In: Accounting
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.
2017 |
2018 |
2019 |
||||
Costs incurred to date |
$404,000 |
$853,160 |
$1,073,000 |
|||
Estimated costs to complete |
606,000 |
254,840 |
–0– |
|||
Billings to date |
301,000 |
904,000 |
1,580,000 |
|||
Collections to date |
271,000 |
812,000 |
1,418,000 |
Instructions:
Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
Prepare all necessary journal entries for 2017, 2018, and 2019.
Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.