Question

In: Accounting

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Gross Profit 2020 and 2021

Solutions

Expert Solution

Calculate gross profit

2020 2021
Cost incurred 486500 1000000
Estimated cost to complete 903500 0
Percentage completion 35% 100%
Revenue recognized

1700000*35% = 595000

1700000
Cost incurred -486500 -1000000
Profit 108500 700000
Profit for previous year 0 -108500
Gross profit for this year 108500 591500

Related Solutions

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016   Costs incurred during the year $ 399,000 $1,060,000      Estimated costs to complete 931,000 0      Billings during the year 485,000 1,330,000      Cash collections during the year 385,000 1,430,000    Required information Assume that Beavis recognizes revenue on this contract over time...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:                                                                                     2012                           2013 Costs incurred during the year                               $450,000                $ 1.100,000 Estimated costs to complete 1,050,000                      0 Billings during the year                                            400,000                    1,400,000 Cash collections during the year                             300,000                     1,500,000 Assume that Beavis uses the percentage- of- completion method for...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,720,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $ 411,000 $1,020,000 Estimated costs to complete 959,000 0 Billings during the year 465,000 1,310,000 Cash collections during the year 365,000 1,410,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required:...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                           2017                           2018 Costs incurred during the year                    $ 450,000                  $1,100,000 Estimated costs to complete                       1,050,000                                  0 Billings during the year                                 400,000                    1,400,000 Cash collections during the year                    300,000                    1,500,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT