Question

In: Finance

Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...

Consider the following projects:

Cash Flows ($)
Project C0 C1 C2 C3 C4 C5
A −2,800 2,800 0 0 0 0
B −5,600 2,800 2,800 5,800 2,800 2,800
C −7,000 2,800 2,500 0 2,800 2,800

  1. If the opportunity cost of capital is 12%, which project(s) have a positive NPV?

    Positive NPV Projects
  2. Calculate the payback period for each project.

    Project A years
    Project B    years
    Project C    years
  3. Which project(s) would a firm using the payback rule accept if the cutoff period is three years?

    Project accepted   
  4. Calculate the discounted payback period for each project.

    Project A    years
    Project B    years
    Project C years
  5. Which project(s) would a firm using the discounted payback rule accept if the cutoff period is three years?

    Project accepted

Solutions

Expert Solution

a) Calculation of NPV

- Project A

Year Cashflow PVF@12% Cashflow*PVF
0                (2,800) 1 -2800.00
1                  2,800 0.8929 2500.00

NPV = PV of Inflows - PV of OUtflows

= 2500-2800

= -300

- Project B

Year Cashflow PVF@12% Cashflow*PVF
0                (5,600) 1 -5600.00
1                  2,800 0.8929 2500.00
2                  2,800 0.7972 2232.14
3                  5,800 0.7118 4128.33
4                  2,800 0.6355 1779.45
5                  2,800 0.5674 1588.80

NPV = PV of Inflows - PV of OUtflows

= (2500+2232.14+4128.33+1779.45+1588.80)-5600

= 12228.71-5600

= 6628.71

- Project C

Year Cashflow PVF@12% Cashflow*PVF
0                (7,000) 1 -7000.00
1                  2,800 0.8929 2500.00
2                  2,500 0.7972 1992.98
3                         -   0.7118 0.00
4                  2,800 0.6355 1779.45
5                  2,800 0.5674 1588.80

NPV = PV of Inflows - PV of OUtflows

= (2500+1992.98+0+1779.45+1588.8)-7000

= 7861.23-7000

=  861.23

So both B and C has positive NPV

b) Calculate the payback period & Discounted Payback Period for each project.

- Project A

Year 0 1
Cashflow(in $)               (2,800)                 2,800
Cumulative Cashflow(in $)               (2,800)                        -  

Payback Period = A + (B/C)

where

A -  last time period where the cumulative cash flow was negative = 0

B - absolute value of the CCF at the end of that period A = 2800

C - value of the CF in the next period after A = 2800

Payback Period = 0+2800/2800

= 1 year

Year 0 1
Cashflow(in $)               (2,800)                 2,800
PVF @12%                          1                 0.893
Discounted Cashflow (Cash flow * PVF)               (2,800)                 2,500
Cumulative Cashflow(in $)               (2,800)                  (300)

Discounted Payback Period = not ascertainable

- Project B

Year 0 1 2 3 4 5
Cashflow(in $)               (5,600)                 2,800                       2,800                   5,800                   2,800                   2,800
Cumulative Cashflow(in $)               (5,600)              (2,800)                              -                     5,800                   8,600                 11,400

Payback Period = 1+2800/2800

= 2 years

Year 0 1 2 3 4 5
Cashflow(in $)               (5,600)                 2,800                       2,800                   5,800                   2,800                   2,800
PVF @12%                          1                 0.893                       0.797                   0.712                   0.636                   0.567
Discounted Cashflow (Cash flow * PVF)               (5,600)                 2,500                       2,232                   4,128                   1,779                   1,589
Cumulative Cashflow(in $)               (5,600)              (3,100)                        (868)                   3,260                   5,040                   6,629

Discounted Payback Period = 2+868/4128

= 2.21 years

- Project C

Year 0 1 2 3 4 5
Cashflow(in $)               (7,000)                 2,800                       2,500                          -                     2,800                   2,800
Cumulative Cashflow(in $)               (7,000)              (4,200)                     (1,700)                 (1,700)                   1,100                   3,900

Payback Period = 3+1700/2800

= 3.61 years

Year 0 1 2 3 4 5
Cashflow(in $)               (7,000)                 2,800                       2,500                          -                     2,800                   2,800
PVF @12%                          1                 0.893                       0.797                   0.712                   0.636                   0.567
Discounted Cashflow (Cash flow * PVF)               (7,000)                 2,500                       1,993                          -                     1,779                   1,589
Cumulative Cashflow(in $)               (7,000)              (4,500)                     (2,507)                 (2,507)                     (728)                       861

Discounted Payback Period = 4+728/1589

= 4.46 years

Based on payback period, except C can be accepted and based on discounted payback B can be accepted.


Related Solutions

Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300 2,300 2,000 0 B –1,600 0 1,000 3,300 4,300 C –3,700 2,300 1,000 1,800 1,300 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200 2,200 2,900 0 B –1,500 0 1,000 3,200 4,200 C –3,800 2,200 1,300 1,700 1,200 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,000 2,000...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,000 2,000 2,000 2,700 0 B –1,300 0 1,000 3,000 4,000 C –4,000 1,000 2,600 1,500 1,000 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum or minimum value? What values of Ci correspond to the minimum value of U? What values of Ci correspond to the maximum value of U? Do these values of Ci make sense from an economic standpoint? Now let us connect the idea of economic utility to actual dollar values. To keep the values more manageable, we will use household income rather than the entire...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum...
U(C1, C2, C3, C4, C5) = C1∙C2∙C3∙C4∙C5 As a mathematical function, does U have a maximum or minimum value? What values of Ci correspond to the minimum value of U? What values of Ci correspond to the maximum value of U? Do these values of Ci make sense from an economic standpoint? Now let us connect the idea of economic utility to actual dollar values. To keep the values more manageable, we will use household income rather than the entire...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT