Question

In: Operations Management

activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C...

activity follows optimistic duration most likely direction pessimistic duration
A - 4 6 14
B A,C 3 4 5
C - 3 5 13
D A,E 12 18 24
E - 8 10 18
F A,E 4 6 8
G B,F 7 8 9
H G 10 12 14
I G 5 6 7
J D,I 5 7 9

Calculate the probability of completing the project between 35 and 40 weeks? [4 pts]
  
f Answer the project manager’s question: “I want to tell the client that there is a 10.03% chance the project will take longer than X weeks - what figure should I give them (i.e. find X)?” [4]

Solutions

Expert Solution

We need to calcuate the project duration using the critical path method / PERT. The expected duration is

E = (optimistic + 4*most likely + pessimistic) / 6

Variance = ((pessimistic - optimistic)/6)^2

The calculated values are shown below

The exxpected duration is 38 weeks and the variance for this duration is 3.88 weeks.

The z value for less 35 weeks = (35-38)/sqrt(3.88) = -1.52

The corresponding probability = 0.063

The z value for less than 40 weeks = (40-38)/sqrt(3.88) = 1.01

The corresponding probability = 0.845

The range between 35 to 40 weeks = 0.845-0.063 = 0.782

The probability of finishing between 35 and 40 weeks is 0.782

A 10.03% probability means that the z value is -1.27

This means -1.27 = (X-38)/sqrt(3.88) or X = 35.47 weeks


Related Solutions

Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B...
Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E C 6 9 24 F E 1 7 13 G C 4 10 28 H D,F 2 5 14 I G,F 5 8 17 J H,I 2 5 8 Determine the expected completion time for each activity. Construct the AON network for the activities of this contract and determine the critical path for the project.
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5...
Times (days) Activity Optimistic Most Likely Pessimistic Preceding Tasks 1 8 10 13 - 2 5 6 8 - 3 13 15 21 2 4 10 12 14 1,3 5 11 20 30 4 6 4 5 8 5 7 2 3 4 5 8 4 6 10 7 9 2 3 4 8,6 Draw the AON Network Diagram Compute the expected activity time Using the expected activity times, compute the early start, early finish, late start, late finish, and...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)...
Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6 9 none B 3 5 7 A C 4 7 12 A D 4 8 10 B E 5 10 16 C F 3 4 5 D, E G 3 6 8 D, E H 5 6 10 F I 5 8 11 G J 3 3 3 H, I A.)Using the information given, construct a network diagram using AON notation....
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have...
QUESTION 7    [18 MARKS) In the following table, optimistic, most likely and pessimistic time estimates have been given for each activity for a project. Task Immediate Predecessor(s) Time (days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 5 7 12 B None 8 8 8 C A 2 6 10 D A,B 12 14 19 E C,D 6 6 12 F B,E 3 12 18 G F 6 8 10 Construct an activity on node network diagram for this...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4...
Activity Duration(hours) Depends on : Numbers of workers A 5 4 B 2 2 C 4 5 D 6 A,B 1 E 2 A,B,C 6 F 2 B,C 3 G 5 F 4 H 8 E,F 2 I 3 G 7 J 5 H,I 3 K 6 J 4 L 8 I 3 Calculate a lower bound for the number of workers required to complete the project in 26 days. [2 ????] Use the precedence table to draw an activity-on-arc...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate)...
Use the following table to answer questions. Activity a (Optimistic Time Estimate) m (Most Likely Estimate) b (Pessimistic Time Estimate) A 3 8 13 B 3 6 9 C 4 6 8 D 7 9 11 E 5 7 12 What is the expected time for activity c? 5.167 3 4.28 6 What is the variance for activity A? 3.33 2.77 5.31 .674 Assume there is one critical path of (A, B, C, E) what is the project variance? 5.583...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D...
Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4 Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help). I would really appreciate excel screenshots!
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT