Question

In: Mechanical Engineering

Find the critical path and critical time for the following business network: Activity Pre. Act. Duration...

Find the critical path and critical time for the following business network:
Activity Pre. Act. Duration
A - 18
B A 25
C B 1
D C 14
E C 12
F E 1
G D 18
H E,G 3
I C 14
J F,I 16
K J 5
L J 25
M H 22
N K,L 13

Solutions

Expert Solution

Dummy activity= an activity which is used to show logic dependance or relationship between of one activity over the other activity but does not consume any time or resources. It is represented by dotted....... Lines in network diagram.

Critical path= it is the maximum time consuming path from 1st event to last event in network diagram.

Time taken along the critical path is critical time or expected completion of project.

Answer - critical path A-B-C-I-J-L-N

critical time = 112


Related Solutions

For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 4 C A,B 3 D A,B 6 E A,B 2 F C,D,E 8 G C,D,E 5
about critical path of a project network is that, A. the critical path is the shortest...
about critical path of a project network is that, A. the critical path is the shortest of all paths through the network B. the critical path is the set of activities that has no slack time C. the critical path is that set of activities that has no positive slack time D. some networks may not have any critical path
Critical Path Network: a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities?
Critical Path Network:  a. Develop the critical path network. b. Show ES, EF, LS, LF, on the network. c. What are the critical path activities? d. What are the slack time of the activities? e. What is the completion time of the project? f. What are the expected times of the activities? g. What is the project variance? h. What is its standard deviation?
Which network path is the critical path of this project?
Which network path is the critical path of this project?
What is the critical path of the network?
What is the critical path of the network?
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?
Explain how the critical path of a network is identified? What are critical path activities and...
Explain how the critical path of a network is identified? What are critical path activities and why are they important?
Build the network and determine the critical path.
Build the network and determine the critical path.
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path...
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10 C None 10 D A,B 40 E C 10 F C,D 20 G E,F 10
1. What is the duration of the critical path? Please show me step by step on...
1. What is the duration of the critical path? Please show me step by step on how you were able to solve this. I WANT TO KNOW IN DETAILED STEPS ON HOW YOU DO THIS, I HAVE NO CLUE/HAVE KNOWLEDGE ABOUT THIS. Activity Duration Predecessor A 2 Start B 4 A,E C 6 A D 3 B,C E 7 Start F 2 E End - D,F
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT