Question

In: Operations Management

Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities...

Mark the WRONG statement.
A. Some Project networks do not have a critical path.
B. Activities on a critical path have a float of zero.
C. A delay in critical activity surely delays the completion of project.
D. A network can have more than one critical path.
E. Each critical activity has identical earliest and the latest start times.

Solutions

Expert Solution

Wrong answer is A) Some Project networks do not have a critical path as

Activities on a critical path have a float of zero. A delay in critical activity surely delays the completion of project. A network can have more than one critical path. Each critical activity has identical earliest and the latest start times are true


Related Solutions

For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Imagine you are a project manager of a green roof top installation project. You have to make a critical path for your project? How can you do it?
Imagine you are a project manager of a green roof top installation project. You have to make a critical path for your project? How can you do it? Construct the critical network diagram (critical path) for this project.
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
Which of the following statements regarding critical paths is true? a. Some activities on the critical...
Which of the following statements regarding critical paths is true? a. Some activities on the critical path may have positive slack b. An activity on the critical path can have Early Start and Late Start times that are different c. The longest path through the network is the critical path d. Every network has exactly one critical path e. The duration of the critical path is the average duration of ALL paths in the project network   Which of the following...
In managing a project of the scale and type indicated below, the Critical path method(CPM) is...
In managing a project of the scale and type indicated below, the Critical path method(CPM) is utilized, composed of the following activities and their durations. Activity Time in days preceding activities A 10 -- B 6 -- C 8 A D 3 B E 7 C G 12 B H 5 C F 3 D, G I 5 E, H J K 8 8 C F, I, J a) Draw a critical path network(CPM) network diagram for this project on...
Consider the project described in the below Excel a. Use Excel to find the critical path...
Consider the project described in the below Excel a. Use Excel to find the critical path and the project duration using normal activity times. b. What is the shortest duration the project can be crashed down to? c. If you were to crash the project manually and your goal is to minimize crashing cost, which activity would you start with? d. Find the cheapest way to crash the project to 33 weeks. What are the critical activities in the crashed...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT