In: Finance
Two energy saving project have been identified by Company ABC.
These potential projects are known as project
A and 8 . The projects require different investments and costs as
indicated in the Table below ..
| Financial item | OPTION A (million) | OPTION B (million) | 
| First cost | 5000 | 700 | 
| Economic life in years | 10 | 5 | 
| Salvage value | 100 | 150 | 
| Annual operating costs | 5 | 10 | 
| Major overhaul costs in year 5 | 20 | 0 | 
| Increase in annual operating costs from year and thereafter | 1.5 | 2 | 
| Penalty costs due to environmental pollution  | 
2 from year five and thereafter | 1 annually from year 2 to 5 and thereafter | 
| Savings in annual energy costs | 250 | 300 | 
Company ABC would like to know which project is worth pursuing.
Use an internal rate of return method to
establish the most viable project
Cash flow = Savings in annual energy costs - first cost - annual operating cost - penalty cost - major overhaul cost + salvage value
Option A cash flows:
| Year (n) | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 
| First cost | (5,000) | ||||||||||
| Savings in annual energy costs | 250 | 250 | 250 | 250 | 250 | 250 | 250 | 250 | 250 | 250 | |
| Annual operating cost with increases | (5.00) | (6.50) | (8.00) | (9.50) | (11.00) | (12.50) | (14.00) | (15.50) | (17.00) | (18.50) | |
| Penalty costs | (2) | (2) | (2) | (2) | (2) | (2) | |||||
| Major overhaul costs | (20) | ||||||||||
| Salvage value | 100 | ||||||||||
| Cash flow (CF) | (5,000) | 245 | 244 | 242 | 241 | 217 | 236 | 234 | 233 | 231 | 330 | 
| IRR | -10.98% | 
Option B cash flows:
| Year (n) | 0 | 1 | 2 | 3 | 4 | 5 | 
| First cost | (700) | |||||
| Savings in annual energy costs | 300 | 300 | 300 | 300 | 300 | |
| Annual operating cost with increases | (10.00) | (12.00) | (14.00) | (16.00) | (18.00) | |
| Penalty costs | (1) | (1) | (1) | (1) | ||
| Salvage value | 150 | |||||
| Cash flow (CF) | (700) | 290 | 287 | 285 | 283 | 431 | 
| IRR | 29.80% | 
IRR for project A = -10.98%
IRR for project B = 29.80%
Project B is the only viable project.
Note: It is not mentioned from year the annual operating costs are increasing. It has been assumed that operating costs start increasing from year 2 onwards.