Question

In: Statistics and Probability

Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is...

Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is a random variable B with the following mass function: P(B $6,000) .40, P(B $8,000) .30, P(B $11,000) .30. It will cost Alden $6,000 to complete the project. Use each of the decision criteria of this section to determine Alden’s bid. Assume that in case of a tie, Alden wins the bidding. (Hint: Let p Alden’s bid. For p 6,000, 6,000 p 8,000, 8,000 p 11,000, and p 11,000, determine Alden’s profit in terms of Alden’s bid and Forbes’s bid.)

Solutions

Expert Solution

Let p be the Alden's bid,

For p 6000

Forbes’s bid Probability Alden wins the bid Payoff
$6,000 0.4 Yes p - 6000
$8,000 0.3 Yes p - 6000
$11,000 0.3 Yes p - 6000

Expected payoff = 0.4 * (p - 6000) + 0.3 * (p - 6000) + 0.3 * (p - 6000) = (p - 6000)

Since p 6000, expected payoff is negative or 0 for p = 6000.

For 6000 < p 8000

Forbes’s bid Probability Alden wins the bid Payoff
$6,000 0.4 No 0
$8,000 0.3 Yes p - 6000
$11,000 0.3 Yes p - 6000

Expected payoff = 0.4 * 0 + 0.3 * (p - 6000) + 0.3 * (p - 6000) = 0.6 (p - 6000)

For p = 8000,  Expected payoff = 0.6 * (8000 - 6000) = $1200

For 8000 < p 11000

Forbes’s bid Probability Alden wins the bid Payoff
$6,000 0.4 No 0
$8,000 0.3 No 0
$11,000 0.3 Yes p-6000

Expected payoff = 0.4 * 0 + 0.3 * 0 + 0.3 * (p-6000) = 0.3(p - 6000)

For p = 11000,  Expected payoff = 0.3 * (11000 - 6000) = $1500

For p > 11000

Forbes’s bid Probability Alden wins the bid Payoff
$6,000 0.4 No 0
$8,000 0.3 No 0
$11,000 0.3 No 0

Expected payoff = 0.4 * 0 + 0.3 * 0 + 0.3 * 0 = 0

So, the maximum expected payoff if for p = 11,000.

Thus, Alden’s bid should be $11,000


Related Solutions

The construction department is planning to bid on a large project for the development of a...
The construction department is planning to bid on a large project for the development of a new airport in Chicago area. The following table shows major activities, times, and sequence required: Activity Immediate Predecessor Activity Duration, Months Optimistic Most Likely Pessimistic A - 2 3 4 B A 1 2 3 C A 4 5 12 D A 3 4 11 E B 1 3 5 F C 1 2 3 G D 1 8 9 H E, F 2...
3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The...
3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The cost of the largest construction contract which Smith had previously performed was $78,000. What should the owner do to determine whether or not to let the contract to Smith?
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name and explain the three different stages of construction projects development. 3. Name and explain the three different stages of Architectural Design process for construction projects. 4. Name ten (10) different drawings in a set of drawing for a construction project. 5. What is Title Block and what type of information you can find in a Title Block?  
The Rogers Construction Company is trying to decide whether to make a bid on a project...
The Rogers Construction Company is trying to decide whether to make a bid on a project against 4 competitors. The lowest bid will win the contract and be paid the amount they bid. It believes it will cost the company £10,000 to complete the project (if it wins the contract) and £350 to prepare the bid. Based on historical data, Rogers believes each competitor’s bid has a normal distribution with mean £15,000 and standard deviation £1,500. a) Set up a...
The Adams Construction Company is bidding on a project to install alarge flood drainage culvert from...
The Adams Construction Company is bidding on a project to install alarge flood drainage culvert from Dandridge to a distantlake. The cost and benefits are shown below. Use the Present Worth conventional and modified Benefit-Cost ration method to make a recommendation.Draw Cash Flow Diagram Initial investment = $2 million Right of way maintenance cost = $30,000 per year Major upkeep every six years = $50,000 Annual benefits to the taxpayers = $135,000 per year Life of the project = 12...
Nasee construction Co. is analyzing the probability of a bidding for the construction of. a new...
Nasee construction Co. is analyzing the probability of a bidding for the construction of. a new building. In the past, Nasee's main competitor, Nana construction Co. has submitted bids 90% of the time. if NANA bids on a project, the probability that NASEE will get the project is 10%. However, if NANA does not bid on a project, NASEE's probability of getting the project increases to 70%. if NASEE gets the project, what is the probability that NANA did not...
Nasee construction Co. is analyzing the probability of a bidding for the construction of. a new...
Nasee construction Co. is analyzing the probability of a bidding for the construction of. a new building. In the past, Nasee's main competitor, Nana construction Co. has submitted bids 70% of the time. if NANA bids on a project, the probability that NASEE will get the project is 20%. However, if NANA does not bid on a project, NASEE's probability of getting the project increases to 80%. if NASEE gets the project, what is the probability that NANA did not...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from other contractors can be described by the following probability distributions: Contractor A: Uniform probability distribution between $500,000 and $1,000,000. Contractor B: Normal probability distribution with a mean bid of $700,000 and a standard deviation of $100,000. a. If Johnson Company submits a bid of $750,000, what is the probability Butler will...
In auction​ bidding, the​ "winner's curse" is the phenomenon of the winning​ (or highest) bid price...
In auction​ bidding, the​ "winner's curse" is the phenomenon of the winning​ (or highest) bid price being above the expected value of the item being auctioned. A study was conducted to see if​less-experienced bidders were more likely to be impacted by the curse than​ super-experienced bidders. The study showed that of the 188 bids by​ super-experienced bidders, 25 winning bids were above the​ item's expected​ value, and of the bids by the 140 less-experienced bidders, 31 winning bids were above...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT