Question

In: Accounting

During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...

During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$405,900 $830,680 $1,074,000

Estimated costs to complete

584,100 262,320 –0–

Billings to date

302,000 898,000 1,600,000

Collections to date

272,000 818,000 1,420,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amount

Gross profit recognized in 2021

$enter a dollar amount

Gross profit recognized in 2022

$enter a dollar amount

  

  

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

(To record cost of construction.)

enter an account title to record progress billings

enter a debit amount

enter a credit amount

enter an account title to record progress billings

enter a debit amount

enter a credit amount

(To record progress billings.)

enter an account title to record collections

enter a debit amount

enter a credit amount

enter an account title to record collections

enter a debit amount

enter a credit amount

(To record collections.)

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

(To recognize revenue.)

  

  

Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2020

2021

2022

Gross profit

$enter a dollar amount

$enter a dollar amount

$enter a dollar amount

Solutions

Expert Solution

  • Percentage of completion method

Requirement 1

2020

2021

2022

Gross Profits (Loss)

$250,100

$135,220

$140,680

Working

2020

2021

2022

A

Contract Price

$1,600,000

$1,600,000

$1,600,000

B

Cost Incurred to Date

$405,900

$830,680

$1,074,000

C

Estimated cost yet to be incurred to complete the contract

$584,100

$262,320

$0

D = B+C

Total Cost

$990,000

$1,093,000

$1,074,000

E = (B/D) x 100

% of Completion

41.00%

76.00%

100.00%

F = A x E

Revenue to date

$656,000

$1,216,000

$1,600,000

G

Revenue of Previous year

$0

$656,000

$1,216,000

H = F - G

Net Revenue this year

$656,000

$560,000

$384,000

I (=B)

Cost to date

$405,900

$830,680

$1,074,000

J

Cost to date of previous year

$0

$405,900

$830,680

K = I - J

Net Cost for the year

$405,900

$424,780

$243,320

L = H - K

Gross Profits

$250,100

$135,220

$140,680

  • Journal entries

Date

Accounts title

Debit

Credit

2021

Construction in Progress

$424,780

   Materials, Cash, Payables

$424,780

(construction cost incurred)

2021

Accounts receivables

$596,000

Billing on Construction contracts

$596,000

(amount billed during the year)

2021

Cash

$546,000

Accounts receivables

$546,000

(cash received)

2021

Construction in Progress

$135,220

Cost of construction or Construction expense

$424,780

Revenue from Long Term contract

$560,000

(revenue recognised)

  • Completed contract method

Gross Profits in:
2020 = $ 0
2021 = $ 0
2020 = $ 1600000-1074000 = $ 526,000


Related Solutions

During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Your answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Skysong Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT