Question

In: Finance

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) modified internal rate of return (MIRR). The firm’s required rate of return is 14 percent. If the projects are independent, which project (s) should be selected? If they are mutually exclusive projects, which project should be selected? Explain.

Solutions

Expert Solution

Calculation of NPV
Year Project P Project Q PV factor @ 14% Present values-P Present values-Q
0 (15,000)    (37,500) 1.000    (15,000)          (37,500)
1        4,500      11,100 0.877        3,947              9,737
2        4,500      11,100 0.769        3,463              8,541
3        4,500      11,100 0.675        3,037              7,492
4        4,500      11,100 0.592        2,664              6,572
5        4,500      11,100 0.519        2,337              5,765
Net Present Value           449                 607
Project Independed Select P & Q both as positive NPV
Project Mutual exclusive Select Q as this project gives highest NPV
Calculation of IRR
Year Project P PV factor @ 14% Present values PV factor @ 16% Present values
0 (15,000) 1.000    (15,000) 1.000    (15,000)
1        4,500 0.877        3,947 0.862        3,879
2        4,500 0.769        3,463 0.743        3,344
3        4,500 0.675        3,037 0.641        2,883
4        4,500 0.592        2,664 0.552        2,485
5        4,500 0.519        2,337 0.476        2,143
          449         (266)
IRR =Lower rate + Difference in rates*(NPV at lower rate)/(Lower rate NPV-Higher rate NPV)
IRR =14%+2%*(449/(449+266))
15.26%
Year Project Q PV factor @ 14% Present values PV factor @ 16% Present values
0    (37,500) 1.000    (37,500) 1.000    (37,500)
1      11,100 0.877        9,737 0.862        9,569
2      11,100 0.769        8,541 0.743        8,249
3      11,100 0.675        7,492 0.641        7,111
4      11,100 0.592        6,572 0.552        6,130
5      11,100 0.519        5,765 0.476        5,285
          607      (1,155)
IRR =Lower rate + Difference in rates*(NPV at lower rate)/(Lower rate NPV-Higher rate NPV)
IRR =14%+2%*(607/(607+1155))
14.69%
Project Independed Select P & Q both giving IRR more than 14%
Project Mutual exclusive Select P as this project gives highest IRR
Calculation of MIRR
Year Project P Future Value factor @ 14% Present values
1        4,500 1.689        7,600
2        4,500 1.482        6,667
3        4,500 1.300        5,848
4        4,500 1.140        5,130
5        4,500 1.000        4,500
FV of inflow     29,745
MIRR =[(FV of Inflow/Initial Outflow)^(1/n)]-1
MIRR =[(29745/15000)^(1/5)]-1
MIRR 14.67%
Year Project Q Future Value factor @ 14% Present values
1      11,100 1.689      18,747
2      11,100 1.482      16,445
3      11,100 1.300      14,426
4      11,100 1.140      12,654
5      11,100 1.000      11,100
FV of inflow     73,372
MIRR =[(FV of Inflow/Initial Outflow)^(1/n)]-1
MIRR =[(73372/37500)^(1/5)]-1
MIRR 14.37%
Project Independed Select P & Q both giving MIRR more than 14%
Project Mutual exclusive Select P as this project gives highest MIRR

Related Solutions

Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for...
Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to produce cash flows of $9,250 per year for five years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive?...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $4,000 per year for 5 years. Project L costs $21,000 and is expected to produce cash flows of $8,000 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, PIs, and Pay Back Period assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive?...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' PIs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to three decimal places. Project S:   Project L:  
Project L costs $50,000, its expected cash inflows are $15,000 per year for 11 years, and...
Project L costs $50,000, its expected cash inflows are $15,000 per year for 11 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
10-10. Project A has a cost of $22,000 and is expected to produce benefits (cash flows)...
10-10. Project A has a cost of $22,000 and is expected to produce benefits (cash flows) of $7,000 per year for 5 years. Project B costs $70,000 and is expected to produce cash flows of $20,000 per year for 5 years. Calculate the two projects' NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 10%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?
You are evaluating a project that is expected to produce cash flows of $5,000 each year...
You are evaluating a project that is expected to produce cash flows of $5,000 each year for the next 3 years and $7,000 each year for the following 3 years. The IRR of this 6-year project is 12%. If the firm’s WACC is 10%, what is the project’s NPV?
Problem 11-1 NPV Project K costs $50,000, its expected cash inflows are $15,000 per year for...
Problem 11-1 NPV Project K costs $50,000, its expected cash inflows are $15,000 per year for 12 years, and its WACC is 9%. What is the project's NPV? Round your answer to the nearest cent. $ Problem 11-2 IRR Project K costs $51,525.47, its expected cash inflows are $11,000 per year for 10 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places. % Problem 11-3 payback period Project K costs $65,000,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT