Given the following project:
Act. Preceding Crash Cost Maximum Crash Normal Time Activity (in million $) Time (in months) (in months)
A - 0 0 1
B A 10 2 3
C A 5 1 4
D B 6 1 3
E C 7 2 4
F D, E 9 1 3
SLACK TIME = Late Starting Time – Early Starting Time OR Late Finish Time – Early Finish Time
To reduce the project time as much as possible given its characteristics, what activity or activities can be crashed?