Question

In: Finance

Given a project with the following cash flows and a cost of capital of 9%. Calculate...

Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, PI, payback and discounted payback. For each of the six calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not?

Time Period Cash Flow

     0 -$200,000

     1 $50,000

     2 $70,000

     3 -$80,000

     4 $75,000

     5 $100,000

     6 $120,000

Solutions

Expert Solution


Related Solutions

Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37500 $11250 $11250 $15000 $6000 $6000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.27 years longer than the payback period. 1.85 years longer than the payback period.
Given the following cash flows for a proposed capital investment project, calculate the payback period. Year...
Given the following cash flows for a proposed capital investment project, calculate the payback period. Year Cash Flow 0 -$40,000 1 15,000 2 15,000 3 15,000 4 15,000 5 10,000 6 10,000 Question 4 options: 5.50 years 3.33 years 4.33 years 2.67 years
You are considering the following project. Your cost of capital is 8%. The cash flows are...
You are considering the following project. Your cost of capital is 8%. The cash flows are as follow: Year 0 1 2 3 4 -1000 300 500 300 300 What is the NPV of the project? A. 165 B. 296 C. 400 D. 1400
Given the following, calculate the cash flows for the project. Initial investment $365,000 Expected life is...
Given the following, calculate the cash flows for the project. Initial investment $365,000 Expected life is 5 years First Year Revenues: 245,000 First Year Expenses: $70,000 Growth for revenue and expenses: 3 percent per year Straight Line Depreciation over 5 years Salvage Value: $45,000 One-time net working capital investment of $10,000 required at the start of the project This investment is recovered at the end of the project The tax rate is 34 percent Answer the following: What are the...
The project has the following cash flows and salvage values and cost of capital 8%: Year...
The project has the following cash flows and salvage values and cost of capital 8%: Year Cash flows Salvage 0 -5000 4000 1 2500 3500 2 3200 1800 3 1600 900 4 1000 0 What are the physical life and the economic life for this project? A. Physical life of this project is 3 years with economic life of 4 years. B. Physical life of this project is 4 years with economic life of 1 year. C. Physical life of...
2. Given the following expected cash flows for two projects, and an opportunity cost of capital...
2. Given the following expected cash flows for two projects, and an opportunity cost of capital of 10%, which project is better and why? (10 points)             Expected Net Cash Flows Year    Project A         Project B 0          -$10,000          -$10,000 1          $5000              $0 2          $5000              $0 3          $5000              $8,000 4          $5000              $2,000 3. Given the following expected cash flows for two projects, and an opportunity cost of capital of 8%, which project is better and why? (10 points)             Expected Net...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
Consider the below estimated cash flows for Project A. Assume the cost of capital is 8%.
  Consider the below estimated cash flows for Project A. Assume the cost of capital is 8%. Year Project A 0 ($30,000) 1 $8,000 2 $9,000 3 $7,000 4 $10,000 8. Find the net present value (NPV) of Project A’s projected cash flows. a. $4,000 b. ($3,200) c. ($1,824) d. $1,754 e. ($1,969) 9. Find the Internal Rate of Return (IRR) Project A’s projected cash flows. a. 13.3%       b. 8.0%       c. 6.3%    ...
Calculate the NPV of a 20-year project with a cost of $300,000 and annual cash flows...
Calculate the NPV of a 20-year project with a cost of $300,000 and annual cash flows of $25,000 in years 1-10 and $50,000 in years 11-20. The company's required rate of return is 10%
Calculate the following project, at cost of capital of 10% Years Cash Flow (RM) 0 -10,000...
Calculate the following project, at cost of capital of 10% Years Cash Flow (RM) 0 -10,000 1 2000 2 2000 3 4000 4 4000 5 5000 i) calculate NPV (8marks) ii) calculate PI iii) Justified should we accept or reject the project?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT