Question

In: Operations Management

When activity times are known with certainty, the critical path is defined as the set of...

When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition?

Solutions

Expert Solution

ANSWERS-

At the point when the time of a movement isn't known with sureness, the genuine span of every path in the undertaking is difficult to assess, the critical path cannot be resolved for this situation. The issue is when there is vulnerability in the planning of each assignment, the critical path decided can go out to not be the critical path because of wrong gauges of the time.

It is additionally regular for various activities to be a piece of the critical path when the sureness of the time of the assignments is obscure,

For instance, an undertaking that has 5 activities which are A, B, C, D, and E with the critical path as A-B-D. The time of the activities is questionable during the fulfillment of each errand, and the time for any action can will in general be longer than anticipated here.

Therefore, A-B-D can likewise go out to not be the critical path if the action C sets aside a more drawn out effort to finish prompting a path with the most noteworthy term.

PLEASE LIKE MY ANSWER PLEASE..


Related Solutions

Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
What activity and it's predecessors would be considered the critical path in the construction schedule of...
What activity and it's predecessors would be considered the critical path in the construction schedule of a two level 14, 000 seat Sports stadium?
Why might a person wish to be involved with a critical path activity? What are some...
Why might a person wish to be involved with a critical path activity? What are some of the reasons one might have for not wanting this type of association? Explain your rationale with an example.
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
Which network path is the critical path of this project?
Which network path is the critical path of this project?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
Assume activity A will actually take 5 weeks, what is the new critical path and new...
Assume activity A will actually take 5 weeks, what is the new critical path and new expected duration? (4 Marks
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
What is the critical path of the network?
What is the critical path of the network?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT