In: Finance
You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are:
Year |
0 |
1 |
2 |
3 |
Project A Cash Flow |
-$50,000 |
$45,000 |
$5,000 |
$5,000 |
Project B Cash Flow |
-$50,000 |
$5,000 |
$5,000 |
$50,000 |
a. Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%. Which project would you take, and why? c) Compute the NPV for each project if the appropriate discount rate is 10%. Which project would you take, and why? d) Summarize the principles demonstrated by this problem.
Using excel to calculate IRR and NPV at 5% and NPV at 10%
A | B | ||
Year | Project A | Project B | |
1 | 0 | -50000 | -50000 |
2 | 1 | 45000 | 5000 |
3 | 2 | 5000 | 5000 |
4 | 3 | 5000 | 50000 |
NPV at 5% | $1,711.48 | $2,488.93 | |
Using excel formula | NPV(0.05,A2:A5)+A1 | NPV(0.05,B2:B5)+B1 | |
IRR | 7.87% | 6.89% | |
Using excel formula | IRR(A1:A7) | IRR(B1:B7) | |
NPV at 10% | -$1,202.10 | -$3,756.57 | |
Using excel formula | NPV(0.1,A2:A5)+A1 | NPV(0.1,B2:B5)+B1 |
at 5% Project B should be Chosen Because NPV of B is higher than
NPV of A
at 10% Project A should be Chosen Because NPV of A is higher than
NPV of B
d) The NPV is preferred over IRR because it is more accurate.
NPV can be different at different discount rates and hence decision
changes with discount rate. The cross over rate is the Rate at
which NPV is same. Above that rate some projects are accepted and
some are rejected.
Please Discuss in case of Doubt
Best
of Luck. God Bless
Please Rate Well