Question

In: Civil Engineering

For the project with the five activities given below, you are required to crash the project...

For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days.

For the project with the five activities given below, you are required to crash the project

duration from its original duration to a final duration of 14 days. Assuming a daily

indirect cost of $100,

what is the total cost of the project with a duration of 14 days

.

Duration (days)

Cost ($)

Cost slope

Activity

IPA

Normal

Crash

Normal

Crash

A

-

3

1

2,000

5,000

B

A

5

2

3,000

6,000

C

A

3

2

3,000

5,000

D

A

8

3

3,000

8,000

E

B,C,D

5

3

1,000

2,000

Total Direct Cost before Crashing

Draw a Network Diagram (with the Crashing shown) below:

Compression

Cycle

Activity

Compression

days

Amount

Project

Duration

Direct

Cost

Indirect

Cost

Total

Cost

0

-

-

-

1

Solutions

Expert Solution


Related Solutions

Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
Given the following project: Act.          Preceding                    Crash Cost    &nbs
Given the following project: Act.          Preceding                    Crash Cost              Maximum Crash               Normal Time                                            Activity                       (in million $)             Time (in months)               (in months) A                     -                                   0                                  0                                  1         B                     A                                 10                                2                                   3                      C                     A                                  5                                 1                                   4                      D                     B                                  6                                 1                                   3                      E                      C                                 7                                  2                                  4                      F                     D, E                                9                                 1                                      3 SLACK TIME = Late Starting Time – Early Starting Time OR Late Finish Time – Early Finish Time To reduce the project time as much as possible given its characteristics, what activity or activities can be crashed?
Identify at least five key hazards associated with the excavation required for the given project, and...
Identify at least five key hazards associated with the excavation required for the given project, and evaluate the degree of risk for each hazard, using scales for likelihood and severity of your own devising.
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
List and describe any five activities performed by the project manager during project planning.
List and describe any five activities performed by the project manager during project planning.
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months Unit 4 Project: Activity Description Est $ Architectural Design 50,000...
[50%] Code Snippet Given snippet code below that you are required to complete. You are not...
[50%] Code Snippet Given snippet code below that you are required to complete. You are not allowed to make a new function or change any given code. Please complete each section that are marked with the notation “INSERT YOUR CODE HERE”. Once you complete the snippet below, your output should have the same result with the given output below. Descriptions: [15%] isValid() This function is for checking that there is no duplicated employee data in the linked list. This function...
You are required to answer the FIVE (5) tasks below, in relation to your chosen organisation....
You are required to answer the FIVE (5) tasks below, in relation to your chosen organisation. For each task, you must fully justify your answer using evidence from your research. Examine the relationship between the organisation’s corporate strategy and its operations strategy. Analyse the importance of technology in supporting operations within the organisation Discuss the rationale for the process types used in the organisation to manufacture the type of goods being created Examine the role of performance measures in the...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost...
Project management Expediting a Project Task Predecessor Normal Time Weeks Normal Cost Crash Time Crash Cost A - 4 $2000 4 - B A 4 $1500 2 4500 C A 6 5000 4 8000 D B 2 1000 2 - E B 6 8000 3 10000 F C 10 10000 7 14000 G D 7 3500 4 5000 H E 4 2500 2 5000 I G,H 3 2000 2 3500 J I,F 3 3000 1 4500 Consider the project shown...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are...
19. Consider a project consisting of five activities. The immediate predecessors and the activity times are summarized as below: Activity Immediate Predecessor Activity time (in days) A None 3 B A 2 C A 1 D B, C 3 E D 4 In CPM, what is the completion time of the project? A 12 days B 11 days C 13 days 20. A forecasting method has produced the following over the past five months. What is the mean absolute deviation...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT