Question

In: Finance

Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5...

Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and its expected cash flows would be $10,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer.

a. Project L, since the NPVL > NPVS.

b. Both Projects S and L, since both projects have NPV's > 0.

c. Both Projects S and L, since both projects have IRR's > 0.

d. Project S, since the NPVS > NPVL.

e. Neither Project S nor L, since each project's NPV < 0.

Solutions

Expert Solution

Answer - Option (a) Project L, since the NPVL > NPVS.

Calculation of NPV as follows :-

NPV of Project S = Present Value of cash Inflow - Present Value of cash Outflow

Present Value of cash Inflow = (4000 / 1.12)1 + (4000 / 1.12)2+ (4000 / 1.12)3+ (4000 / 1.12)4+ (4000 / 1.12)5

Present Value of cash Inflow = $3571.4286 + $3188.7755 + $2847.12099 + $2542.0723 + $2269.7074

Present Value of cash Inflow = $14419.10481

Present Value of cash Outflow = $17000

NPV of Project S = $14419.10481 - $17000

NPV of Project S = (-) $2580.895

NPV of Project L = Present Value of cash Inflow - Present Value of cash Outflow

Present Value of cash Inflow = (10200 / 1.12)1 + (10200 / 1.12)2+ (10200 / 1.12)3+ (10200 / 1.12)4+ (10200 / 1.12)5

Present Value of cash Inflow = $9107.142857 + $8131.377551 + $7260.158528 + $6482.2844 + $5787.753928

Present Value of cash Inflow = $36768.71726

Present Value of cash Outflow = $25000

NPV of project L = $36768.71726 - $25000

NPV of project L = $11768.717


Related Solutions

Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project S, since the NPVS > NPVL. c....
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Both Projects S and L, since both projects have NPV's > 0. c....
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $43,500 and its expected cash flows would be $11,750 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0. c....
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for...
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $41,000 and its expected cash flows would be $8,550 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project L, since the NPVL > NPVS. c. Project S, since the...
Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $15,000 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Neither S or L, since each project's NPV < 0. III. Both...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $42,500 and its expected cash flows would be $8,900 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project L, since the NPVL > NPVS. c....
Project X is expected to generate cash flows of $5,000 per year for 5 years and...
Project X is expected to generate cash flows of $5,000 per year for 5 years and its initial cost is $17,000. Project Y is mutually exclusive to Project S. Project Y costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, what is the IRR of the better project? a)12.00% b)14.85% c)13.65% d)14.05% e)14.40%
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT