Question

In: Accounting

During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available.

2017

2018

2019

Costs incurred to date $366,300 $831,440 $1,067,000
Estimated costs to complete 623,700 262,560 –0–
Billings to date 297,000 894,000 1,590,000
Collections to date 270,000 816,000 1,417,000

a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit in 2017

Gross profit in 2018

Gross profit in 2019

b) Prepare all necessary journal entries for 2018.

Dr. Construction in Process

Cr. Materials, Cash, Payables

--

Dr. Accounts Receivable

Cr. Billings on Construction in Process

--

Dr. Cash

Cr. Accounts Receivable

--

Dr. Construction in Process

Dr. Construction Expense

Cr. Revenue from Long Term Contracts

c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2017

2018

2019

Solutions

Expert Solution

Ans.1
Particulars 2017 2018 2019
Contract price 1590000 1590000 1590000
Costs:
Cost to date 366300 831440 1067000
Estimated costs to complete 623700 262560 0
Total cost 990000 1094000 1067000
Total estimated profit 600000 496000 523000
Percentage completed to date 37% 76% 100%
Total gross profit recognized 222000 376960 523000
Less: Gross profit recongnize in last year 0 222000 376960
Gross profit of current year 222000 154960 146040
*Percentage completed to date = Cost to date / Total cost * 100
*Total estmated profit = Contract price - Total cost
*Total gross profit recognized = Total estimated profit * percentage completed to date
Ans.b Particulars Debit Credit
Dr. Construction in process 465140
Cr. Materials, Cash, Payables 465140
(831440 - 366300)
Dr. Accounts Receivable 597000
Cr. Billings on Construction in process 597000
(894000 - 297000)
Dr. Cash 546000
Cr. Accounts Receivable 546000
(816000 - 270000)
Dr. Construction in process 465140
Dr. Construction Expense 154960
Cr. Revenue from Long term contracts 620100
(1590000 * (76%-37%)
Ans.c Gross Profit under completed contract method:
2017 0
2018 0
2019 523000
*Calculation:
Contract price - Cost incurred to date
1590000 - 1067000
523000
*The job/contract was completed in 2019 so the profit of previous two years is NIL under completed contract method.

Related Solutions

During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date       $393,900       $760,380       $1,059,000 Estimated costs to complete       616,100       341,620       –0– Billings to date       299,000       905,000       1,610,000 Collections to date       268,000       818,000       1,421,000    Compute the amount of gross profit to be recognized each year, assuming the...
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job...
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $404,000 $853,160 $1,073,000 Estimated costs to complete 606,000 254,840 –0– Billings to date 301,000 904,000 1,580,000 Collections to date 271,000 812,000 1,418,000 Instructions: Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT