Question

In: Civil Engineering

A Design-Bid-Build project delivery approach overlaps the design and construction phases, whereas the Design-Build approach requires...

  1. A Design-Bid-Build project delivery approach overlaps the design and construction phases, whereas the Design-Build approach requires each phase to be completed before moving on to the next one.
  1. True
  2. False
  1. Identify ALL that apply: Under the Design-Bid-Build delivery method, there are legal contacts between which of the following.
  1. Owner-Engineer
  2. Owner-Contractor
  3. Engineer-Contractor
  1. Identify ALL that apply: The CM at Risk is responsible for:
  1. Means and Methods
  2. Quality Assurance
  3. Payment to Subcontractors
  4. Safety

  1. A General Contractor must be the employer of the electrical and mechanical trades to be considered a General Contractor.
  1. True
  2. False

Solutions

Expert Solution

Solution –

  1. A Design-Bid-Build project delivery approach overlaps the design and construction phases, whereas the Design-Build approach requires each phase to be completed before moving on to the next one.

Answer – False

Explanation –

Under Design – Bid – Build project delivery approach, the owner develops specifications, drawings, and other pre-set information along with an engineer or architect and then bids are invited and contract is awarded.

As we need detailed information prior to bidding process so design and construction phase can’t overlap.

Under Design-Build these two processes can overlap.

  1. Identify ALL that apply: Under the Design-Bid-Build delivery method, there are legal contacts between which of the following.
  1. Owner-Engineer
  2. Owner-Contractor
  3. Engineer-Contractor

Answer – Owner -engineer, Engineer – contractor

Explanation-

Under Design – Bid – Build project delivery approach, the owner develops specifications, drawings, and other pre-set information along with an engineer or architect and then bids are invited and contract is awarded.

So, the flow goes like Owner-Engineer-contractor

So, legal contracts are between owner-engineer and engineer-contractor

  1. Identify ALL that apply: The CM at Risk is responsible for:
  1. Means and Methods
  2. Quality Assurance
  3. Payment to Subcontractors
  4. Safety

Answer – All of these

Explanation –

Under CM@Risk owner will hire a contractor or construction manager (CM) to act as a combined agent or general contractor. A substantial portion of documents are completed and bids are invited and awarded as per merits.

So, CM is responsible for gathering means and materials, quality assurance, payment to subcontractors and safety.

  1. A General Contractor must be the employer of the electrical and mechanical trades to be considered a General Contractor.
  1. True
  2. False

Answer – True

Explanation –

A general contractor is the one who is responsible for gathering all the means and materials, equipments and labour etc. they are also responsible for quality assurance, supervising, and safety.


Related Solutions

Explain how Design-Bid-Build and Design-Build project delivery methods can differently affect on management of project changes,...
Explain how Design-Bid-Build and Design-Build project delivery methods can differently affect on management of project changes, claims, and disputes (Max 200 words).             
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Using the NPV bid price method, a construction firm submits a bid to build an apartment...
Using the NPV bid price method, a construction firm submits a bid to build an apartment building, wins the bid, and proceeds to complete the building. After the project is completed, the company's CFO is puzzled by the fact that the company lost money on the project. If the CFO used the correct method for calculating the NPV bid price , how could this have happened?
Project management process involves many phases. Construction is one of the phases. Which of the following...
Project management process involves many phases. Construction is one of the phases. Which of the following aspects of the construction phase do you consider as most important as well as most challenging/demanding? Why do you think so? Third party coordination Quality Management Safety management? Please select only one option and justify your response.
The construction department is planning to bid on a large project for the development of a...
The construction department is planning to bid on a large project for the development of a new airport in Chicago area. The following table shows major activities, times, and sequence required: Activity Immediate Predecessor Activity Duration, Months Optimistic Most Likely Pessimistic A - 2 3 4 B A 1 2 3 C A 4 5 12 D A 3 4 11 E B 1 3 5 F C 1 2 3 G D 1 8 9 H E, F 2...
3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The...
3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The cost of the largest construction contract which Smith had previously performed was $78,000. What should the owner do to determine whether or not to let the contract to Smith?
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is...
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is a random variable B with the following mass function: P(B $6,000) .40, P(B $8,000) .30, P(B $11,000) .30. It will cost Alden $6,000 to complete the project. Use each of the decision criteria of this section to determine Alden’s bid. Assume that in case of a tie, Alden wins the bidding. (Hint: Let p Alden’s bid. For p 6,000, 6,000 p 8,000, 8,000 p...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name and explain the three different stages of construction projects development. 3. Name and explain the three different stages of Architectural Design process for construction projects. 4. Name ten (10) different drawings in a set of drawing for a construction project. 5. What is Title Block and what type of information you can find in a Title Block?  
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....