Question

In: Operations Management

Two possible projects have beenidentified for potential selection (i.e., Project 1 or Project 2).These...

Two possible projects have been identified for potential selection (i.e., Project 1 or Project 2). These projects should be evaluated based on the following criteria: Strategic fit; Probability of technical success; Financial risk; Potential profit; Strategic leverage; and Recommendations. Using the weighted scoring model and the information provided below, determine which project you should pursue:

Criteria Weight Project 1 Project 2 Strategic fit Probability of technical success 25% 65 90 20% 90 65 Financial risk 10% 40

The weighted project score forProject 1 was calculated to be68.25 (you should check this value to verify that your method is correct).

  • Using the information, evaluate the following:

  1. Weighted Score for Project 2 (to the “hundredth” decimal place). Please show your hand calculations forProject 2. NOTE: You may solve this problem manually. If you do, please show your calculations for Project 2 below. If you choose to use Excel, please upload your spreadsheet to Canvas.

  2. Which project would you choose, and why?


Solutions

Expert Solution

Weighted Score for project 1 = (0.25*65 + 0.2*90 + 0.1*40 + 0.15*85 + 0.25*55 + 0.5*70)

= (16.25 + 18 + 4 + 12.75 + 13.75 + 3.5)

= 68.25

a. Weighted Score for project 2 = (0.25*90 + 0.2*65 + 0.1*80 + 0.15*55 + 0.25*75 + 0.5*80)

= (22.5 + 13 + 8 + 8.25 + 13.75 + 4)

= 69.5

b. I would choose project 2 because of the high weighted score for the same.


Related Solutions

2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW 1 $95,000 $112,000 2 $150,000 $95,000 3 $10,000 $85,000 4 $12,000 $65,000 5 $45,000 $10,000 6 $198,000 $15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5%. A) Calculate the payback period for each project. State if payback is acceptable for each project and state why. B) Calculate the NPV for each project. State if NPV is acceptable for each...
You have two potential investment projects, Project A and Project B. You can take one, but...
You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are: Year 0 1 2 3 Project A Cash Flow -$50,000 $45,000 $5,000 $5,000 Project B Cash Flow -$50,000 $5,000 $5,000 $50,000 a. Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%.   Which project would you take, and why? c)  Compute the NPV for each...
Two energy saving project have been identified by Company ABC. These potential projects are known as...
Two energy saving project have been identified by Company ABC. These potential projects are known as project A and 8 . The projects require different investments and costs as indicated in the Table below .. Financial item OPTION A (million) OPTION B (million) First cost 5000 700 Economic life in years 10 5 Salvage value 100 150 Annual operating costs 5 10 Major overhaul costs in year 5 20 0 Increase in annual operating costs from year and thereafter 1.5...
Suppose there are two potential projects for investment. Project 1 has a certain payoff of $50...
Suppose there are two potential projects for investment. Project 1 has a certain payoff of $50 in one year, while project 2 has a 50% chance of generating $100 in one year, and another 50% chance of generating $0 in one year. Suppose the company has an outstanding debt = $50. (1)Which project will shareholders prefer? Justify your answer. (2)Which project will debt holders prefer? Justify your answer. (3)Which project will the financial manager prefer? Justify your answer.
IT Project Management: Ch4 1) How are potential projects identified? 2) What are the methods for...
IT Project Management: Ch4 1) How are potential projects identified? 2) What are the methods for categorizing Information Technology projects?
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B....
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                          CASHFLOW                           CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $10,000                                   $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $ 15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5% A.  Calculate the payback period for each project.  State if payback is acceptable for each project and state why. B.  Calculate the NPV for each project.  State if NPV is acceptable for each project and state why. C.  Calculate the IRR for each project.  State if IRR is acceptable for each project and...
DGO Corporation has to decide whether to undertake project 1 or project 2. The projects have...
DGO Corporation has to decide whether to undertake project 1 or project 2. The projects have the following initial investments and future net revenues: . Project 1 Project 2 Initial investment $34,000 $40,000 Net revenue in 2021 $25,000 $35,000 Net revenue in 2022 $30,000 $45,000 Using IP method and a discount rate of 12%, which project would you recommend? Why or why not. This in reference  to Profitability Index
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT