In: Statistics and Probability
| The Time Numbers represent weeks | ||||||
| a. Find the mean time for completion of the project | ||||||
| b. Find the probability that the project will be completed two weeks earlier than the mean | ||||||
| time. | ||||||
| Preceding | Optimistic | Most Likely | Pessimistic | |||
| Activity | Activity | Time | Time | Time | ||
| A. Write Book | 10 | 13 | 17 | |||
| B. Design Book Cover | A | 1 | 1 | 1 | ||
| C. Edit Manuscript | A | 3 | 6 | 9 | ||
| D. Check Editing | C | 2 | 3 | 6 | ||
| E. Accept Design | B | 1 | 1 | 1 | ||
| F. Copy Edit | D,E | 1 | 2 | 3 | ||
| G. Prepare Artwork | D,E | 3 | 4,5 | 5 | ||
| H. Accept and Correct | G | 5 | 5 | 5 | ||
| Artwork | ||||||
| I. Set Galleys | F | 3 | 4 | 6 | ||
| J. Check and Correct | I | 1 | 1 | 1 | ||
| Galleys | ||||||
| K. Pull Page Proofs | H,J | 2 | 2 | 3 | ||
| L. Check and Correct | I | 1 | 1 | 1 | ||
| Galleys | ||||||
| M. Prepare Index | K | 1 | 1 | 1 | ||
| N. Set and Correct | M | 0.5 | 0.5 | 0.5 | ||
| Index | ||||||
| O. Check Camera- | L,N | 0.5 | 1 | 1.5 | ||
| Ready Copy | ||||||
| P. Print and Bind | O | 1 | 2 | 3 | ||
| Book | ||||||
The solution is provided below:
The output is shown below:
Part A:
Formula:

Output:



So, the mean time for project completion is 38.5 weeks
Part B:
Please find the solution below:
So, there is a probability of
0.1271 that the project will be completed 2 weeks earlier...
End of the Solution...