In: Civil Engineering
Solution –
Answer – False
Explanation –
Under Design – Bid – Build project delivery approach, the owner develops specifications, drawings, and other pre-set information along with an engineer or architect and then bids are invited and contract is awarded.
As we need detailed information prior to bidding process so design and construction phase can’t overlap.
Under Design-Build these two processes can overlap.
Answer – Owner -engineer, Engineer – contractor
Explanation-
Under Design – Bid – Build project delivery approach, the owner develops specifications, drawings, and other pre-set information along with an engineer or architect and then bids are invited and contract is awarded.
So, the flow goes like Owner-Engineer-contractor
So, legal contracts are between owner-engineer and engineer-contractor
Answer – All of these
Explanation –
Under CM@Risk owner will hire a contractor or construction manager (CM) to act as a combined agent or general contractor. A substantial portion of documents are completed and bids are invited and awarded as per merits.
So, CM is responsible for gathering means and materials, quality assurance, payment to subcontractors and safety.
Answer – True
Explanation –
A general contractor is the one who is responsible for gathering all the means and materials, equipments and labour etc. they are also responsible for quality assurance, supervising, and safety.