Question

In: Statistics and Probability

The Time Numbers represent weeks a. Find the mean time for completion of the project b....

The Time Numbers represent weeks
a. Find the mean time for completion of the project
b. Find the probability that the project will be completed two weeks earlier than the mean
time.
Preceding Optimistic Most Likely Pessimistic
Activity Activity Time Time Time
A. Write Book 10 13 17
B. Design Book Cover A 1 1 1
C. Edit Manuscript A 3 6 9
D. Check Editing C 2 3 6
E. Accept Design B 1 1 1
F. Copy Edit D,E 1 2 3
G. Prepare Artwork D,E 3 4,5 5
H. Accept and Correct G 5 5 5
Artwork
I. Set Galleys F 3 4 6
J. Check and Correct I 1 1 1
Galleys
K. Pull Page Proofs H,J 2 2 3
L. Check and Correct I 1 1 1
Galleys
M. Prepare Index K 1 1 1
N. Set and Correct M 0.5 0.5 0.5
Index
O. Check Camera- L,N 0.5 1 1.5
Ready Copy
P. Print and Bind O 1 2 3
Book

Solutions

Expert Solution

The solution is provided below:

The output is shown below:

Part A:

Formula:

Output:

So, the mean time for project completion is 38.5 weeks

Part B:

Please find the solution below:

So, there is a probability of 0.1271 that the project will be completed 2 weeks earlier...

End of the Solution...


Related Solutions

The time required to complete a project is normally distributed with a mean of 78 weeks...
The time required to complete a project is normally distributed with a mean of 78 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. 4. What is the probability of the completing the project in no more than 52 weeks? a) 0.25 b) 0.50 c) 0.75 d) 0.05 5. What is the probability of the completing the project in more than 55 weeks? a) 0.1587 b) 0.5091...
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. What is the probability of the completing the project in no more than 52 weeks? 0.25 0.50 0.75 0.05 What is the probability of the completing the project in more than 55 weeks? 0.1587 0.5091 0.7511 0.0546 What is the probability of completing...
Will the time frame of a project affect the completion design? Discuss.
Will the time frame of a project affect the completion design? Discuss.
A project completion time can be assumed to be represented by a normal distribution curve The...
A project completion time can be assumed to be represented by a normal distribution curve The project is expected to complete in 36 weeks with a path variance of 6.67 Base on the information provided, calculate: a. Calculate the probability that the project will be completed in 39 weeks or less b. The probability that the project will be completed in between 33.5 and 38 weeks c. With 95 percent probability, calculate the date the project can be completed.
A tasks completion time is normally distributed with a mean of 200 work days and a...
A tasks completion time is normally distributed with a mean of 200 work days and a SD of 10 work days. What is the probability that: (a) The task finishes within 185 work days. (b) The task takes longer than 212 work days (c) In order to be 99% sure that the task will not be completed late, the contractor must request a completion time of _______ days
Let A and B be sets of real numbers such that A ⊂ B. Find a...
Let A and B be sets of real numbers such that A ⊂ B. Find a relation among inf A, inf B, sup A, and sup B. Let A and B be sets of real numbers and write C = A ∪ B. Find a relation among sup A, sup B, and sup C. Let A and B be sets of real numbers and write C = A ∩ B. Find a relation among sup A, sup B, and sup...
Using? PERT, Adam Munson was able to determine that the expected project completion time for the...
Using? PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 ?months, and the project variance is 9. ?a) The probability that the project will be completed in 13 months? = nothing ?(round your response to four decimal? places). ?b) The probability that the project will be completed in 21 months? = nothing ?(round your response to four decimal? places). ?c) The probability that the project will be...
Summarize the qualitative risks of on‐time project completion considering the current employment and work environment in...
Summarize the qualitative risks of on‐time project completion considering the current employment and work environment in the U.S. Several members of your programming team live and work throughout the U.S., and are subject to the laws of those states. Additionally, some of the programming tasks could be modified and possibly sub‐contracted to India, Bulgaria, China, Argentina, and Indonesia.Discuss how the project manager should address cost/time trade‐offs associated with international outsourced completion of programming tasks. What criteria should be used to...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT