Question

In: Accounting

During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...

During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$410,000 $901,180 $1,067,000

Estimated costs to complete

590,000 197,820 –0–

Billings to date

297,000 903,000 1,590,000

Collections to date

271,000 805,000 1,434,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amount

Gross profit recognized in 2021

$enter a dollar amount

Gross profit recognized in 2022

$enter a dollar amount

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

(To record cost of construction.)

enter an account title to record progress billings

enter a debit amount

enter a credit amount

enter an account title to record progress billings

enter a debit amount

enter a credit amount

(To record progress billings.)

enter an account title to record collections

enter a debit amount

enter a credit amount

enter an account title to record collections

enter a debit amount

enter a credit amount

(To record collections.)

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

(To recognize revenue.)

Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2020

2021

2022

Gross profit

$enter a dollar amount

$enter a dollar amount

$enter a dollar amount

Solutions

Expert Solution

ANSWER

1)

Contract Price = $ 1,590,000.00
2020 2021 2022
a) Cost incurred (cumulative) $       410,000.00 $      901,180.00 $   1,067,000.00
b) Estimated cost to complete $       590,000.00 $      197,820.00 -
c) Estimated total cost (a+b) $   1,000,000.00 $ 1,099,000.00 $   1,067,000.00
d) % of completion (a/c) 41% 82% 100%
For the schedule above, revenues under the percentage of completion method:
Year % of completion Contract Price Revenues Previously Recognized Net Revenue
2020 41% $   1,590,000.00 $      651,900.00 $                       -   $      651,900.00
2021 82% $   1,590,000.00 $   1,303,800.00 $      651,900.00 $      651,900.00
2022 100% $   1,590,000.00 $   1,590,000.00 $ 1,303,800.00 $      286,200.00
Total Net Revenue $ 1,590,000.00
Costs under the percentage of completion method:
Year Cost Previously Recognized Net cost
2020 $      410,000.00 $                        -   $      410,000.00
2021 $      901,180.00 $       410,000.00 $      491,180.00
2022 $ 1,067,000.00 $       901,180.00 $      165,820.00
Total net cost $ 1,067,000.00
Gross Profit Recognization:
Year Net Revenue Net Cost Gross Profit
2020 $ 651,900.00 $       410,000.00 $      241,900.00
2021 $ 651,900.00 $       491,180.00 $      160,720.00
2022 $ 286,200.00 $       165,820.00 $      120,380.00

-----------------

2)

Date Account Titles Debit Credit
2018 Construction in Progress 491180
Materials, cash ,Payables 491180
[901,180-410,000]
2018 Accounts Receivable 606000
Billing on Construction in Progress 606000
[903,000-297,000]
2018 Cash
Accounts Receivable 534000
[805,000-271,000] 534000
2018 Construction Expense 491180
Construction in Progress 160720
Revenue from Contract 651900

Workings:

1. Revenue to be recognized for 2017:

Estimated Costs =410000+590000 = 1,000,000

Percentage of completion = 410000/ 1000000 = 41%

Estimated Profit = 1,590,000 - 1,000,000 = 590,000

Revenue to be recognized in 2017 = 590,000 *41% = 241900

2. Revenue to be recognized in 2018:

Estimated Costs =901180+197820 = 1,099,000

Percentage of completion = 901180/ 1099000 = 82%

Estimated Profit = 1,590,000 - 1,099,000 = 491,000

Revenue to be recognized in 2018 = (491,000 *82%) - 241,900 = 402,620 -241,900 = 160,720

--------

WE ANSWERED 2 PARTS ONLY,IF YOU WANT 3rd  PART ,PLEASE REUPLOAD THAT ONE.

---------------------------------------------------------------------

DEAR STUDENT,
If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************


Related Solutions

During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Your answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $366,300 $831,440 $1,067,000 Estimated costs to complete 623,700 262,560 –0– Billings to date 297,000 894,000 1,590,000 Collections to date 270,000 816,000 1,417,000 a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit in 2017 Gross profit in 2018...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT