Question

In: Operations Management

Why might a person wish to be involved with a critical path activity? What are some...


Why might a person wish to be involved with a critical path activity? What are some of the reasons one might have for not wanting this type of association? Explain your rationale with an example.

Solutions

Expert Solution

A critical path activity has longest time associated with it. With a critical path, there is ample slack time which provides flexibility to the tasks and working is less stressful for an employee. For a beginner, the slack time gives opportunity to learn on the job while performing the tasks.It is a high visibility path, with important activities thereby offering the person a prominent position in th project.

The reason for not involving in critical path activity is the avoidnce of risk where a delay in critical path activity may hamper the project schedule, as there is no longer path than this. Some events like demand of an early closure of the project by the client need to crash the activities ( reduce the time) or fasttracking the project.

An example of working on a critical path activity is to take a peripheral route that is not busy in comparison to the regular busy route to reach the destination while you don't have much driving experience to avoid risk and still reach on time.


Related Solutions

What activity and it's predecessors would be considered the critical path in the construction schedule of...
What activity and it's predecessors would be considered the critical path in the construction schedule of a two level 14, 000 seat Sports stadium?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
Assume activity A will actually take 5 weeks, what is the new critical path and new...
Assume activity A will actually take 5 weeks, what is the new critical path and new expected duration? (4 Marks
What is the critical path of the network?
What is the critical path of the network?
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
When activity times are known with certainty, the critical path is defined as the set of...
When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition?
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Some entrepreneurs will not highlight critical risks in their written business plan. Why might this be...
Some entrepreneurs will not highlight critical risks in their written business plan. Why might this be a big mistake?
List 3 possible reasons why a person might not observe a reaction even when the activity...
List 3 possible reasons why a person might not observe a reaction even when the activity series indicates that it should. Please explain carefully. Thank you for your help.
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10