Question

In: Accounting

Assume activity A will actually take 5 weeks, what is the new critical path and new...

Assume activity A will actually take 5 weeks, what is the new critical path and new expected duration? (4 Marks

Solutions

Expert Solution

The critical path method is to avoid project delays by identifying the tasks that are critical for the project schedule. By establishing the duration of each activity on the critical path it helps to determine the project completion time. While problems in non-critical work may delay the project, any delays in activities on the critical path delay the project completion time by an equal amount unless corrective action are taken.

Activities

Before work on scheduling, to break down the project into individual activities. A second group of tasks depends on the completion of the first tasks, and subsequent tasks depend on particular predecessors. By dividing the project into separate activities in this way, establish a network of tasks including those at the beginning, those in the middle that depend on prerequisites and those at the end, with no successors. The network is made up of parallel sequences of tasks from each of the first activities to those at the end.

Duration

Once  broken down the project into discrete activities, it can assign a duration to each one. For activities you contract out to sub-contractors, such as installation or site preparation work, they can provide you with estimates of how long their work takes. For internal tasks, you have to assign enough employees and resources to get the duration you need. If you manufacture certain components yourself, your operations employees can tell you how long that takes. For externally ordered equipment, you can establish contractual delivery times.

Critical Path

When you examine the sequences of activities of the project schedule that shows the individual tasks and their duration, you can add the times on each sequence and get a total duration for that sequence. The sequence that takes the longest is the critical path. Besides having the longest total duration, the critical path activities follow each other immediately, without gaps. If one of the critical path activities takes longer than anticipated, the project is delayed as well.

Completion Time

When calculated the duration of the critical path, it can determine the completion time of the project. Adding the time it takes to complete the tasks on the critical path to the starting date gives you the completion date. You can maintain this date as long as you complete every critical activity within its projected duration.

At the same time, you have to monitor the other activities of the project for delays. If there is a substantial problem in one particular area, the task sequences affected may take longer. In some cases, one of these delayed sequences may become the one with the highest total duration and replace the original critical path. The project may suffer delays unless you can reschedule tasks and reassign resources to reduce the duration of some of the critical activities.


Related Solutions

5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
What activity and it's predecessors would be considered the critical path in the construction schedule of...
What activity and it's predecessors would be considered the critical path in the construction schedule of a two level 14, 000 seat Sports stadium?
Why might a person wish to be involved with a critical path activity? What are some...
Why might a person wish to be involved with a critical path activity? What are some of the reasons one might have for not wanting this type of association? Explain your rationale with an example.
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
What is the critical path of the network?
What is the critical path of the network?
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...
Find the critical path and critical time for the following business network: Activity Pre. Act. Duration A - 18 B A 25 C B 1 D C 14 E C 12 F E 1 G D 18 H E,G 3 I C 14 J F,I 16 K J 5 L J 25 M H 22 N K,L 13
When activity times are known with certainty, the critical path is defined as the set of...
When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition?
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
5) What is the path that a typical spermatogonium would take to fertilize an oocyte? Include...
5) What is the path that a typical spermatogonium would take to fertilize an oocyte? Include at least 4 structures for the male and at least 4 structures for the female. Name each step like you would give someone directions (College Drive, to Atlanta street, through downtown, to Highway 41…) (organs, openings, regions of the organ, etc) 8pts n
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT