Mark the WRONG statement.
A. Some Project networks do not have a critical path.
B. Activities on a critical path have a float of zero.
C. A delay in critical activity surely delays the completion of
project.
D. A network can have more than one critical path.
E. Each critical activity has identical earliest and the latest
start times.
Wrong answer is A) Some Project networks do not have a critical path as
Activities on a critical path have a float of zero. A delay in critical activity surely delays the completion of project. A network can have more than one critical path. Each critical activity has identical earliest and the latest start times are true