Question

In: Finance

Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...

Consider the following projects:

Cash Flows ($)
Project C0 C1 C2 C3 C4 C5
A −2,500 2,500 0 0 0 0
B −5,000 2,500 2,500 5,500 2,500 2,500
C −6,250 2,500 2,500 0 2,500 2,500

a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV?

Positive NPV project(s)

Project A
Project B
Project C
Projects A and B
Projects A and C
Projects B and C
Projects A, B, and C
No project

b. Calculate the payback period for each project: (Round your answers to 2 decimal places. If a project never pays back, enter "0".)

  Project A year(s)
  Project B year(s)
  Project C year(s)

c. Which project(s) would a firm using the payback rule accept if the cutoff period were three years?

Project(s) accepted                  (Click to select)Project AProject BProject CProjects A and BProjects A and CProjects B and CProjects A, B, and CNo project

d. Calculate the discounted payback for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places. If a project never pays back, enter "0".)

Project A year(s)
Project B year(s)
Project C year(s)

e. Which project(s) would a firm using the discounted payback rule accept if the cutoff period were three years?

Project(s) accepted                (Click to select)Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project

Solutions

Expert Solution

Part a:
Project B and project C have positive NPV.

9% shown in the NPV formula (in excel) is the cost of capital.

Part b:

Payback period for project A:

Cash flows for project A:

Net cash flow:
C0:-$2,500
C1:$2,500
C2:0
C3:0
C4:0
C5:0

Cumulative net cash flow:
C0:-$2,500
C1:$2,500-$2,500=$0
C2:0
C3:0
C4:0
C5:0

Payback Period=Full years until recovery+(Unrecovered cost at the beginning of last year)/(Cash flow during the last year)

Payback Period=1+0=1 years

Cash flow for project B:
Project B
C0:-$5,000
C1:$2,500
C2:$2,500
C3:$5,500
C4:$2,500
C5:$2,500

Cumulative net cash flow:
C0:-$5,000
C1:$2,500-$5,000=-$2,500
C2:$2,500-$2,500=$0
C3:$5,500
C4:$2,500
C5:$2,500
Payback Period=2

Cash flow for project C:
C0:-$6,250
C1:$2,500
C2:$2,500
C3:$0
C4:$2,500
C5:$2,500


Cumulative cash flow for project C
C0:-$6,250
C1:$2,500-$6,250=-$3750
C2:$2,500-$3750=-$1250
C3:$0-$1250=-$1250
C4:$2,500-$1250=$1250
C5:$2,500

Payback period=3+$1250/$2,500=3.5 years

Part c:
The firm would accept project A and project B if the cutoff payback period were three years.

Part d:

Discounted payback period for project A at a cost of capital of 9%:

Cash flows for project A:
Net cash flow:
C0:-$2,500
C1:$2,500
C2:0
C3:0
C4:0
C5:0

Discounted net cash flow:
C0:-$2,500
C1:$2,500/(1+9%)^1=$2,500/(1.09)^1=$2293.577982
C2:0
C3:0
C4:0
C5:0

Cumulative discounted net cash flow:
C0:-$2,500
C1:$2293.577982-$2,500=$-206.422018
C2:0
C3:0
C4:0
C5:0

Payback period=0

Cash flow for project B:
Project B
C0:-$5,000
C1:$2,500
C2:$2,500
C3:$5,500
C4:$2,500
C5:$2,500

Discounted net cash flow:
Project B
C0:-$5,000
C1:$2,500/(1+9%)=$2,500/(1.09)^1=$2293.577982
C2:$2,500/(1+9%)^2=$2,500/(1.09)^2=$2104.199983
C3:$5,500/(1+9%)^3=$5,500/(1.09)^3=$4247.00914
C4:$2,500/(1+9%)^4
C5:$2,500/(1+9%)^5

Cumulative discounted net cash flow:
C0:-$5,000
C1:$2293.577982-$5,000=-$2706.422018
C2:$2104.199983-$2706.422018=-$602.222035
C3:$4247.00914-$602.222035=$3644.787105

Payback Period=Full years until recovery+(Unrecovered cost at the beginning of last year)/(Cash flow during the last year)
=2+$602.222035/$4247.00914=2+0.141799091 or 2.14 years (Rounded to 2 decimal places)

Cash flow for project C:
C0:-$6,250
C1:$2,500
C2:$2,500
C3:$0
C4:$2,500
C5:$2,500


Discounted cash flow for project C at a cost of capital of 9%:
C0:-$6,250
C1:$2,500/(1+9%)^1=$2,500/(1.09)^1=$2293.577982
C2:$2,500/(1+9%)^2=$2,500/(1.09)^2=$2104.199983
C3:$0/(1+9%)^3=$0
C4:$2,500/(1+9%)^4=$2,500/(1.09)^4=$1771.063028
C5:$2,500/(1+9%)^5=$2,500/(1.09)^5=$1624.828466

Cumulative discounted net cash flow:

C0:-$6,250
C1:$2293.577982-$6,250=-$3956.422018
C2:$2104.199983-$3956.422018=-$1852.222035
C3:$0-$1852.222035=-$1852.222035
C4:$1771.063028-$1852.222035=-$81.159007
C5:$1624.828466-$81.159007=$1543.669459
Payback Period=Full years until recovery+(Unrecovered cost at the beginning of last year)/(Cash flow during the last year)
=4+$81.159007/$1624.828466=4+0.049949277=4.049949277 or 4.05 Years (Rounded to 2 decimal places)

Part e:
Only project B can be selected as the discounted payback period is less than 3 years and the whole amount is paid back.


Related Solutions

Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300 2,300 2,000 0 B –1,600 0 1,000 3,300 4,300 C –3,700 2,300 1,000 1,800 1,300 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200 2,200 2,900 0 B –1,500 0 1,000 3,200 4,200 C –3,800 2,200 1,300 1,700 1,200 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum or minimum value? What values of Ci correspond to the minimum value of U? What values of Ci correspond to the maximum value of U? Do these values of Ci make sense from an economic standpoint? Now let us connect the idea of economic utility to actual dollar values. To keep the values more manageable, we will use household income rather than the entire...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum or minimum value? What values of Ci correspond to the minimum value of U? What values of Ci correspond to the maximum value of U? Do these values of Ci make sense from an economic standpoint? Now let us connect the idea of economic utility to actual dollar values. To keep the values more manageable, we will use household income rather than the entire...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT