii) Constructing a highway has its target price as an important criterion: A contractor herein is asked to construct the road within a targeted cost. Constructing a dam requires a lot of material and labor, which is calculated and over it a certain percentage of profit usually 10% is given to the contractor. Building a railway line is done by unit price contract because payment to the contractor is made based on a unit item completed i.e. per miles of the railway line. This can also be applied to road construction. Maintaining or repairing a pavement is a pitty work for which the contractor is paid a fixed lump sum amount.

iii) advantages :

1) Target cost contract has common features of the lump sum and cost-plus contracts. The contractor is paid based on the actual costs plus a certain fee either fixed or percentage of total cost in case the cost of the project doesn’t exceed certain target cost specified by the owner. The contractor has also rewarded a percentage of any savings between target and actual cost.

2) There is no risk of loss arising from changing prices, wrong estimates, and underestimated quotation and all agreed costs are recovered in cost plus profit contract.

3) In unit price contract the contractor is paid based on the actual cost of the project, including direct and indirect costs, plus a specific fee. This fee could be a fixed fee or percentage of costs.

4) Lump-sum Contract - In this type, the contractor bids a single fixed price for overall activities in the project scope.

iv) Disadvantages :

1)In target cost contract there is a risk carried by the contractor in case of an increase in the cost of construction projects.

2) advantage on account of the favorable market price is denied and The profit earned is usually low

3) There are no incentives for the early finish in the unit price contract.

4)In the lump sum contract, all risks are assigned to the contractor, and there isn’t any risk carried by the owner. The contractor has an incentive in this contract as he is rewarded for an early finish, and there is a penalty for a late finish.


Related Solutions

Select four (4) large projects (local or international) and carry out the following: i. Suggest the...
Select four (4) large projects (local or international) and carry out the following: i. Suggest the most suitable (unique for each one) forms of contract for them. ii. Provide a brief description for why each of the form of contracts is suitable for the projects. iii. Describe one (1) advantage for using each of the form of contracts for the projects. iv. Describe one (1) disadvantage for using each of the form of contracts for the projects.
A large company has the opportunity to select one of four projects: A, B, C, D,...
A large company has the opportunity to select one of four projects: A, B, C, D, or the null (Do nothing) alternative. Each project requires a single initial investment as shown in the table below. Information on each alternative was fed into a computer program that calculated the IRR for each project as well as the pertinent incremental IRR(s) as shown in the table below. Project Initial Investment Project IRR Incremental Rate of Return of “Row” – “Column” Null A...
John is planning to carry out projects in any of the following: Timber (T), Air Conditioners...
John is planning to carry out projects in any of the following: Timber (T), Air Conditioners (A), Car Sales (C) and Horticulture (H). Experience has shown that the three states of nature prevailing are: Poor (P), Stable (S) and Good (G) economic conditions. The payoff table below shows the most likely returns of each investment type under each state of nature. The values are millions of Pula and the probabilities are supplied for each state of nature. P S G...
I have been requested to carry out a journal review on the following: " Explain what...
I have been requested to carry out a journal review on the following: " Explain what corporate goals provides the primary objective for the most financial decisions" I tried to search in the university online library and found a few articles related to profit and shareholder wealth maximization but I don't seem to know how to approach this question actually through literature review. Appreciate some advise on how to start with this, thank you
Determine the individuals who carry out contact investigations, or partner notification for STD’s at the local...
Determine the individuals who carry out contact investigations, or partner notification for STD’s at the local health department (by interview or web search). How do they contact a person who is less than 18 years of age? What strategies do they use to bring the contact in for treatment? How do they maintain confidentiality? References should be included at the end of the answer and in a reference page for complete credit
Energy projects are usually large and impact local labor markets. Suppose a large energy project is...
Energy projects are usually large and impact local labor markets. Suppose a large energy project is being implemented in North-East of Edmonton which will employ approximately 10,000 individuals in the construction phase during the first two years and then 1,500 people in its operation stage after construction. What impact do you expect this project to have on the labor market in Edmonton during the construction phase? Explain. What impact do you expect this project to have on the labor market...
State four (4) possible causes each of the following troubles in dc motor and suggest two...
State four (4) possible causes each of the following troubles in dc motor and suggest two solutions to avert them: (i) sparking at brushes, and (ii) overheating.
A company compare between 4 projects. Use the following information to evaluate and select the adequate...
A company compare between 4 projects. Use the following information to evaluate and select the adequate project using: Net Present Value NPV. Profitability Index. Internal Rate of Return IRR Modified Internal Rate of Return MIRR Projects P1 P2 P3 P4 Cost 100000 150000 200000 250000 Cash in 20000 25000 30000 80000 Life(years) 7 9 10 7     Cost of capital 10%.
I work for a local company that does not take part in international trade. Should I...
I work for a local company that does not take part in international trade. Should I write my paper on the "what if" approach? Question: Describe how a change in the exchange rate affected your firm. Explain what happened to your price and quantity. Howcan you profit fromfuture shifts in the exchange rate? How do you predict future changes in the exchange rate?
The Federal Reserve has the power to __________________. Note: Please select two correct answers. carry out...
The Federal Reserve has the power to __________________. Note: Please select two correct answers. carry out monetary policy through open market operations lend money directly to its member commercial banks act as a lender of first resort open checking and savings accounts for individuals
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT