5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...

5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:

Activity Name

Predecessor(s)

Duration (Weeks)

A

None

20

B

None

10

C

None

10

D

A,B

40

E

C

10

F

C,D

20

G

E,F

10

Solutions

Expert Solution

Activity on Arrow Diagram:

Project Duration:90 weeks

Critical Path:A-D-F-G

Slack is tabulated below

Activity SLACK
A 0
B 10
C 50
D 0
E 60
F 0
G 0

Explanation


Related Solutions

Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
Many project managers use critical path analysis to minimize slack time in projects and ensure tasks...
Many project managers use critical path analysis to minimize slack time in projects and ensure tasks are completed in a timely manner. Briefly discuss what is meant by critical path analysis. What are critical path activities and why are they important?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Assume activity A will actually take 5 weeks, what is the new critical path and new...
Assume activity A will actually take 5 weeks, what is the new critical path and new expected duration? (4 Marks
Given the following binary relations R on two sets, for each relation: Draw the arrow diagram...
Given the following binary relations R on two sets, for each relation: Draw the arrow diagram of R. Is R a function, and why? If R is a function, determine if it is injective or surjective. Is the function bijective? Justify your answers. R = {(a, 3), (c, 1)} on domain {a, b, c} and codomain {1, 2, 3} R = {(1, a), (3, c), (2, b)} on domain {1, 2, 3} and codomain {a, b, c} R = {(a,...
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
1. What is the duration of the critical path? Please show me step by step on...
1. What is the duration of the critical path? Please show me step by step on how you were able to solve this. I WANT TO KNOW IN DETAILED STEPS ON HOW YOU DO THIS, I HAVE NO CLUE/HAVE KNOWLEDGE ABOUT THIS. Activity Duration Predecessor A 2 Start B 4 A,E C 6 A D 3 B,C E 7 Start F 2 E End - D,F
When activity times are known with certainty, the critical path is defined as the set of...
When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition?
Draw the Swimlanes Activity diagram for Library Information System.
Draw the Swimlanes Activity diagram for Library Information System.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT