Question

In: Civil Engineering

3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The...

3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The cost of the largest construction contract which Smith had previously performed was $78,000. What should the owner do to determine whether or not to let the contract to Smith?

Solutions

Expert Solution


Related Solutions

The construction department is planning to bid on a large project for the development of a...
The construction department is planning to bid on a large project for the development of a new airport in Chicago area. The following table shows major activities, times, and sequence required: Activity Immediate Predecessor Activity Duration, Months Optimistic Most Likely Pessimistic A - 2 3 4 B A 1 2 3 C A 4 5 12 D A 3 4 11 E B 1 3 5 F C 1 2 3 G D 1 8 9 H E, F 2...
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is...
Alden Construction is bidding against Forbes Construction for a project. Alden believes that Forbes’s bid is a random variable B with the following mass function: P(B $6,000) .40, P(B $8,000) .30, P(B $11,000) .30. It will cost Alden $6,000 to complete the project. Use each of the decision criteria of this section to determine Alden’s bid. Assume that in case of a tie, Alden wins the bidding. (Hint: Let p Alden’s bid. For p 6,000, 6,000 p 8,000, 8,000 p...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name...
Construction Documents 1. What is included in a Bid Package for a construction project? 2. Name and explain the three different stages of construction projects development. 3. Name and explain the three different stages of Architectural Design process for construction projects. 4. Name ten (10) different drawings in a set of drawing for a construction project. 5. What is Title Block and what type of information you can find in a Title Block?  
The Rogers Construction Company is trying to decide whether to make a bid on a project...
The Rogers Construction Company is trying to decide whether to make a bid on a project against 4 competitors. The lowest bid will win the contract and be paid the amount they bid. It believes it will cost the company £10,000 to complete the project (if it wins the contract) and £350 to prepare the bid. Based on historical data, Rogers believes each competitor’s bid has a normal distribution with mean £15,000 and standard deviation £1,500. a) Set up a...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from other contractors can be described by the following probability distributions: Contractor A: Uniform probability distribution between $500,000 and $1,000,000. Contractor B: Normal probability distribution with a mean bid of $700,000 and a standard deviation of $100,000. a. If Johnson Company submits a bid of $750,000, what is the probability Butler will...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
Provide 3 types of construction permits may be required in a construction project and elaborate on...
Provide 3 types of construction permits may be required in a construction project and elaborate on their impact on the construction schedule.
Using the NPV bid price method, a construction firm submits a bid to build an apartment...
Using the NPV bid price method, a construction firm submits a bid to build an apartment building, wins the bid, and proceeds to complete the building. After the project is completed, the company's CFO is puzzled by the fact that the company lost money on the project. If the CFO used the correct method for calculating the NPV bid price , how could this have happened?
A Design-Bid-Build project delivery approach overlaps the design and construction phases, whereas the Design-Build approach requires...
A Design-Bid-Build project delivery approach overlaps the design and construction phases, whereas the Design-Build approach requires each phase to be completed before moving on to the next one. True False Identify ALL that apply: Under the Design-Bid-Build delivery method, there are legal contacts between which of the following. Owner-Engineer Owner-Contractor Engineer-Contractor Identify ALL that apply: The CM at Risk is responsible for: Means and Methods Quality Assurance Payment to Subcontractors Safety A General Contractor must be the employer of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT