Question

In: Operations Management

Given the following project: Activity Predecessor Optimistic (day) Most Likely (day) Pessimistic (day) Start A, B,...

Given the following project:

Activity

Predecessor

Optimistic (day)

Most Likely (day)

Pessimistic (day)

Start

A, B, C

-

-

-

A

D

38

50

62

B

E

90

99

108

C

End

85

100

115

D

F

19

25

31

E

End

91

100

115

F

End

62

65

68

  1. Identify the critical path of the project using activity expected time.
  2. What is the probability that the critical path will be completed in 205 days.

Solutions

Expert Solution

Critical path method (CPM) is a step-by-step process by which critical and non-critical tasks are defined so that time-frame problems and process bottlenecks are prevented.


Related Solutions

Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10...
Consider the following project. Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 a) Calculate mean duration and standard deviation for all the activities using the beta distribution. [4pts]    b) Construct a network...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time...
Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none B 2 5 9 A C 4 6 12 A D 5 6 10 B E 6 10 17 C F 3 4 6 D,E G 3 6 10 D,E H 5 7 10 F I 5 8 11 G J 3 3 3 H,I (a) Calculate the expected completion time for this project. (Round...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
1.The following time estimates are given for an activity: optimistic time = 16 days, most likely...
1.The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 40 days. What is the variance of this activity? Group of answer choices A. 9 B. 16 C. 20 D. 24 E. None of these answers are correct 2.The expected waiting time in line is equal to the expected number of customers in line divided by the arrival rate Group of answer choices True False 3....