Given the following project:
| 
 Activity  | 
 Predecessor  | 
 Optimistic (day)  | 
 Most Likely (day)  | 
 Pessimistic (day)  | 
| 
 Start  | 
 A, B, C  | 
 -  | 
 -  | 
 -  | 
| 
 A  | 
 D  | 
 38  | 
 50  | 
 62  | 
| 
 B  | 
 E  | 
 90  | 
 99  | 
 108  | 
| 
 C  | 
 End  | 
 85  | 
 100  | 
 115  | 
| 
 D  | 
 F  | 
 19  | 
 25  | 
 31  | 
| 
 E  | 
 End  | 
 91  | 
 100  | 
 115  | 
| 
 F  | 
 End  | 
 62  | 
 65  | 
 68  | 
Critical path method (CPM) is a step-by-step process by which critical and non-critical tasks are defined so that time-frame problems and process bottlenecks are prevented.