In: Operations Management
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:
Activity Name |
Predecessor(s) |
Duration (Weeks) |
A |
None |
20 |
B |
None |
10 |
C |
None |
10 |
D |
A,B |
40 |
E |
C |
10 |
F |
C,D |
20 |
G |
E,F |
10 |
Activity on Arrow Diagram:
Project Duration:90 weeks
Critical Path:A-D-F-G
Slack is tabulated below
Activity | SLACK |
A | 0 |
B | 10 |
C | 50 |
D | 0 |
E | 60 |
F | 0 |
G | 0 |
Explanation