Question

In: Finance

Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300...

Consider the following information:

Cash Flows ($) Project C0 C1 C2 C3 C4

A –6,300 2,300 2,300 2,000 0

B –1,600 0 1,000 3,300 4,300

C –3,700 2,300 1,000 1,800 1,300

a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.)

Project Payback Period

A year(s)

B year(s)

C year(s)

b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you accept?

Project A and Project B

Project A

None

Project A, Project B, and Project C

Project A and Project C

Project C

Project B and Project C

Project B

c. If you use a cutoff period of three years, which projects would you accept?

Project B and Project C

Project A

Project A and Project B

Project B

Project C

Project A and Project C

Project A, Project B, and Project C

d. If the opportunity cost of capital is 9%, which projects have positive NPVs?

Project A and Project B

Project A and Project C

Project B

Project C

Project A, Project B, and Project C

Project B and Project C

Project A

e. “If a firm uses a single cutoff period for all projects, it is likely to accept too many short-lived projects.” True or false?

True

False

f-1. If the firm uses the discounted-payback rule, will it accept any negative-NPV projects?

Yes

No

f-2. Will it turn down positive-NPV projects?

Yes

No

Solutions

Expert Solution

a

Project A
Year Cash flow stream Cumulative cash flow
0 -6300 -6300
1 2300 -4000
2 2300 -1700
3 2000 300
4 0 300
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-1700))/(300-(-1700))
2.85 Years
Project B
Year Cash flow stream Cumulative cash flow
0 -1600 -1600
1 0 -1600
2 1000 -600
3 3300 2700
4 4300 7000
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-600))/(2700-(-600))
2.18 Years
Project C
Year Cash flow stream Cumulative cash flow
0 -3700 -3700
1 2300 -1400
2 1000 -400
3 1800 1400
4 1300 2700
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-400))/(1400-(-400))
2.22 Years

b

none, all have payback period above cut off of 2 years

c

Project A, B & C

d

Project A
Discount rate 9.000%
Year 0 1 2 3 4
Cash flow stream -6300 2300 2300 2000 0
Discounting factor 1.000 1.090 1.188 1.295 1.412
Discounted cash flows project -6300.000 2110.092 1935.864 1544.367 0.000
NPV = Sum of discounted cash flows
NPV Project A = -709.68
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 9.000%
Year 0 1 2 3 4
Cash flow stream -1600 0 1000 3300 4300
Discounting factor 1.000 1.090 1.188 1.295 1.412
Discounted cash flows project -1600.000 0.000 841.680 2548.205 3046.228
NPV = Sum of discounted cash flows
NPV Project B = 4836.11
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project C
Discount rate 9.000%
Year 0 1 2 3 4
Cash flow stream -3700 2300 1000 1800 1300
Discounting factor 1.000 1.090 1.188 1.295 1.412
Discounted cash flows project -3700.000 2110.092 841.680 1389.930 920.953
NPV = Sum of discounted cash flows
NPV Project C = 1562.65
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

Project B & C as NPV is positive

Please ask remaining parts separately


Related Solutions

Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200 2,200 2,900 0 B –1,500 0 1,000 3,200 4,200 C –3,800 2,200 1,300 1,700 1,200 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT