Chapter 9: Concrete Form Construction
Matching
Match terms to their definitions. Write the corresponding letters on the blanks. Not all terms will be used.
1. heavy timer or beam used to support vertical loads | a. buck |
2. the quality of being resistant to breaking under a pulling force | b. compressive strength |
3. column built within and usually projecting from a wall to reinforce the wall | c. girder |
d. microsilica | |
4. a rough frame used to form openings in poured concrete walls | e. pilaster |
5. vertical framing member in a wall running between plates | f. Portland cement |
6. in stairs, the vertical distance of the flight; in roofs, the vertical distance from plate to ridge | g. reinforcing rods |
7. a length of lumber or material applied over a joint to stiffen and strengthen it | h. rise |
i. run | |
8. a strip of wood used to keep other pieces a desired distance apart | j. scab |
k. spreader | |
9. the quality of being resistant to crushing | l. stud |
m. tensile strength |
True/False
Write True or False before the statement.
1. Footings are the first part of a building to be installed.
2. Building forms for slabs, walks, and driveways are exactly the same as building continuous footing forms.
3. A vapor retarder provides a barrier to soil gases, such as radon.
4. All wall form systems use similar components to make them perform as expected.
5. Outside corners of concrete-forming systems are created by attaching panels to angle irons with wedges.
6. Walers are difficult to install on forming systems.
7. Riser form boards for stairs are beveled on the top edge.
8. Water should be added to concrete so that it flows into forms without working it.
9. A slump test shows the wetness or dryness of a concrete mix.
10. Curing agents placed on green concrete contain harmful chemicals.
Multiple Choice
Choose the best answer. Write the corresponding letter on the blank.
1. A combined slab foundation/footing is called a slab.
2. When applying a vapor barrier of heavy plastic film under concrete, it should be lapped and sealed.
3. is the only insulation recommended for ground contact and can be placed between concrete and the subsoil.
4. The snap ties run through form boards and are wedged against additional form supports called .
5. Concrete-forming system panels are tied together with wedges.
6. The width of a step is called the .
7. Which of the following statements about the placement of concrete is true?
8. Concrete must be protected from freezing for after being placed.
9. If moist-cured for seven days, concrete strength will be full strength.
Terms
Read the descriptions of terms associated with concrete construction. Write the correct term on the corresponding blanks.
1. Provide a base on which to spread the load of a structure over a wider area of the soil
2. Provides a lock between the footing and the foundation wall
3. Hold wall forms together at the desired distance apart; support both sides against lateral pressure of concrete
4. Used to reinforce concrete floor slabs resting on the ground, driveways, and walks
5. Performed by inspectors on a job to determine the consistency of the concrete
Put in Order
Put in order the following steps for constructing footing forms. Write the corresponding numbers on the blanks.
A. Fasten the spreaders across the form at intervals necessary to hold the form the correct distance apart.
B. Stretch lines back on the batter boards in line with the outside edge of the footing.
C. Erect the inside forms in a manner similar to the outside forms.
D. Drive corner stakes to the correct elevation and stretch lines between the stakes, if desired.
Identify
Identify the following items use with concrete construction. Write the correct name on the line next to the item.
1.
Courtesy of Dayton/Richmond Concrete Accessories.
2.
Courtesy of Dayton/Richmond Concrete Accessories.
3.
© 2016 Cengage Learning®
4.
© 2016 Cengage Learning®
Procedures
Read the following procedures. Determine what procedure is being described and write the name of the procedure on the blank.
Procedure 1:
Procedure 2:
Calculations
Use the information provided to complete your calculations. Write answers on the lines provided within the exercises.
Estimating the Amount of Concrete for a Slab
Estimate the cubic yards of concrete for the slab shown below. The depth of the slab is 6 inches. Use the space provided for your calculations.
© 2016 Cengage Learning®
Total cubic yards:
Estimating the Amount of Concrete for a Footer
Estimate the cubic yards of concrete for a footer. Use the space provided for your calculations.
© 2016 Cengage Learning®
Total cubic yards:
Estimating Concrete Materials
Estimate the materials for a complete poured concrete foundation for a rectangular building 32' × 60'. Poured walls are 8 feet tall and 8 inches thick. Form boards are 12 feet long, and rebar is 20 feet long.
Estimate the materials for a foundation of a rectangular 30' × 56' building. Walls 8' tall and 10" thick, the footing is 2' wide by 12" thick, and slab is 5" thick. | |||
Item | Formula | Waste factor | Example |
Footing form boards | footing PERM × 2 sides ÷ 12' = NUM of 12' boards | 172' × 2 ÷ 12' = 28.6 ⇒ 29 boards | |
Slab form boards | slab PERM ÷ board LEN = NUM of boards | 172' ÷ 12' = 14.3 ⇒ 15 boards | |
Wall forms | wall PERM × 2 sides ÷ 2' WID of form = NUM of form panels | 172 × 2 ÷ 2' = 172 panels | |
Rebar footing | PERM × 2 ÷ 20' rebar LEN × waste = NUM of bars. | Add 10% for bar overlap | 172 × 2 ÷ 20' × 1.10 = 18.9 ⇒ 19 rebars |
Rebar walls 2' × 2' grid horizontal | PERM × [wall HGT ÷ 2 FT grid − 1] ÷ 20' rebar LEN × waste = NUM of 20' HOR bars | Add 10% for bar overlap | [8' ÷ 2 − 1] × 172' ÷ 20 × 1.10 = 28.3 ⇒ 29 rebars |
Rebar walls 2' × 2' grid vertical | PERM ÷ 2 ft grid + 1 per corner = NUM of VERT bars | 172 ÷ 2 + 4 = 90 vertical rebars | |
Concrete footing (Be sure all measurements are in terms of feet) | footing width × footing depth × PERM ÷ 27 = CY | Add 5% | 2' × 1' × 172' ÷ 27 × 1.05 5 5.6 1 5 3/4 CY |
Concrete slab | slab WID × slab LEN × slab thickness ÷ 27 = CY concrete | Add 10% | 30' × 56' × 5"/12 ÷ 27 × 1.10 = 28.5 ⇒ 28 3/4 CY |
Concrete wall | PERM × wall HGT × wall thickness ÷ 27 = CY | Add 5% | 172' × 8 × 10"/12 ÷ 27 × 1.05 = 44.5 ⇒ 44 3/4 CY |
© 2016 Cengage Learning®
Footing form boards | |
Slab form boards | |
Wall forms | |
Rebar footing | |
Rebar walls 2 × 2 grid horizontal | |
Rebar walls 2 × 2 grid vertical | |
Concrete footings | |
Concrete slab | |
Concrete walls |
File Upload
Maximum upload file size is 10MB
In: Civil Engineering
A direct shear test is conducted on a large specimen of dry sand (square cross section with following dimensions: 7.5 cm x 7.5 cm x 3.0 cm [height], Mass = 271.0 g) with a normal stress of 500 kPa. Failure occurred when the horizontal force was 1.96 kN. For the same sand, tests were also conducted to determine the specific gravity and the maximum and minimum void ratios. These tests yielded the following results: Gs= 2.65, emax=0.80, emin = 0.45. a) Calculate the relative density of the sand specimen b) Determine the friction angle of the soil. c) A triaxial specimen (H= 8.0 cm, D = 3.8 cm, Dr~45%) is prepared using the same sand. The test is performed on a saturated specimen with a chamber pressure of 500 kPa and an initial value of the pore pressure u of 100 kPa. Assuming that the results of the direct shear test can be used to predict those of the triaxial test, at what value of the total axial stress does the triaxial specimen fail?
In: Civil Engineering
2. The La Salle Bus Company has decided to purchase a new bus for $95,000 with a trade-in of their old bus. The old bus has a BV of $10,000 at the time of the trade-in. The new bus will be kept for 10 years before being sold. Its estimated SV at that time is expected to be $15,000.
a. Determine which asset class of the bus.
b. Determine annual Straight-Line Depreciation charge.
In: Civil Engineering
Shouldgovernment (state or federal) subsidies be provided to rural communities for the recycling of paper, plastics, glass, and tin cans? What are the advantages and disadvantages of such subsidies? Could the money that would be spent on such subsidies be spent more effectively? How?
In: Civil Engineering
Consider a lake with 65 × 106 m2 of surface area for which the only source of phosphorous is the effluent from a wastewater treatment plant. The lake is receiving a flow rate of 1 m3/s from the wastewater treatment plant, which has a phosphorous concentration of 20 mg/L. The lake is also fed by a stream having 20 m3/s of flow with no phosphorous in it. If the phosphorous settling rate is estimated to be 10 m/yr. (a) Write down the phosphorous mass balance equation for the lake and draw a control volume diagram for the lake showing influent streams, effluent streams, point-discharge source. (b) Estimate the average phosphorous concentration in the lake at steady-state. (c) Bonus Q: What level of phosphorous removal at the treatment plant would be required to keep the average lake concentration below 0.02 mg/L?
In: Civil Engineering
In: Civil Engineering
For construction project risk and conflict management: Provide a comparison between Dispute Resolution Techniques and compare them based on their process time, cost, and legal aspects.
In: Civil Engineering
The room is 5*6
Steel yield stress (fy = 60000 psi)
Concrete ultimate compressive strength (f’c = 4000 psi)
Reinforced concrete density = 150 lb/ft3.
Normal weight concrete is used.
The slab is treated as a one way slab and subjected to a dead
load of 120 psf (excluding the self-weight
of the slab) and a live load of 220 psf.
- The slab is supported by beams on the edges.
- There is a column at each corner of the slab supporting the
beams.
- Each beam is sitting on a non-load-bearing wall.
Design
- The slab
- The beams
- The columns
Carry out all ACI code checks and sketch your designs.
In: Civil Engineering
Q2. a) Explain the penetration test carried out on bitumen, state its significance and draw the test apparatus.
b). Mention the main factors considered in the choice of construction materials at the design office – is any of them more important than the other?
c). What factors affect the weldability of steel?
d). Consider the iron value chain from material extraction to disposal, at what point according to your assessment is the most energy used? As a design engineer, at what stage do you think is your intervention most important and what role can you play in making iron more sustainable?
In: Civil Engineering
why we don't use density,average speed,and volume to describe the intersection LOS(LEVEL OF SERVICE)
In: Civil Engineering
In: Civil Engineering
Compare the methods of measuring tensile strength by (a) direct tension; (b) splitting tension; (c) flexure.
In: Civil Engineering
What is truly elastic material? Is concrete truly elastic? If not, why? Describe the various stages of micro cracking when a concrete specimen is loaded to failure (please use sketches to explain the behavior and the micro cracking).
In: Civil Engineering
In: Civil Engineering
The detail of column and pad footing are as under: [5]
Size of column: 300 mm x 300 mm.
Live load on column: 900 kN.
Dead load on column: 1200 kN.
Soil Bearing Pressure: 180 kN/m² and Depth of footing as 400 mm
Nominal cover: 50 mm and 20 mm diameter bars for reinforcement
iii. Write the reasons for considering the service loads for dimensioning of the footing and factored loads for calculating the factored soil pressure.
In: Civil Engineering