Question

In: Accounting

During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...

During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$424,200 $885,330 $1,060,000

Estimated costs to complete

585,800 207,670 –0–

Billings to date

299,000 908,000 1,590,000

Collections to date

273,000 819,000 1,435,000

Part 1

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$

Gross profit recognized in 2021

$

Gross profit recognized in 2022

$

Solutions

Expert Solution

· Requirement asked

Requirement 1

2020

2021

2022

Gross Profits (Loss)

$243,600

$158,970

$127,430

--Working

Working

2020

2021

2022

A

Contract Price

$1,590,000

$1,590,000

$1,590,000

B

Cost Incurred to Date

$424,200

$885,330

$1,060,000

C

Estimated cost yet to be incurred to complete the contract

$585,800

$207,670

$0

D = B+C

Total Cost

$1,010,000

$1,093,000

$1,060,000

E = (B/D) x 100

% of Completion

42.00%

81.00%

100.00%

F = A x E

Revenue to date

$667,800

$1,287,900

$1,590,000

G

Revenue of Previous year

$0

$667,800

$1,287,900

H = F - G

Net Revenue this year

$667,800

$620,100

$302,100

I (=B)

Cost to date

$424,200

$885,330

$1,060,000

J

Cost to date of previous year

$0

$424,200

$885,330

K = I - J

Net Cost for the year

$424,200

$461,130

$174,670

L = H - K

Gross Profits

$243,600

$158,970

$127,430


Related Solutions

During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...
During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $366,300 $831,440 $1,067,000 Estimated costs to complete 623,700 262,560 –0– Billings to date 297,000 894,000 1,590,000 Collections to date 270,000 816,000 1,417,000 a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit in 2017 Gross profit in 2018...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT