In: Finance
Consider the following information:
Cash Flows ($) Project C0 C1 C2 C3 C4
A –6,300 2,300 2,300 2,000 0
B –1,600 0 1,000 3,300 4,300
C –3,700 2,300 1,000 1,800 1,300
a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.)
Project Payback Period
A year(s)
B year(s)
C year(s)
b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you accept?
Project A and Project B
Project A
None
Project A, Project B, and Project C
Project A and Project C
Project C
Project B and Project C
Project B
c. If you use a cutoff period of three years, which projects would you accept?
Project B and Project C
Project A
Project A and Project B
Project B
Project C
Project A and Project C
Project A, Project B, and Project C
d. If the opportunity cost of capital is 9%, which projects have positive NPVs?
Project A and Project B
Project A and Project C
Project B
Project C
Project A, Project B, and Project C
Project B and Project C
Project A
e. “If a firm uses a single cutoff period for all projects, it is likely to accept too many short-lived projects.” True or false?
True
False
f-1. If the firm uses the discounted-payback rule, will it accept any negative-NPV projects?
Yes
No
f-2. Will it turn down positive-NPV projects?
Yes
No
a
Project A | ||
Year | Cash flow stream | Cumulative cash flow |
0 | -6300 | -6300 |
1 | 2300 | -4000 |
2 | 2300 | -1700 |
3 | 2000 | 300 |
4 | 0 | 300 |
Payback period is the time by which undiscounted cashflow cover the intial investment outlay |
this is happening between year 2 and 3 |
therefore by interpolation payback period = 2 + (0-(-1700))/(300-(-1700)) |
2.85 Years |
Project B | ||
Year | Cash flow stream | Cumulative cash flow |
0 | -1600 | -1600 |
1 | 0 | -1600 |
2 | 1000 | -600 |
3 | 3300 | 2700 |
4 | 4300 | 7000 |
Payback period is the time by which undiscounted cashflow cover the intial investment outlay |
this is happening between year 2 and 3 |
therefore by interpolation payback period = 2 + (0-(-600))/(2700-(-600)) |
2.18 Years |
Project C | ||
Year | Cash flow stream | Cumulative cash flow |
0 | -3700 | -3700 |
1 | 2300 | -1400 |
2 | 1000 | -400 |
3 | 1800 | 1400 |
4 | 1300 | 2700 |
Payback period is the time by which undiscounted cashflow cover the intial investment outlay |
this is happening between year 2 and 3 |
therefore by interpolation payback period = 2 + (0-(-400))/(1400-(-400)) |
2.22 Years |
b
none, all have payback period above cut off of 2 years
c
Project A, B & C
d
Project A | |||||
Discount rate | 9.000% | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -6300 | 2300 | 2300 | 2000 | 0 |
Discounting factor | 1.000 | 1.090 | 1.188 | 1.295 | 1.412 |
Discounted cash flows project | -6300.000 | 2110.092 | 1935.864 | 1544.367 | 0.000 |
NPV = Sum of discounted cash flows | |||||
NPV Project A = | -709.68 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project B | |||||
Discount rate | 9.000% | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1600 | 0 | 1000 | 3300 | 4300 |
Discounting factor | 1.000 | 1.090 | 1.188 | 1.295 | 1.412 |
Discounted cash flows project | -1600.000 | 0.000 | 841.680 | 2548.205 | 3046.228 |
NPV = Sum of discounted cash flows | |||||
NPV Project B = | 4836.11 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project C | |||||
Discount rate | 9.000% | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -3700 | 2300 | 1000 | 1800 | 1300 |
Discounting factor | 1.000 | 1.090 | 1.188 | 1.295 | 1.412 |
Discounted cash flows project | -3700.000 | 2110.092 | 841.680 | 1389.930 | 920.953 |
NPV = Sum of discounted cash flows | |||||
NPV Project C = | 1562.65 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project B & C as NPV is positive
Please ask remaining parts separately