Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5...

Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?

Select the correct answer.

a. Both Projects S and L, since both projects have IRR's > 0.
b. Both Projects S and L, since both projects have NPV's > 0.
c. Project S, since the NPVS > NPVL.
d. Project L, since the NPVL > NPVS.
e. Neither Project S nor L, since each project's NPV < 0.

Solutions

Expert Solution

NPV & IRR
Project S
Year Cash Flow DF for 16% Discounted Cash Flow FOR IRR 40% DF for 40% Discounted Cash Flow
0 -11000 1 $                    (11,000.00) 1 $                           (11,000.00)
1 6000 0.8621 $                         5,172.41 0.71429 $                               4,285.71
2 6000 0.7432 $                         4,458.98 0.51020 $                               3,061.22
3 6000 0.6407 $                         3,843.95 0.36443 $                               2,186.59
4 6000 0.5523 $                         3,313.75 0.26031 $                               1,561.85
5 6000 0.4761 $                         2,856.68 0.18593 $                               1,115.61
NPV $                         8,645.76 NPV $                               1,210.98
IRR =Ra + NPV @ Ra (Rb-Ra) Ra = Lower discount rate
            NPV @ Ra - NPV @ Rb Rb = higher discount rate
=0.16 + [ ((8645.76 X (.40 - .16)) / (8645.76 - 1210.98)
=0.16 + (1.162881 X (.40 - .16))
0.44
44%
Project L
Year Cash Flow DF for 16% Discounted Cash Flow FOR IRR 40% DF for 40% Discounted Cash Flow
0 -30500 1 $                    (30,500.00) 1 $                           (30,500.00)
1 14500 0.8621 $                       12,500.00 0.71429 $                             10,357.14
2 14500 0.7432 $                       10,775.86 0.51020 $                               7,397.96
3 14500 0.6407 $                         9,289.54 0.36443 $                               5,284.26
4 14500 0.5523 $                         8,008.22 0.26031 $                               3,774.47
5 14500 0.4761 $                         6,903.64 0.18593 $                               2,696.05
NPV $                       16,977.26 NPV $                                 (990.12)
IRR =Ra + NPV @ Ra (Rb-Ra) Ra = Lower discount rate
            NPV @ Ra - NPV @ Rb Rb = higher discount rate
=0.16 + [ ((16977.26 X (.40 - .16)) / (16977.26 - (-990.123))
=0.16 + (0.944 X (.40 - .16))
0.38
38%
Based on NPV Project L is recommended
Based on IRR Project S is recommended
The Best way to select the project is NPV so project L is recommended

Related Solutions

10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for...
10) Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $41,000 and its expected cash flows would be $8,550 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project L, since the NPVL > NPVS. c. Project S, since the...
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $43,500 and its expected cash flows would be $11,750 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0. c....
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $17,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and its expected cash flows would be $10,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Project S, since the NPVS > NPVL. c....
Project L costs $53,716.57, its expected cash inflows are $11,000 per year for 11 years, and...
Project L costs $53,716.57, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places. ___%
Project L costs $35,000, its expected cash inflows are $11,000 per year for 7 years, and...
Project L costs $35,000, its expected cash inflows are $11,000 per year for 7 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places. ___years
Project L costs $51,295.68, its expected cash inflows are $11,000 per year for 9 years, and...
Project L costs $51,295.68, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
Project K costs $50,000, its expected cash inflows are $11,000 per year for 11 years, and...
Project K costs $50,000, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 12%. What is the project's NPV? Round your answer to the nearest cent. Project K costs $50,000, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 12%. What is the project's NPV? Project K costs $68,499.16, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 13%. What is the...
Project L costs $45,414.75, its expected cash inflows are $11,000 per year for 8 years, and...
Project L costs $45,414.75, its expected cash inflows are $11,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places. ____% Project L costs $75,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places. ____ years Project L costs $40,000, its expected cash inflows are $9,000 per year for...
Project L costs $52,093.65, its expected cash inflows are $11,000 per year for 11 years, and...
Project L costs $52,093.65, its expected cash inflows are $11,000 per year for 11 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT