Question

In: Civil Engineering

For the project with the five activities given below, you are required to crash the project...

For the project with the five activities given below, you are required to crash the project duration from its original duration to a final duration of 14 days. Assuming a daily indirect cost of $100, what is the total cost of the project with a duration of 14 days.

For the project with the five activities given below, you are required to crash the project

duration from its original duration to a final duration of 14 days. Assuming a daily

indirect cost of $100,

what is the total cost of the project with a duration of 14 days

.

Duration (days)

Cost ($)

Cost slope

Activity

IPA

Normal

Crash

Normal

Crash

A

-

3

1

2,000

5,000

B

A

5

2

3,000

6,000

C

A

3

2

3,000

5,000

D

A

8

3

3,000

8,000

E

B,C,D

5

3

1,000

2,000

Total Direct Cost before Crashing

Draw a Network Diagram (with the Crashing shown) below:

Compression

Cycle

Activity

Compression

days

Amount

Project

Duration

Direct

Cost

Indirect

Cost

Total

Cost

0

-

-

-

1

Solutions

Expert Solution


Related Solutions

The estimated times and immediate predecessors for activities in a project are given below in the...
The estimated times and immediate predecessors for activities in a project are given below in the table. Assume that the activity time are independent. Task                           Predecessor                Optimistic   Most Likely   Pessemistic                                                                             Time (wks)    time (wks)     time (wks) Architectural design                            --         10                  30                    45 Software                      Architectural design    13                  15                    23 Compilg                      Software                          2                  3                    4 Hardware                    Architectural design    15                  20                    25 Integration                   Software & Hardware   20                  22                    24 Bug fixes                     Integration                   3                    4                      11             a) Draw an activity-on-node...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations...
Consider the project with the listed activities. Normal durations and costs, as well as crash durations and costs are listed for each activity. Precedence relationships are implicitly given by the activity names (e.g., activity (1,2) is represented as an arc from node 1 to node 2).                                 Crash     Crash                                     Normal                 Normal Activity                 Time      Cost                                       Time                      Cost (1, 2)                      5              $41,000                                 8                              $29,000 (1, 3)                      2              $18,000                                 3                              $10,000 (2, 4)                      10           $50,000                                 12                           $46,000 (2, 5)                      4              $26,000                                 6                             ...
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
Given the following project: Act.          Preceding                    Crash Cost    &nbs
Given the following project: Act.          Preceding                    Crash Cost              Maximum Crash               Normal Time                                            Activity                       (in million $)             Time (in months)               (in months) A                     -                                   0                                  0                                  1         B                     A                                 10                                2                                   3                      C                     A                                  5                                 1                                   4                      D                     B                                  6                                 1                                   3                      E                      C                                 7                                  2                                  4                      F                     D, E                                9                                 1                                      3 SLACK TIME = Late Starting Time – Early Starting Time OR Late Finish Time – Early Finish Time To reduce the project time as much as possible given its characteristics, what activity or activities can be crashed?
Identify at least five key hazards associated with the excavation required for the given project, and...
Identify at least five key hazards associated with the excavation required for the given project, and evaluate the degree of risk for each hazard, using scales for likelihood and severity of your own devising.
The expected times and variances for the project activities are given below. Complete the table showing...
The expected times and variances for the project activities are given below. Complete the table showing which activities are critical. ID Description Predecessor Te Variance Critical? 1 Pilot Production None 6 3 ? 2 Select Channels of Distribution None 20 4 ? 3 Develope Mktg. Program None 18 2 ? 4 Test Market 1 4 2 ? 5 Patent 1 17 5 ? 6 Full production 4 9 10 ? 7 Ad Promotion 3 16 2 ? 8 Release 2,5,6,7...
For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL...
For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL COST$ CRASH SLOPE A NONE 3 0 60 0 B NONE 7 1 30 50 C A 5 3 50 13.33 D A 6 1 30 20 E C,B 4 2 40 30 1.What is the normal project duration? = BLANK-1 2. Whatis the normal project cost? = BLANK-2 3. What is the project cost when fully crashed? = BLANK-3 4. Which activities were...
List and describe any five activities performed by the project manager during project planning.
List and describe any five activities performed by the project manager during project planning.
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the...
For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months Unit 4 Project: Activity Description Est $ Architectural Design 50,000...
A project manager has compiled a list of major activities that will be required to install...
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. Use standard deviation table. Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT