Question

In: Operations Management

Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities...

Mark the WRONG statement.
A. Some Project networks do not have a critical path.
B. Activities on a critical path have a float of zero.
C. A delay in critical activity surely delays the completion of project.
D. A network can have more than one critical path.
E. Each critical activity has identical earliest and the latest start times.

Solutions

Expert Solution

Wrong answer is A) Some Project networks do not have a critical path as

Activities on a critical path have a float of zero. A delay in critical activity surely delays the completion of project. A network can have more than one critical path. Each critical activity has identical earliest and the latest start times are true


Related Solutions

For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Imagine you are a project manager of a green roof top installation project. You have to make a critical path for your project? How can you do it?
Imagine you are a project manager of a green roof top installation project. You have to make a critical path for your project? How can you do it? Construct the critical network diagram (critical path) for this project.
What is the critical path?What is the EF for the project to obtain financing?What...
What is the critical path?What is the EF for the project to obtain financing?What is the ES for the Legal work?What is the total duration of the entire project?What is the LF for creating the financing plan?What is the LS for Detailed Engineering (2/2)?What is the Float for the accounting activity?What is the EF for commissioning and transfer?What is the LF for commissioning and transfer?What is the ES for the Finish Construction activity?What is the EF for the Detailed Engineering...
Which of the following statements regarding critical paths is true? a. Some activities on the critical...
Which of the following statements regarding critical paths is true? a. Some activities on the critical path may have positive slack b. An activity on the critical path can have Early Start and Late Start times that are different c. The longest path through the network is the critical path d. Every network has exactly one critical path e. The duration of the critical path is the average duration of ALL paths in the project network   Which of the following...
Subject: Computer Networks Chapter:packets 2.0. Suppose the path from A to B has a single switch...
Subject: Computer Networks Chapter:packets 2.0. Suppose the path from A to B has a single switch S in between: A───S───B. Each link has a propagation delay of 60 µsec and a bandwidth of 2 bytes/µsec. (a). How long would it take to send a single 600-byte packet from A to B? (b). How long would it take to send two back-to-back 300-byte packets from A to B? (c). How long would it take to send three back-to-back 200-byte packets from...
In managing a project of the scale and type indicated below, the Critical path method(CPM) is...
In managing a project of the scale and type indicated below, the Critical path method(CPM) is utilized, composed of the following activities and their durations. Activity Time in days preceding activities A 10 -- B 6 -- C 8 A D 3 B E 7 C G 12 B H 5 C F 3 D, G I 5 E, H J K 8 8 C F, I, J a) Draw a critical path network(CPM) network diagram for this project on...