Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
NPV & IRR | |||||||
Project S | |||||||
Year | Cash Flow | DF for 16% | Discounted Cash Flow | FOR IRR 40% | DF for 40% | Discounted Cash Flow | |
0 | -11000 | 1 | $ (11,000.00) | 1 | $ (11,000.00) | ||
1 | 6000 | 0.8621 | $ 5,172.41 | 0.71429 | $ 4,285.71 | ||
2 | 6000 | 0.7432 | $ 4,458.98 | 0.51020 | $ 3,061.22 | ||
3 | 6000 | 0.6407 | $ 3,843.95 | 0.36443 | $ 2,186.59 | ||
4 | 6000 | 0.5523 | $ 3,313.75 | 0.26031 | $ 1,561.85 | ||
5 | 6000 | 0.4761 | $ 2,856.68 | 0.18593 | $ 1,115.61 | ||
NPV | $ 8,645.76 | NPV | $ 1,210.98 | ||||
IRR | =Ra + NPV @ Ra (Rb-Ra) | Ra = Lower discount rate | |||||
NPV @ Ra - NPV @ Rb | Rb = higher discount rate | ||||||
=0.16 + [ ((8645.76 X (.40 - .16)) / (8645.76 - 1210.98) | |||||||
=0.16 + (1.162881 X (.40 - .16)) | |||||||
0.44 | |||||||
44% | |||||||
Project L | |||||||
Year | Cash Flow | DF for 16% | Discounted Cash Flow | FOR IRR 40% | DF for 40% | Discounted Cash Flow | |
0 | -30500 | 1 | $ (30,500.00) | 1 | $ (30,500.00) | ||
1 | 14500 | 0.8621 | $ 12,500.00 | 0.71429 | $ 10,357.14 | ||
2 | 14500 | 0.7432 | $ 10,775.86 | 0.51020 | $ 7,397.96 | ||
3 | 14500 | 0.6407 | $ 9,289.54 | 0.36443 | $ 5,284.26 | ||
4 | 14500 | 0.5523 | $ 8,008.22 | 0.26031 | $ 3,774.47 | ||
5 | 14500 | 0.4761 | $ 6,903.64 | 0.18593 | $ 2,696.05 | ||
NPV | $ 16,977.26 | NPV | $ (990.12) | ||||
IRR | =Ra + NPV @ Ra (Rb-Ra) | Ra = Lower discount rate | |||||
NPV @ Ra - NPV @ Rb | Rb = higher discount rate | ||||||
=0.16 + [ ((16977.26 X (.40 - .16)) / (16977.26 - (-990.123)) | |||||||
=0.16 + (0.944 X (.40 - .16)) | |||||||
0.38 | |||||||
38% | |||||||
Based on NPV Project L is recommended | |||||||
Based on IRR Project S is recommended | |||||||
The Best way to select the project is NPV so project L is recommended |