Question

In: Finance

2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                

2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS

                                                            PROJECT 1                            PROJECT 2

YEAR                                                                         CASHFLOW                          CASHFLOW

   1                                                                               $95,000                                   $112,000

   2                                                                               $150,000                                 $95,000

   3                                                                               $1,000                                     $85,000

   4                                                                               $12,000                                   $65,000

   5                                                                               $45,000                                   $10,000

   6                                                                               $198,000                                 $15,000

BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5%

A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY.

B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER NPV AND WHY.

C. CALCULATE THE IRR FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER IRR AND WHY.

D. CALCULATE THE PI FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PI AND WHY.

E. STATE WHICH IS THE BEST PROJECT OVERALL AND WHY.

Solutions

Expert Solution

A)

If projects are independent , Under payback both projects are acceptable as both projects have payback < cut off period. If projects are mutually exclusive Project 2 will be accepted as it has a lower payback period.

b)

If projects are independent, both projects will be accepted under NPV rule because NPV > 0 for both projects. If projects are mutually exclusive,then Project 1 will be accepted due to higher NPV

c)

If projects are independent, both projects will be accepted as their IRR> Cost of capital. If mutually exclusive, Project 1 will be chosen due to higher IRR.

d)

If projects are independent, using PI rule both projects will be accepted as their PI >1 . If mutually exclusive, then Project 1 will be accepted due to higher PI.

e)

Overall the best project is Project 1 as it has better NPV, IRR and PI than project 2

Formulae


Related Solutions

2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B. CALCULATE THE NPV FOR EACH PROJECT. STATE IF...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                         CASHFLOW                          CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $1,000                                     $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $15,000 BOTH PROJECTS HAVE A COST OF $300,000. THE COST OF CAPITAL IS 9.5% A. CALCULATE THE PAYBACK FOR EACH PROJECT. STATE IF THE PROJECT IS ACCEPTABLE UNDER PAYBACK AND WHY. B....
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS                                                             PROJECT 1                            PROJECT 2 YEAR                                                                          CASHFLOW                           CASHFLOW    1                                                                               $95,000                                   $112,000    2                                                                               $150,000                                 $95,000    3                                                                               $10,000                                   $85,000    4                                                                               $12,000                                   $65,000    5                                                                               $45,000                                   $10,000    6                                                                               $198,000                                 $ 15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5% A.  Calculate the payback period for each project.  State if payback is acceptable for each project and state why. B.  Calculate the NPV for each project.  State if NPV is acceptable for each project and state why. C.  Calculate the IRR for each project.  State if IRR is acceptable for each project and...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW...
2 POTENTIAL CAPITAL PROJECTS HAVE THE FOLLOWING ESTIMATED CASHFLOWS PROJECT 1 PROJECT 2 YEAR CASHFLOW CASHFLOW 1 $95,000 $112,000 2 $150,000 $95,000 3 $10,000 $85,000 4 $12,000 $65,000 5 $45,000 $10,000 6 $198,000 $15,000 BOTH PROJECTS HAVE A COST OF $275,000. THE COST OF CAPITAL IS 11.5%. A) Calculate the payback period for each project. State if payback is acceptable for each project and state why. B) Calculate the NPV for each project. State if NPV is acceptable for each...
The estimated cashflows for two mutually exclusive projects are shown below. (A) Using a cost of...
The estimated cashflows for two mutually exclusive projects are shown below. (A) Using a cost of capital of 14%, which project should be taken based on the NPV amounts? (B) Calculate the IRR for both projects.  Based on the IRR amounts, which project should be taken? (C) Why are your answer to parts A and B not the same? (D) Using a cost of capital of 17%, which project should be taken based on the NPV amounts? (E) Create an NPV...
Mr tan is considering 2 potential investment projects that have similar capital requirements: Year 0 year...
Mr tan is considering 2 potential investment projects that have similar capital requirements: Year 0 year 1 year 2 year 3 year 4 project A 4,000,000 1,600,000 1,800,000 2,000,000 2,100,000 Project B 4,200,000 500,000 1,700,000 1,900,000 2,000,000 For project A,the company cost of capital is 14%.For project B,assessed as the riskier project of the two.,a risk adjusted cost of capital of 15% is considered appropriate. 1) calculate the NPV of the 2 projects and assess the projects using the investment...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections. Cash Flow Project A Project B Project C Investment Cost ($400,000) ($375,000) ($400,000) Year One Cash Flow $200,000 $75,000 $50,000 Year Two Cash Flow $50,000 $75,000 $120,000 Year Three Cash Flow $75,000 $85,000 $140,000 Year Four Cash Flow $50,000 $225,000 $125,000 Year Five Cash Flow $125,000 $60,000 $125,000 1.Calculate the Internal Rate of Return (IRR) for each project. 2.Assuming your...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections. Cash Flow Project A Project B Project C Investment Cost ($400,000) ($375,000) ($400,000) Year One Cash Flow $200,000 $75,000 $50,000 Year Two Cash Flow $50,000 $75,000 $120,000 Year Three Cash Flow $75,000 $85,000 $140,000 Year Four Cash Flow $50,000 $225,000 $125,000 Year Five Cash Flow $125,000 $60,000 $125,000 1.Calculate the Payback Period for each project. 2.If the discount rate for...
Your firm has estimated the following cash flows for two mutually exclusive capital investment projects. The...
Your firm has estimated the following cash flows for two mutually exclusive capital investment projects. The firm's required rate of return is 13%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 -$100,000 -$100,000 1 28,900 48,000 2 28,900 40,000 3 28,900 40,000 4 28,900 5 28,900 Which of the following statements best describes projects A and B? a) Project A should be accepted because it has the highest NPV. b)...
Should firms reassess their cost of capital as they assess potential projects or acquisitions?
Should firms reassess their cost of capital as they assess potential projects or acquisitions?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT