In: Finance
Both the projects have same duration.
Since these projects are mutually exclusive, we can select only one project.
NPV is better way of finding the worth of the project as it calculate the value that projects will deliver in terms of cash while IRR gives the rate at which NPV equals zero.
NPV of project S = $7620.62 Answer
NPV of project L = $ 3758,47 Answer
Since NPV of project S is higher than project L , you would recommend project S.
Option V is correct.
Because of above calculation other options will be ruled out.