Question

In: Operations Management

The construction department is planning to bid on a large project for the development of a...

The construction department is planning to bid on a large project for the development of a new airport in Chicago area. The following table shows major activities, times, and sequence required:

Activity

Immediate Predecessor

Activity Duration, Months

Optimistic

Most Likely

Pessimistic

A

-

2

3

4

B

A

1

2

3

C

A

4

5

12

D

A

3

4

11

E

B

1

3

5

F

C

1

2

3

G

D

1

8

9

H

E, F

2

4

6

I

H

2

4

12

J

G

3

4

5

K

I, J

5

7

9

  1. *Draw the network diagram, using appropriate technology and the nomenclature that is used in the solved Exercise for this Chapter.
  2. Determine the expected time (Te) and the variance for each activity.
  3. *Determine and show the early start, early finish, late start and late finish for each activity (use the nomenclature used in the solved Exercise).
  4. Determine the critical path and the expected project completion time.
  5. What is the probability that the project can be completed in:
    1. 25 months
    2. 30 months
  6. There is a 85% chance that the project can be completed in X months or less. What is X?

*For problems A and C, the textbook focused on the Critical Path Method (AON Network/PERT Chart).

Solutions

Expert Solution

a.

b.c.

Formula

d. Critical path is A-C-F-H-I-K as all the activities have 0 slack.

Expected project duration = Duration of critical path = 27 months
e.

project variation = sum of variations of critical activities

We know, Z = (Required project completion time-expected project completion time)/project standard deviation

When Required project completion time = 25 months,

Z = (25-27)/sqrt(5.666666667) = -0.84016805

Corresponding probability = norm.s.dist(-0.84016805,TRUE) = 0.200407085 = probability of completing the project within 25 months

When Required project completion time = 30 months,

Z = (30-27)/sqrt(5.666666667) = 1.260252076

Corresponding probability = norm.s.dist(1.260252076,TRUE) = 0.896210779 = probability of completing the project within 30 months

f.

Z score for 85% probability = normsinv(0.85) = 1.036433389

We know, Z = (Required project completion time-expected project completion time)/project standard deviation

or, 1.036433389 =(Required project completion time-27)/sqrt(5.666666667)

or, Required project completion time = sqrt(5.666666667)*1.036433389+27 = 29.46720496 months (Answer)


Related Solutions

3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The...
3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The cost of the largest construction contract which Smith had previously performed was $78,000. What should the owner do to determine whether or not to let the contract to Smith?
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is...
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is a random variable B with the following mass function: P(B $6,000) .40, P(B $8,000) .30, P(B $11,000) .30. It will cost Alden $6,000 to complete the project. Use each of the decision criteria of this section to determine Alden’s bid. Assume that in case of a tie, Alden wins the bidding. (Hint: Let p Alden’s bid. For p 6,000, 6,000 p 8,000, 8,000 p...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name and explain the three different stages of construction projects development. 3. Name and explain the three different stages of Architectural Design process for construction projects. 4. Name ten (10) different drawings in a set of drawing for a construction project. 5. What is Title Block and what type of information you can find in a Title Block?  
The Research & Development Department of Large Mart is currently working on the development of a...
The Research & Development Department of Large Mart is currently working on the development of a “study pillow” that allows students to upload study material into their brain whilst sleeping. In order to complete this project, Large Mart has purchased the following items: A car (which is used to transport students participating in a trial of the study pillow to the laboratory) A notebook computer (which is used to record the feedback of students participating in the trial) The car...
The Rogers Construction Company is trying to decide whether to make a bid on a project...
The Rogers Construction Company is trying to decide whether to make a bid on a project against 4 competitors. The lowest bid will win the contract and be paid the amount they bid. It believes it will cost the company £10,000 to complete the project (if it wins the contract) and £350 to prepare the bid. Based on historical data, Rogers believes each competitor’s bid has a normal distribution with mean £15,000 and standard deviation £1,500. a) Set up a...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from other contractors can be described by the following probability distributions: Contractor A: Uniform probability distribution between $500,000 and $1,000,000. Contractor B: Normal probability distribution with a mean bid of $700,000 and a standard deviation of $100,000. a. If Johnson Company submits a bid of $750,000, what is the probability Butler will...
Journal entries The Research & Development Department of Large Mart is currently working on the development...
Journal entries The Research & Development Department of Large Mart is currently working on the development of a “study pillow” that allows students to upload study material into their brain whilst sleeping. In order to complete this project, Large Mart has purchased the following items: • A minibus (which is used to transport students participating in a trial of the study pillow to the laboratory) • A video camera (which is used to record the feedback of students participating in...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
Suppose that you work in the inventory planning department of a large electronics store, and a...
Suppose that you work in the inventory planning department of a large electronics store, and a (Q, R) inventory system is used to control the replenishment of a popular LCD computer monitor. The store pays $85 for each monitor when it purchases the monitors from its supplier in Asia; in addition, a fixed setup fee of $275 is charged for each order. Assume the annual holding rate is 15%. The penalty cost per shortage is $10. Monthly demand is normally...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT