In: Operations Management
Which of the following statements regarding critical paths is true?
a. |
Some activities on the critical path may have positive slack |
|
b. |
An activity on the critical path can have Early Start and Late Start times that are different |
|
c. |
The longest path through the network is the critical path |
|
d. |
Every network has exactly one critical path |
|
e. |
The duration of the critical path is the average duration of ALL paths in the project network |
Which of the following statements regarding Gantt charts is true?
a. |
Gantt charts give a timeline and precise precedence/dependency relationships for each activity of a project |
|
b. |
Gantt charts are expensive |
|
c. |
Gantt charts are visual tools showing the timing and duration of activities in a project |
|
d. |
Gantt charts use the four standard activities of Methods, Materials, Manpower, and Machinery |
|
e. |
All of the statements listed are true |
The network analysis in project management involves Forward pass and Backward pass of start and finish times. These calculations allow determination of slack times.
True
False
Answer 1 : C. The longest path through the network is the critical path
Explanation : Critical paths are the longest through the network which has no slack while the sequence of activities define the start and end dates of the projects.
Answer 2 : C. Gantt charts are visual tools showing the timing and duration of activities in a project.
Explanation : Gantt charts display tasks against the time while have visual view where the ritical information regarding tasks, duration etc of the project are been displayed.
Answer 3 : True
Explanation : Forward pass is been used to determine project duration, while the backward pass represent end results in which the slack in the activities can be known.