In: Accounting
You are the manager of a project to improve the billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1600 per week, and penalty costs are $1200 per week after week 12.
a- What is the minimum-cost schedule for this project?
b- What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part a. Please show work in POM QM as well as outlining the answer.
Activity | Normal Time | Normal Cost | Crash Time (Days) | Crash Cost ($) | Immediate Predecessors |
---|---|---|---|---|---|
a | 6 | $1000 | 5 | $1200 | --- |
b | 4 | 800 | 2 | 2000 | --- |
c | 3 | 600 | 2 | 900 | a, b |
d | 2 | 1500 | 1 | 2000 | b |
e | 6 | 900 | 4 | 1200 | c, d |
f | 2 | 1300 | 1 | 1400 | e |
g | 4 | 900 | 4 | 900 | e |
h | 4 | 500 | 2 | 900 | g |