Question

In: Finance

Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...

Consider the following cash flows:

C0 / C1/ C2 /C3 /C4

? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46

a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)

2.5%

2.9%

14.3%

33.9%

40.0%

Solutions

Expert Solution

If we discount Cashflows @ IRR NPV = 0
So if NPV is 0 for a given IRR ;it is the IRR of project
(i) Year CF PV Factor @ r PV of cash flows
0 -27 1 -27
1 24 0.97561 23.41463
2 24 0.951814 22.84355
3 24 0.928599 22.28639
4 46 0.905951 41.67373
NPV = 83.2183
(NO)
(ii) Year CF PV Factor @ r PV of cash flows
0 -27 1 -27
1 24 0.971817 23.32362
2 24 0.944429 22.66629
3 24 0.917812 22.0275
4 46 0.891946 41.02951
NPV = 82.04691
(NO)
(iii) Year CF PV Factor @ r PV of cash flows
0 -27 1 -27
1 24 0.874891 20.99738
2 24 0.765434 18.37041
3 24 0.669671 16.0721
4 46 0.585889 26.95088
NPV = 55.39076
(NO)
(iv) Year CF PV Factor @ r PV of cash flows
0 -27 1 -27
1 24 0.746826 17.92382
2 24 0.557749 13.38598
3 24 0.416541 9.996996
4 46 0.311084 14.30986
NPV = 28.61666
(NO)
(v) Year CF PV Factor @ r PV of cash flows
0 -27 1 -27
1 24 0.714286 17.14286
2 24 0.510204 12.2449
3 24 0.364431 8.746356
4 46 0.260308 11.97418
NPV = 23.10829
(NO)
Lets Make NPV profile and find out the IRR of This project.
Irr NPV
0% 91.00
10% 64.10
20% 45.74
30% 32.69
40% 23.11
50% 15.86
60% 10.25
70% 5.81
80% 2.24
90% -0.69
100% -3.13
120% -6.91
140% -9.71
160% -11.85
There is only 1 IRR of the project it is around 85%

Related Solutions

Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,300 2,300 2,300 2,000 0 B –1,600 0 1,000 3,300 4,300 C –3,700 2,300 1,000 1,800 1,300 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200...
Consider the following information: Cash Flows ($) Project C0 C1 C2 C3 C4 A –6,200 2,200 2,200 2,900 0 B –1,500 0 1,000 3,200 4,200 C –3,800 2,200 1,300 1,700 1,200 a. What is the payback period on each of the above projects? (Round your answers to 2 decimal places.) Project Payback Period A year(s) B year(s) C year(s) b. Given that you wish to use the payback rule with a cutoff period of two years, which projects would you...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT