In: Statistics and Probability
The Time Numbers represent weeks | ||||||
a. Find the mean time for completion of the project | ||||||
b. Find the probability that the project will be completed two weeks earlier than the mean | ||||||
time. | ||||||
Preceding | Optimistic | Most Likely | Pessimistic | |||
Activity | Activity | Time | Time | Time | ||
A. Write Book | 10 | 13 | 17 | |||
B. Design Book Cover | A | 1 | 1 | 1 | ||
C. Edit Manuscript | A | 3 | 6 | 9 | ||
D. Check Editing | C | 2 | 3 | 6 | ||
E. Accept Design | B | 1 | 1 | 1 | ||
F. Copy Edit | D,E | 1 | 2 | 3 | ||
G. Prepare Artwork | D,E | 3 | 4,5 | 5 | ||
H. Accept and Correct | G | 5 | 5 | 5 | ||
Artwork | ||||||
I. Set Galleys | F | 3 | 4 | 6 | ||
J. Check and Correct | I | 1 | 1 | 1 | ||
Galleys | ||||||
K. Pull Page Proofs | H,J | 2 | 2 | 3 | ||
L. Check and Correct | I | 1 | 1 | 1 | ||
Galleys | ||||||
M. Prepare Index | K | 1 | 1 | 1 | ||
N. Set and Correct | M | 0.5 | 0.5 | 0.5 | ||
Index | ||||||
O. Check Camera- | L,N | 0.5 | 1 | 1.5 | ||
Ready Copy | ||||||
P. Print and Bind | O | 1 | 2 | 3 | ||
Book | ||||||
The solution is provided below:
The output is shown below:
Part A:
Formula:
Output:
So, the mean time for project completion is 38.5 weeks
Part B:
Please find the solution below:
So, there is a probability of 0.1271 that the project will be completed 2 weeks earlier...
End of the Solution...