1. What is the difference betw een direct and indirect site characterization methods? 2. Give an example of direct measurement method? 3. Give an example of indirect measurement method?
In: Civil Engineering
I DOWNVOTE for incorrect answers.
Explain the helicoidal flow theory required.
In: Civil Engineering
In: Civil Engineering
1.Describe the four stages to Project Life Cycle. Discuss in your own words the key documents likely to be utilized by the PM for each stage. Provide a template as an example for each one.
In: Civil Engineering
As a consultant you are need to solve these problems and need to suggest (with explanation) suitable method to install the pile.
In: Civil Engineering
bridge components description and painting with some details
In: Civil Engineering
A natural soil slope failed overnight after experiencing several days of rainfall. The rain continued even after the slope failure. The shape of the failure resembled a spoon (i.e., circular failure). You are the consulting engineer hired, please answer the following questions:
i. In order to confirm the stability of the slope prior to the rainfall induced failure (when it was stable), what Shear Strength parameters you will likely use in this calculation? Why?
ii. In order to explain the slope failure, i.e., for your slope stability model of the slope at failure, what Shear strength parameters will you likely use in this calculation? Why?
In: Civil Engineering
In: Civil Engineering
PLEASE SOLVE ALL
In: Civil Engineering
Provide cost analysis and decide on the cheapest design concept of a bridge.
In: Civil Engineering
In: Civil Engineering
a) What is the primary difference between the dependent variable of an OLS regression model and a logit model?
b) What is the primary difference between the model results of an OLS regression model and a logit model?
In: Civil Engineering
part 1) A deep excavation (choose all that apply):
Needs to consider Lateral Pressures
Are possible only if the soil is cohesive
Must consider the need for dewatering
Can use braces if needed
Requires Engineering Design
part 2)
Some of the important steps/information necessary while planning excavations are (choose all that apply):
Proper monitoring equipment during construction
Soil exploration
Survey of surroundings
Dimension of the Excavation
In: Civil Engineering
A grouted riprap, trapezodial channel (n = 0.025) with a bottom width of 4 meters and side slope of m= 1 carries a discharge of 12m3/s on a 0.001 slope. Compute the backwater curve created by a low dam that backs water up to a depth of 2m immediately behind the dam specifically, water depths are required at a critical diversion points that are located at a distance of 188m,423m,748m,1675m, upstream of the dam ( Take normal depth Yn and Yc as 1.66m and 0.92m respectively)
A rectangular concrete (n= 0.020)canal has a slope of 0.0015,is 7m wide,and is carrying 15m3/s. At the upstream end of a broad crested weird, the depth is 3.3m
In: Civil Engineering
A truck will haul an average load of 15 cy, heaped capacity, and loose measure per load. Use average values of swell factors in Table 7.3 on p. 131 of your textbook to determine the volume of the truck in bank measure when the material is sand, ordinary earth, dense clay, and well-blasted rock.
Then, using an Excel spreadsheet, determine the number of trucks required to move material in the following scenario:
A project requires 40,000 cy of compacted fill that must be completed in 32 working days. The fill material will be hauled to the site in 21 cy loose measure trucks. The cycle time for a truck is 40 min. per trip. The swell factor for the earth is 25% and the shrinkage factor is 10%. Assume 8 hours per day and a 45-min. effective hour. Determine the number of required trucks to complete the project in 32 days.
Deliverable:
Upon completion of this project, you will deliver an excel
spreadsheet to include:
In: Civil Engineering