In: Accounting
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.
Gross Profit 2020 and 2021
Calculate gross profit
2020 | 2021 | |
Cost incurred | 486500 | 1000000 |
Estimated cost to complete | 903500 | 0 |
Percentage completion | 35% | 100% |
Revenue recognized |
1700000*35% = 595000 |
1700000 |
Cost incurred | -486500 | -1000000 |
Profit | 108500 | 700000 |
Profit for previous year | 0 | -108500 |
Gross profit for this year | 108500 | 591500 |