Question

In: Operations Management

Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...

Activity Predecessor Optimistic Most Likely Pessimistic
A 4 7 10
B 2 9 10
C A,B 2 5 8
D C 16 19 28
E C 6 9 24
F E 1 7 13
G C 4 10 28
H D,F 2 5 14
I G,F 5 8 17
J H,I 2 5 8
  1. Determine the expected completion time for each activity.
  2. Construct the AON network for the activities of this contract and determine the critical path for the project.

Solutions

Expert Solution

Expected time of each activity,

Activity to tm tp te=(to+4⋅tm+tp)/6 σ2=(tp-to/6)2
A 4 7 10 7 1
B 2 9 10 8 1.78
C 2 5 8 5 1
D 16 19 28 20 4
E 6 9 24 11 9
F 1 7 13 7 4
G 4 10 28 12 16
H 2 5 14 6 4
I 5 18 17 15.67 4
J 2 5 8 5 1

The earliest and latest expected time for each activity is calculated by considering the expected time te

Activity Immediate Predecessors Duration
A - 7
B - 8
C A,B 5
D C 20
E C 11
F E 7
G C 12
H D,F 6
I G,F 15.67
J H,I 5

Edge and it's preceded and succeeded node

Edge Node1 → Node2
A 1→2
B 1→3
d 2→3
C 3→4
D 4→5
E 4→6
G 4→8
H 5→9
F 6→7
d 7→5
d 7→8
I 8→9
J 9→10

The network diagram for the project, along with activity time, is

Forward Pass Method

E1=0

E2=E1+t1,2 [t1,2=A=7]=0+7=7

E3=Max{Ei+ti,3}[i=1,2]

=Max{E1+t1,3;E2+t2,3}

=Max{0+8;7+0}

=Max{8;7}

=8

E4=E3+t3,4 [t3,4=C=5]=8+5=13

E5=Max{Ei+ti,5}[i=4,7]

=Max{E4+t4,5;E7+t7,5}

=Max{13+20;31+0}

=Max{33;31}

=33

E6=E4+t4,6 [t4,6=E=11]=13+11=24

E7=E6+t6,7 [t6,7=F=7]=24+7=31

E8=Max{Ei+ti,8}[i=4,7]

=Max{E4+t4,8;E7+t7,8}

=Max{13+12;31+0}

=Max{25;31}

=31

E9=Max{Ei+ti,9}[i=5,8]

=Max{E5+t5,9;E8+t8,9}

=Max{33+6;31+15.67}

=Max{39;46.67}

=46.67

E10=E9+t9,10 [t9,10=J=5]=46.67+5=51.67

Backward Pass Method

L10=E10=51.67

L9=L10-t9,10 [t9,10=J=5]=51.67-5=46.67

L8=L9-t8,9 [t8,9=I=15.67]=46.67-15.67=31

L7=Min{Lj-t7,j}[j=8,5]

=Min{L8-t7,8;L5-t7,5}

=Min{31-0;40.67-0}

=Min{31;40.67}

=31

L6=L7-t6,7 [t6,7=F=7]=31-7=24

L5=L9-t5,9 [t5,9=H=6]=46.67-6=40.67

L4=Min{Lj-t4,j}[j=8,6,5]

=Min{L8-t4,8;L6-t4,6;L5-t4,5}

=Min{31-12;24-11;40.67-20}

=Min{19;13;20.67}

=13

L3=L4-t3,4 [t3,4=C=5]=13-5=8

L2=L3-t2,3 [t2,3=d=0]=8-0=8

L1=Min{Lj-t1,j}[j=3,2]

=Min{L3-t1,3;L2-t1,2}

=Min{8-8;8-7}

=Min{0;1}

=0

The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : 1-3-4-6-7-8-9-10 and critical activities are B,C,E,F,d,I,J

The total project time is 51.67

The network diagram for the project, along with E-values and L-values, is

****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please****


Related Solutions

activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000...
Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F 5 B,C 12000 G 3 D,E 7000 H 12 D,E 42000 I 10 F,G 36000 Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made. a) Find the net present value of the project at...
A = [4, 5, 9] B = [-4, 5, -7] C = [2, -7, -8, 5]...
A = [4, 5, 9] B = [-4, 5, -7] C = [2, -7, -8, 5] D = [1, -9, 5, -3] E = [3, 3, -1] Uz = 1/|z| ^z d(X,Y) = (Rθ) d = diameter R = Radius θ = Theta Find a. Uc b. d (D, C) c. Let P = B + 3E, UP = d. A x B e. 3B x E f. C x D
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT