Question

In: Accounting

You are the manager of a project to improve the billing process at your firm. The...

You are the manager of a project to improve the billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1600 per week, and penalty costs are $1200 per week after week 12.

a- What is the minimum-cost schedule for this project?

b- What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part a. Please show work in POM QM as well as outlining the answer.

Activity Normal Time Normal Cost Crash Time (Days) Crash Cost ($) Immediate Predecessors
a 6 $1000 5 $1200 ---
b 4 800 2 2000 ---
c 3 600 2 900 a, b
d 2 1500 1 2000 b
e 6 900 4 1200 c, d
f 2 1300 1 1400 e
g 4 900 4 900 e
h 4 500 2 900 g

Solutions

Expert Solution


Related Solutions

You are the manager of a project to improve the healthcare insurance claims auditing process.  For each...
You are the manager of a project to improve the healthcare insurance claims auditing process.  For each day that the claims auditing process takes, there is an associated cost of $1,700 so this cost is saved for each day reduction in the project completion time.  Following is the information for the healthcare claims auditing process. The normal time and crash time are the times it will take to complete each activity under each of those scenarios (normal and crash).  The Total Normal Cost...
As the project manager for a not-for-profit organization, you were notified that your proposal to improve...
As the project manager for a not-for-profit organization, you were notified that your proposal to improve the safety of the Lafayette Park in Los Angeles was approved. You and your team will receive funding for $50,000. Please prepare a positive letter informing your team members and outline the safety improvements you propose to be implemented. Prepare this into a Positive Letter.
Pretend you are a project manager employed by a General Contracting firm. Your company is currently...
Pretend you are a project manager employed by a General Contracting firm. Your company is currently serving as a Construction Manager at Risk for a project and is requiring all vendors, material suppliers and subcontractors to submit digital design files. Provide 4 strategies you may implement to facilitate interoperability issues. Provide detailed descriptions of each strategy
You are now the manager of your favorite grocery store. Your job is to improve the...
You are now the manager of your favorite grocery store. Your job is to improve the store aesthetics and products to make sure that more shoppers come in to shop. You are asked to come up with a regression analysis to answer this question: If you were to run a logistic regression analysis, what would your dependent variable be? What would the 1, 0 indicate?
You are now the manager of your favorite grocery store. Your job is to improve the...
You are now the manager of your favorite grocery store. Your job is to improve the store aesthetics and products to make sure that more shoppers come in to shop. You are asked to come up with a regression analysis to answer this question: What are the differences between how you would interpret the normal regression and logistic regression when it comes down to (i) fit of the model, (ii) results of the regression (IV)
You are employed as an assistant project manager for a large firm that specializes in the...
You are employed as an assistant project manager for a large firm that specializes in the construction of commercial buildings throughout the Southeast. You recently finished work on a large bank building in Birmingham, Alabama, and are now working in the main office in Atlanta where you are heavily involved in estimating. The company is very safety conscious. This awareness is reflected in the firm’s injury incidence rate which is about 1/6th of the national average for this type of...
Describe the process of billing and collections.
Describe the process of billing and collections.
A project for improving a billing process has the following precedence relationships and activity​ times: Using...
A project for improving a billing process has the following precedence relationships and activity​ times: Using the info below calculate the slack for each activity. Which activities are on the critical path?                                                                                                           Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 5 ---- B 10 ----- C 6 A D 14 ​B, C E 9 B F 5 D G 3 E H 6 ​F, G
What is “process capability”? How can a firm generally improve process capability?
What is “process capability”? How can a firm generally improve process capability?
As a programmer in a java project, you have been asked by your project manager to...
As a programmer in a java project, you have been asked by your project manager to describe the most efficient way to store the following assigned numbers 10,20,30,1000,200,350 for an operation which involves on calculation such as sum and average.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT