Question

In: Operations Management

A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...

A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology?

Activity Predecessor Length Activity Predecessor Length
A -- 18 E C, D 13
B -- 16 F C 9
C A 22 G E, F 15
D B 14

Options:

0

1

2

3

Solutions

Expert Solution

The activity table is:

Activity

Predecessor

Length

A

---

18

B

---

16

C

A

22

D

B

14

E

C, D

13

F

C

9

G

E, F

15

The precedence diagram is:

The critical path is the path with the longest total task length.

Length of each path is:

A -> C -> F -> G: 64

A -> C -> E -> G: 68

B -> D -> E -> G: 58

Hence, the critical path is A -> C -> E -> G

Feeding buffer (or feeder buffers) are used in the non-critical paths so that any delay in the non-critical path wont delay the critical path.

Here the critical path is A->C->E->G

This path depends on B->D->E->G non-critical path so as to start E on time.

This path depends on A->C->F->G non-critical path so as to start G on time.

As the likelihood of completion is 90%, hence 90% of the total task time should be performed. 90% of total task time is = 0.9*107 = 96.3

Hence till the starting of task G, it should be completed.

Hence, the number of feeder buffers used = 2.

Answer is: 2

.

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!


Related Solutions

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...
Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A Clear Site and mobilize labour and equipment None 5 B Excavate foundation A 15 C Procure materials (sand, cement, chippings etc.) A 10 D Pour foundation concrete B, C 5 E Mould sandcrete blocks (substructure) C 5 F Construct substructure block work D, E 15 G Construct superstructure block work F, H 30 H Make doors and window frames I 10 I Procure and...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None...
QUESTION 5 A project has the following activities: Activity Duration, days Predecessor activity A 8 None B 7 A C 4 None D 11 C E 7 B & D The project started on Day 1. Assume 7 working days a week. For example, activity A start on Day 1 and finish on the end of day 8. John is responsible for both activities B and D. However, he CAN'T work on both of them on the same period. By...
A project completion time can be assumed to be represented by a normal distribution curve The...
A project completion time can be assumed to be represented by a normal distribution curve The project is expected to complete in 36 weeks with a path variance of 6.67 Base on the information provided, calculate: a. Calculate the probability that the project will be completed in 39 weeks or less b. The probability that the project will be completed in between 33.5 and 38 weeks c. With 95 percent probability, calculate the date the project can be completed.
8. if the project duration needs to be reduced then a. the activity with the lost...
8. if the project duration needs to be reduced then a. the activity with the lost cost should be selected b. activity which is currently undergoing should be selected c. activity with the highest cost should be selected d. activity on the critical path should be selected . 9. it does not make any sense to crash if a. if there is no critical activity left b. project crashing cost is equal or more than saving c. project is more...
The total plan for the project involved 1000 staff-days of value (the Budgeted at Completion or...
The total plan for the project involved 1000 staff-days of value (the Budgeted at Completion or BAC) accumulated over 10 months with a staff of 5 full-time people. At the 4-month mark, with no open tasks, the total accumulated earned value is 320 staff-days. The plan at this point is for 340 staff-days to have been earned. Alas, the actual amount spent (because extra staff time has already been spent on this project) is 370 staff-days. A summary of the...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
The project is estimated to be of 10 years duration. It involves setting up new machinery...
The project is estimated to be of 10 years duration. It involves setting up new machinery with an estimated cost of as much as Thai baht (THB) 375 million, including installation. This amount could be depreciated using the straight-line method (SLM) over a period of 10 years with a resale value of THB 13.5 million. The project would require an initial working capital of THB 15.5 million. With the planned new capacity, the company would be able to produce 200,000...
Assume that credit sales "to be received in 90 days" are received in exactly 90 days...
Assume that credit sales "to be received in 90 days" are received in exactly 90 days and that EFT wage payments are made in exactly 7 days. Expected to pay income tax of 35%? And its journal entries CR and DR 01-January-2016 Open business bank account with transfer of personal funds $210,000 02-January-2016 EFT for rental of office space. Immediate occupancy. 60 months at $3500 per month. $210,000 11-January-2016 Office equipment purchased for cash to get discount from the retail...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities...
The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A D 5 A E 4 B F 7 B G 8 D, E H 5 G, F            (a)        Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path. [12 marks] (b)       Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks] (c)       From which activity...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors...
The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors Predecessors: A is none B is none C is B D is A & C E is B F is D, E, G G is B H is F I is G J is I What is slack time (float) for A6 weeks---B6 weeks---C5 weeks D4 weeks, E5 weeks F7 weeks, G4 weeks H8 weeks I5 weeks J3 weeks Step 1: Construct a network...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT