Question

In: Statistics and Probability

QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...

QUESTION 7    [18 MARKS)

In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project.

Task

Immediate

Predecessor(s)

Time (days)

Optimistic (a)

Most Likely (m)

Pessimistic (b)

A

None

5

7

12

B

None

8

8

8

C

A

2

6

10

D

A,B

12

14

19

E

C,D

6

6

12

F

B,E

3

12

18

G

F

6

8

10

  1. Construct an activity on node network diagram for this project.                               
  2. If the project is due to be completed in 47 days, what is the probability that this project will be completed on or before the due date?                                                                
  3. If the project manager wants at least a 95% probability that the project will be completed on or before the due date, what is the shortest project time due date that will satisfy the manager?

                                                                                                                                                 

Solutions

Expert Solution

Solution:
Expected time for each activity can be calculated as
Expected time = (O+4*M+P)/6
Variance = ((P-O)^2)/36

Task O M P Expected Time Variance
A 5 7 12 7.5 1.361111111
B 8 8 8 8 0
C 2 6 10 6 1.777777778
D 12 14 19 14.5 1.361111111
E 6 6 12 7 1
F 3 12 18 11.5 6.25
G 6 8 10 8 0.444444444


Paths through which this task can be completed as
A-C-E-F-G with the completion time (7.5+6+7+11.5+8) = 40
A-D-E-F-G with the completion time (7.5+14.5+7+11.5+8) = 48.5
B-D-E-F-G with the completion time (8+14.5+7+11.5+8) = 49.5
B-F-G with the completion time (8+11.5+8) = 27.5
So critical path is B-D-E-F-G with a critical time 49.5 days and Variance = (0+1.36+1+6.25+0.44) = 9.06
Standard deviation = sqrt(9.06) = 3.01
Solution(b)
We need to calculate the probability that the project is due to complete in 47 days
P(X<47) = ?
Here we will use the standard normal distribution, First, we will calculate Z-score which can be calculated as
Z= (47-49.5)/3.01 = -0.83
So from Z table, we found a p-value
P(X<47) = 0.2033
So there is a 20.33% probability that the project is due to be completed in 47 days.
Solution(c)
Given that P-value = 0.95, So Z score from Z table is 1.645
So Due date can be calculated as
Due date = 49.5 + 1.645*3.01 = 49.5 + 5 = 54.5 days
So the shortest project time due date that will satisfy the manager is 54.5 days.


Related Solutions

Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
Given the following project: Activity Predecessor Optimistic (day) Most Likely (day) Pessimistic (day) Start A, B,...
Given the following project: Activity Predecessor Optimistic (day) Most Likely (day) Pessimistic (day) Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 Identify the critical path of the project using activity expected time. What is the probability that the critical path will be completed in 205 days.
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]    f Answer the project manager’s question:...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...
activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 a) Calculate mean duration and standard deviation for all the activities using the beta distribution. [4pts]    b) Construct a network...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT