Question

In: Finance

You have two potential investment projects, Project A and Project B. You can take one, but...

You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are:

Year

0

1

2

3

Project A Cash Flow

-$50,000

$45,000

$5,000

$5,000

Project B Cash Flow

-$50,000

$5,000

$5,000

$50,000

a. Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%.   Which project would you take, and why? c)  Compute the NPV for each project if the appropriate discount rate is 10%. Which project would you take, and why? d) Summarize the principles demonstrated by this problem.

Solutions

Expert Solution

Using excel to calculate IRR and NPV at 5% and NPV at 10%

A B
Year Project A Project B
1 0 -50000 -50000
2 1 45000 5000
3 2 5000 5000
4 3 5000 50000
NPV at 5% $1,711.48 $2,488.93
Using excel formula NPV(0.05,A2:A5)+A1 NPV(0.05,B2:B5)+B1
IRR 7.87% 6.89%
Using excel formula IRR(A1:A7) IRR(B1:B7)
NPV at 10% -$1,202.10 -$3,756.57
Using excel formula NPV(0.1,A2:A5)+A1 NPV(0.1,B2:B5)+B1


at 5% Project B should be Chosen Because NPV of B is higher than NPV of A
at 10% Project A should be Chosen Because NPV of A is higher than NPV of B


d) The NPV is preferred over IRR because it is more accurate.
NPV can be different at different discount rates and hence decision changes with discount rate. The cross over rate is the Rate at which NPV is same. Above that rate some projects are accepted and some are rejected.

Please Discuss in case of Doubt

Best of Luck. God Bless
Please Rate Well


Related Solutions

Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000....
Suppose that you have the two projects as below: Project B. Project A Year 200. 1,000. 1 600. 800. 2 800. 600. 3 1,200. 200. 4 Each project has a cost of $ 2,000 and the total cost of capital is 10%. Determine which project should be accepted ?Using Net present value (NPV)
Suppose there are two potential projects for investment. Project 1 has a certain payoff of $50...
Suppose there are two potential projects for investment. Project 1 has a certain payoff of $50 in one year, while project 2 has a 50% chance of generating $100 in one year, and another 50% chance of generating $0 in one year. Suppose the company has an outstanding debt = $50. (1)Which project will shareholders prefer? Justify your answer. (2)Which project will debt holders prefer? Justify your answer. (3)Which project will the financial manager prefer? Justify your answer.
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
you have $100 to invest in two different investment projects, A and B, the total returns...
you have $100 to invest in two different investment projects, A and B, the total returns from which (TR and TR) are given below. the cost of purchasing a unit of investment in each project is $10 per unit. your problem is to invest the $100 in the two invest the $100 in the two investments so as to maximize your total return (for example, if you invested the entire $100 in investment B, you would receive a total return...
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.9%. The cash flows for the two projects are as follows​ ($ million): Project   Year 0   Year 1   Year 2   Year 3   Year 4   A -$103 28 34 44 53 B -$103 53 44 34 24 What is the IRR of each project? Which project should you choose? Select one: a. IRR of Project A = 17.7%, IRR of Project B = 21.7%....
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.1%. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$100 $27 $32 $39 $52 B −$100 $52 $39 $32 $22 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At what cost of capital...
You are considering the following two projects and can only take one. Your cost of capital...
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At what cost of...
You are considering the following two projects and can only take one. Your cost of capital...
You are considering the following two projects and can only take one. Your cost of capital is 11.2 %11.2%. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$100 $27 $30 $42 $52 B $100 $ 52 $ 42 $ 30 $21 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At...
Two possible projects have beenidentified for potential selection (i.e., Project 1 or Project 2).These...
Two possible projects have been identified for potential selection (i.e., Project 1 or Project 2). These projects should be evaluated based on the following criteria: Strategic fit; Probability of technical success; Financial risk; Potential profit; Strategic leverage; and Recommendations. Using the weighted scoring model and the information provided below, determine which project you should pursue:The weighted project score forProject 1 was calculated to be68.25 (you should check this value to verify that your method is correct).Using the information, evaluate the...
You are considering an investment in two projects, A and B. Both projects will cost $115,000,...
You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows: YEAR PROJECT A PROJECT B 1 $7,188    $51,750 2 $21,562    $38,812 3 $40,250    $28,750 4 $50,315    $21,563 5    $57,500 $14,375 Using Excel and show formulas a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT