In: Accounting
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available.
2020 |
2021 |
2022 |
||||
---|---|---|---|---|---|---|
Costs incurred to date |
$424,200 | $885,330 | $1,060,000 | |||
Estimated costs to complete |
585,800 | 207,670 | –0– | |||
Billings to date |
299,000 | 908,000 | 1,590,000 | |||
Collections to date |
273,000 | 819,000 | 1,435,000 |
Part 1
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2020 |
$ |
|
---|---|---|
Gross profit recognized in 2021 |
$ |
|
Gross profit recognized in 2022 |
$ |
· Requirement asked
Requirement 1 |
|||
2020 |
2021 |
2022 |
|
Gross Profits (Loss) |
$243,600 |
$158,970 |
$127,430 |
--Working
Working |
2020 |
2021 |
2022 |
|
A |
Contract Price |
$1,590,000 |
$1,590,000 |
$1,590,000 |
B |
Cost Incurred to Date |
$424,200 |
$885,330 |
$1,060,000 |
C |
Estimated cost yet to be incurred to complete the contract |
$585,800 |
$207,670 |
$0 |
D = B+C |
Total Cost |
$1,010,000 |
$1,093,000 |
$1,060,000 |
E = (B/D) x 100 |
% of Completion |
42.00% |
81.00% |
100.00% |
F = A x E |
Revenue to date |
$667,800 |
$1,287,900 |
$1,590,000 |
G |
Revenue of Previous year |
$0 |
$667,800 |
$1,287,900 |
H = F - G |
Net Revenue this year |
$667,800 |
$620,100 |
$302,100 |
I (=B) |
Cost to date |
$424,200 |
$885,330 |
$1,060,000 |
J |
Cost to date of previous year |
$0 |
$424,200 |
$885,330 |
K = I - J |
Net Cost for the year |
$424,200 |
$461,130 |
$174,670 |
L = H - K |
Gross Profits |
$243,600 |
$158,970 |
$127,430 |