In: Civil Engineering
For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days.
For the project with the five activities given below, you are required to crash the project
duration from its original duration to a final duration of 14 days. Assuming a daily
indirect cost of $100,
what is the total cost of the project with a duration of 14 days
.
Duration (days)
Cost ($)
Cost slope
Activity
IPA
Normal
Crash
Normal
Crash
A
-
3
1
2,000
5,000
B
A
5
2
3,000
6,000
C
A
3
2
3,000
5,000
D
A
8
3
3,000
8,000
E
B,C,D
5
3
1,000
2,000
Total Direct Cost before Crashing
Draw a Network Diagram (with the Crashing shown) below:
Compression
Cycle
Activity
Compression
days
Amount
Project
Duration
Direct
Cost
Indirect
Cost
Total
Cost
0
-
-
-
1