Question

In: Operations Management

For the following network determine: a) The activities on the critical path b) The time for...

For the following network determine:

a) The activities on the critical path

b) The time for the critical path

c) The slack for EVERY activity

Activity Immediate Predecessors Time
A - 5
B - 4
C A,B 3
D A,B 6
E A,B 2
F C,D,E 8
G C,D,E 5

Solutions

Expert Solution

To answer the above question, we'll have to make a network diagram first.

A, B activities are independent and can be started right away.

C, D, E are dependent on A and B and will start only after completion of A and B.

F and G are dependent on C, D & E and will start only after completion of C, D, & E

The project will be completed after completion of activities E and F.

The above details give us the following network diagram.

We now perform forward pass on Activity on Node network diagram.

In the forward pass,

The early start for independent activities is always 0. Early start for activities A, B is 0.

Early finish (EF) = Early start (ES) + Duration of the task

For task A, Early finish = 0 + 5 = 5

For task B, Early finish = 0 + 4 = 4

Early start any activity is the lastest Early finish value for any predecessor.

For activity C, D, & E, Early start is 5, Latest early finish value of its predecessors A(5) and B(4).

For task C, Early finish = 5 + 3 = 8

For task D, Early finish = 5 + 6 = 11

For task E, Early finish = 5 + 2 = 7

For activity E& F, an early start is 11, Latest early finish value of its predecessors C(8) and D(11) & E(7).

For task F, Early finish = 11 + 8 = 19

For task G, Early finish = 11 + 5 = 16

Project completion time is the highest time required for activity with no dependent activity. In this case, F takes 19 time period to finish which is more than 3 weeks taken by G. G and F are only 2 activities without any dependents.

Project completion time = 19

In the backward pass,

Late finish (LF) for activities without dependents is always equal to project completion time.

Late finish for F =19

Late finish for G =19

Late start (LS) = Lates finish - Duration of the task

For task F, Late start = 19 - 8= 11

For task G, Late start = 19 - 5= 14

Late finish for C, D & E is 11 the earliest of late start value from its dependents F(11) and G(14).

Late finish for C = 11

Late finish for D = 11

Late finish for E = 11

For task C, Late start = 11 - 3= 8

For task D, Late start = 11 - 6= 5

For task D, Late start = 11 - 2= 9

Late finish for A & B  is 5 the earliest of late start value from its dependents C(8) and D(5) & E(9).

For task A, Late start = 5 - 5= 0

For task B, Late start = 5- 4= 1

Following is the completed Network diagram.

Now slack for the activity is given by Late start (LS) of activity minus Early start (ES) of activity.

Slack = LS - ES

Slack for A = 0-0 = 0

Slack for B = 1-0 = 1

Slack for C = 8-5 = 3

Slack for D = 5-5 = 0

Slack for E = 9-5 = 4

Slack for F = 11-11 = 0

Slack for G = 14-11 = 3

a. Activities which has 0 slack cannot be delayed and hence called critical activities. The string of critical activities is called critics path.

Activities on the critical path are A, D, F.

b. The critical path determines completion time of the Project.

Time for critical path = Project completion time = 5 + 6 + 8 = 19

c.

Slack for A, D, F is 0.

Slack for B is 1

Slack for C & G is 3.

Slack for E is 4.


Related Solutions

Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
Build the network and determine the critical path.
Build the network and determine the critical path.
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Which network path is the critical path of this project?
Which network path is the critical path of this project?
What is the critical path of the network?
What is the critical path of the network?
Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities...
Mark the WRONG statement. A. Some Project networks do not have a critical path. B. Activities on a critical path have a float of zero. C. A delay in critical activity surely delays the completion of project. D. A network can have more than one critical path. E. Each critical activity has identical earliest and the latest start times.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
In the Critical Path Method network diagram, what is unique about the early start and early...
In the Critical Path Method network diagram, what is unique about the early start and early finish date of each node on the critical path?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT