Question

In: Finance

Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200...

Consider the following information:

Cash Flows ($)
Project C0 C1 C2 C3 C4
A –6,200 2,200 2,200 2,900 0
B –1,500 0 1,000 3,200 4,200
C –3,800 2,200 1,300 1,700 1,200

a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.)

Project Payback Period
A year(s)
B year(s)
C year(s)

b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you accept?

Project A, Project B, and Project C
None
Project A and Project C
Project B and Project C
Project A
Project C
Project B
Project A and Project B

c. If you use a cutoff period of three years, which projects would you accept?

Project A
Project B
Project A and Project C
Project A, Project B, and Project C
Project A and Project B
Project C
Project B and Project C

d. If the opportunity cost of capital is 12%, which projects have positive NPVs?

Project A and Project B
Project A and Project C
Project A
Project B
Project A, Project B, and Project C
Project C
Project B and Project C

e. “If a firm uses a single cutoff period for all projects, it is likely to accept too many short-lived projects.” True or false?

True
False

f-1. If the firm uses the discounted-payback rule, will it accept any negative-NPV projects?

Yes
No

f-2. Will it turn down positive-NPV projects?

Yes
No

Solutions

Expert Solution

a.

Project

Payback Period

A

2.62 Years

B

2.16 Years

C

2.18 Years

Explanation:

Payback Period = A +B/C

Where,

A = Last period with a negative cumulative cash flow

B = Absolute value of cumulative cash flow at the end of the period A

C = Total cash flow during the period after A

Project A

Project B

Project C

Year

Cash Flow

‘CUM Cash Flow

Cash Flow

‘CUM Cash Flow

Cash Flow

‘CUM Cash Flow

0

($6,200)

($6,200)

($1,500)

($1,500)

($3,800)

($3,800)

1

$2,200

($4,000)

$0

($1,500)

$2,200

($1,600)

2

$2,200

($1,800)

$1,000

($500)

$1,300

($300)

3

$2,900

$1,100

$3,200

$2,700

$1,700

$1,400

4

$0

$1,100

$4,200

$6,900

$1,200

$2,600

Payback period for Project A = 2 + $ 1,800/$ 2,900 = 2 + 0.6206896552 = 2.6206896552 or 2.62 years

Payback period for Project B = 2 + $ 500/$ 3,200 = 2 + 0.15625 = 2.15625 or 2.16 years

Payback period for Project C = 2 + $ 300/$ 1,700 = 2 + 0.1764705882 = 2.1764705882 or 2.18 years

b.

If cut-off period is of 2 years, none of the project is acceptable as all the projects have payback period more than 2 years.

c.

If cut-off period is of 3 years, all of the three projects are acceptable as all the projects have payback period less than 3 years. So Project A, Project B, Project C is acceptable.

d.

If opportunity cost of capital is 12 %, Project B and Project C have positive NPVs.

Explanation:

Project A

Project B

Project C

Year

PV Factor Computation

PV Factor @ 12 % (F)

Cash Flow

(CA)

PV (F x CA)

Cash Flow

(CB)

PV (F x CB)

Cash Flow (CC)

PV (F x CC)

0

1/(1+0.12)0

1

($6,200)

($6,200.00)

($1,500)

($1,500)

($3,800)

($3,800)

1

1/(1+0.12)1

0.892857142857143

$2,200

$1,964.2857

$0

$0

$2,200

$1,964

2

1/(1+0.12) 2

0.797193877551020

$2,200

$1,753.8265

$1,000

$797

$1,300

$1,036

3

1/(1+0.12)3

0.711780247813411

$2,900

$2,064.1627

$3,200

$2,278

$1,700

$1,210

4

1/(1+0.12)4

0.635518078404831

$0

$0.0000

$4,200

$2,669

$1,200

$763

NPV

($417.7250)

NPV

$4,244.0666

NPV

$1,173.2859

e.

“If a firm uses a single cutoff period for all projects, it is likely to accept too many short-lived Projects.”

True.

f-1.

No, the firm will not accept any project with negative NPV. Discounted payback period cannot be computed for such negative NPV projects.

f-2.

The firm may turn-down positive NPV project, if discounted payback period is higher than cut-off period.


Related Solutions

Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300 2,300 2,000 0 B –1,600 0 1,000 3,300 4,300 C –3,700 2,300 1,000 1,800 1,300 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,000 2,000...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,000 2,000 2,000 2,700 0 B –1,300 0 1,000 3,000 4,000 C –4,000 1,000 2,600 1,500 1,000 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −8,450 6,200 21,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −8,450 6,200 21,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. (Do not round intermediate calculations. Round your answers to the nearest whole dollar amount.) NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT