5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:
|
Activity Name |
Predecessor(s) |
Duration (Weeks) |
|
A |
None |
20 |
|
B |
None |
10 |
|
C |
None |
10 |
|
D |
A,B |
40 |
|
E |
C |
10 |
|
F |
C,D |
20 |
|
G |
E,F |
10 |
Activity on Arrow Diagram:

Project Duration:90 weeks
Critical Path:A-D-F-G
Slack is tabulated below
| Activity | SLACK |
| A | 0 |
| B | 10 |
| C | 50 |
| D | 0 |
| E | 60 |
| F | 0 |
| G | 0 |
Explanation